WELL05-045-13651CHEVRON
12-11D
QB ENERGY OPERATING LLC
10844
PA
7/14/2023
GRAND VALLEY
31290
GARFIELD  045
NWSW 12 6S97W 6
335837View Related
 
COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
EngineerForm: (04)
403244757
12/13/2022
1) Repair or P&A well by 3/9/2023 (6 months from BH test date) 2) Report work completed with a Form 4 Sundry REPORT OF WORK DONE - Repair Well or Form 5 noting final pressure test results and include any operational or job summaries. If the wellbore geometry changes or there is not a updated WBD in the well file submit an updated WBD. 3) Complete a bradenhead test following completion of the repair and submit results on a Form 17 or directive approved method
OGLAForm: (06)
403340007
03/22/2023
Operator will control all fluids and emissions during plugging and abandonment operations.
EngineerForm: (06)
403340007
04/05/2023
1) Provide electronic Form 42 Notice of MIRU 2 business days ahead of operations and electronic Form 42 Notice of Plugging Operations 48 hours prior to mobilizing for plugging operations. 2) The approved Form 6, Notice of Intent will be at the location during all phases of plugging operations. 3) Operator shall implement measures to control venting and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard. 4) If applicable properly abandon flowlines as per Rule 1105. Pursuant to Rule 911.a. Closure of Oil and Gas Facilities, Operator will submit Site Investigation and Remediation Work plans via Form 27 for COGCC prior approval before cutting and capping the plugged well, conducting flowline abandonment, and removing production equipment. Pursuant to Rule 1105.f. Abandonment Verification, within 90 days of an operator completing abandonment requirements for a flowline or crude oil transfer line, an operator must submit a Field Operations Notice, Form 42-Abandonment of Flowlines for on-location flowlines, and a Flowline Report, Form 44, for off-location flowlines or crude oil transfer lines. 5) Prior to starting plugging operations a bradenhead test shall be performed if there has not been a reported bradenhead test within the 60 days immediately preceding the start of plugging operations. If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required. If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required. The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the COGCC within three (3) months of collecting the samples.
 