Skip to Main Content

COGIS DB

 
Facility TypeFacility ID/
API
Facility Name/
Number
Operator Name/
Number
StatusField Name/
Number
LocationLocation IDRelated Facilities
WELL05-073-06722MARY JANE
13-5
POLARIS PRODUCTION OPCO LLC
10793
SI
2/1/2025
BROKEN SPEAR
7567
LINCOLN  073
SWSW 5 7S54W 6
450629View Related
 
COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
EngineerForm: (02)
401219842
04/21/2017
1) Provide 48 hour notice prior to spud via electronic Form 42. 2) Set at least 430’ of surface casing for aquifer protection. Cement to surface. 3) If production casing is set provide cement coverage to at least 200’ above the shallowest completed interval or Lansing, whichever is shallower and across Cheyenne/Dakota interval (5200’ to 4600’ min). Run and submit CBL to verify cemented intervals. 4) If well is a dry hole set plugs at the following depths: 40 sks cement +/- 50’ above the Spergen, 40 sks cement +/- 50’ above the Lansing, 40 sks cement across any DST w/ show, 40 sks cement 100’ below Cheyenne (5200’), 40 sks cement 50’ above top of Dakota (4600’), 50 sks cement from 50’ below surface casing shoe up into surface casing, 15 sks cement in top of surface casing, cut 4 ft below GL, weld on plate, 5 sks cement each in rat hole and mouse hole.
EngineerForm: (02)
401845552
12/27/2018
1) Provide 48 hour notice prior to spud vai electronic Form 42. 2) Set at least 440' of surface casing (5% of proposed TVD). Cement to surface. 3) If production casing is set provide cement coverage to at least 200' above the shallowest completed interval or Lansing, whichever is shallower and across Cheyenne/Dakota interval (5200' to 4600' min). Run and submit CBL to verify cemented intervals. 4) If well is a dry hole, set plugs at the following depths: 40 sks cement +/- 50' above the Spergen, 40 sks cement +/- above the Lansing, 40 sks cement across any DST w/ show, 40 sks cement 100' below Cheyenne (5200'), 40 sks cement 50' above top of Dakota (4600'), 50 sks cement from 50' below surface casing show up into surface casing. 15 sks cement in top of surface casing, cut 4 ft below GL, weld on plate, 5 sks cement each in rat hole and mouse hole.
EngineerForm: (02)
401845552
12/27/2018
Bradenhead tests shall be performed and reported according to the following schedule and Form 17 submitted within 10 days of each test.: 1) All: Within 60 days of rig release, prior to stimulation. 2) Delayed completion: 6 months after rig release, prior to stimulation. 3) All: Within 30 days of first production, as reported on Form 5A.
 
COGIS - Best Management Practice Results
BMP TypeSource DocumentBest Management Practices
Drilling/Completion OperationsForm: (02 )
401219842
5/15/2017
Open-hole Resistivity Log with Gamma Ray Log will be run from TD into the surface casing. A Cement Bond Log with Gamma-Ray will be run on production casing, or on intermediate casing if a production liner is run. The Form 5, Completion Report, will list all logs run and have those logs attached.
Drilling/Completion OperationsForm: (02 )
401845552
1/4/2019
1) Provide 48 hour notice prior to spud vai electronic Form 42. 2) Set at least 430' of surface casing for aquifer protection. Cement to surface. 3) If production casing is set provide cement coverage to at least 200' above the shallowest completed interval or Lansing, whichever is shallower and across Cheyenne/Dakota interval (5200' to 4600' min). Run and submit CBL to verify cemented intervals. 4) If well is a dry hole, set plugs at the following depths: 40 sks cement +/- 50' above the Spergen, 40 sks cement +/- above the Lansing, 40 sks cement across any DST w/ show, 40 sks cement 100' below Cheyenne(5200'), 40 sks cement 50' above top of Dakota (4600'), 50 sks cement from 50' below surface casing show up into surface casing. 15 sks cement in top of surface casing, cut 4ft below GL, weld on plate, 5 sks cement each in rat hole and mouse holw
Drilling/Completion OperationsForm: (02 )
401845552
1/4/2019
Open-hole Resistivity Log with Gamma-Ray Log will be run from TD into the surface casing. A Cement Bond Log with Gamma-Ray will be run on production casing, or on intermediate casing if a production liner is run. The Form 5, Completion Report, will list all logs run and have those logs attached.