Skip to Main Content

COGIS DB

 
Facility TypeFacility ID/
API
Facility Name/
Number
Operator Name/
Number
StatusField Name/
Number
LocationLocation IDRelated Facilities
WELL05-045-10807SILT VALLEY
44A-22-692
TEP ROCKY MOUNTAIN LLC
96850
PR
3/5/2006
MAMM CREEK
52500
GARFIELD  045
SESE 22 6S92W 6
335438View Related
 
COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
EngineerForm: (04)
403246619
12/05/2022
1) Operator shall comply with the Notice to Operators Drilling Wells in the Buzzard, Mamm Creek, and Rulison fields, Garfield County and Mesa County – Procedures and Submittal Requirements for Compliance with COGCC Order Nos. 1-107, 139-56, 191-22, and 369-2 (“Bradenhead NTO”), dated July 8, 2010. 2) Operator shall comply with COGCC Rule 419. Bradenhead Monitoring, Testing, and Reporting and Rule 420. Form 17, Bradenhead Test Report 3) At least once a year shut in bradenhead for 7 days or until the pressure reaches the bradenhead threshold and perform a bradenhead test. Report results on a Form 17, as specified in Rule 420 or other Director approved submittal method.
EngineerForm: (04)
403617067
12/07/2023
1) Operator shall comply with the Notice to Operators Drilling Wells in the Buzzard, Mamm Creek, and Rulison fields, Garfield County and Mesa County – Procedures and Submittal Requirements for Compliance with COGCC Order Nos. 1-107, 139-56, 191-22, and 369-2 (“Bradenhead NTO”), dated July 8, 2010. 2) Operator shall comply with COGCC Rule 419. Bradenhead Monitoring, Testing, and Reporting and Rule 420. Form 17, Bradenhead Test Report or other Director approved submittal method. 3) Comply with any CDPHE, Air Pollution Control Division rules or requirements for all atmospheric discharges. 4) Any liquids blown down are to be collected, stored, handled, and treated or disposed as E&P waste per COGCC’s 900 series rules.
EngineerForm: (04)
404444306
01/22/2026
1. Operator will implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well operations do not constitute a nuisance or hazard to public welfare. 2. Bradenhead gas is not to be vented to atmosphere; any gas from the Bradenhead will be routed to the specified abatement system. Operator will implement measures to get an initial estimate of the gas flow rate and/or volume from the bradenhead. The abatement program may be used for six consecutive months. 3. Operator will submit a Form 42 (“OTHER”) stating that “bradenhead abatement program has started.” 4. At the conclusion of the six months (from installation of pressure mitigation system), conduct a new bradenhead test and submit the Form 17 within ten days of the test and submit a Form 4 Sundry that summarizes current well condition. The sundry should include details of the future plans, flow rate information, pressure data and a discussion of the sample analysis. 5. At least one check valve is required for annular spaces that are tied to sales line or separator. Maintain equipment for pressure regulation and check valves in good working order. 6. At least one valve is required to monitor pressure and sample flow from the bradenhead. 7. Within 30 days of completing the work, submit a Form 4 Subsequent Report including a schematic of the bradenhead tie in
 
COGIS - Best Management Practice Results
No records to display.