Engineer | Form: (06 ) 401963428 3/22/2019 | 1)Provide 48 hour notice of plugging MIRU via electronic Form 42.
2)Properly abandon flowlines as per Rule 1105. File electronic Form 42 once
abandonment complete. Within 30 days of an operator completing abandonment
requirements for an off-location flowline or crude oil transfer line the operator shall
submit a Flowline Report, Form 44.
3)Operator shall implement measures to control unnecessary and excessive venting, to protect the health and safety of the public, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public welfare.
4)Visually confirm returns to surface in 4.5" production casing as well as annulus between the 4.5" production casing and the 7" surface casing.
|