WELL05-045-07537ROE
13-12
CAERUS PICEANCE LLC
10456
PA
9/26/2022
MAMM CREEK
52500
GARFIELD  045
SESW 13 7S93W 6
334593View Related
 
COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
EngineerForm: (04)
401865728
02/25/2019
1)This approval is good for one year and a new application must be submitted. Updates for the planned utilization of the well should be included with the application. 2)A Form 5A is required to report all plugs currently downhole which isolate the perforated interval. 3)The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request.
EngineerForm: (04)
402106302
05/27/2020
1) This approval is good for one year and a new application must be made before 7/12/2020 (1 year from prior application). Updates for the planned utilization of the well should be included with the application. 2) The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request. 3) A Form 5A is required to report all plugs currently downhole which isolate the perforated interval.
EngineerForm: (04)
402308923
10/21/2020
1) This approval is good for one year and a new application must be made before 2/11/2021 (1 year from prior application). Updates for the planned utilization of the well should be included with the application. 2) The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request. 3) A Form 5A is required to report all plugs currently downhole which isolate the perforated interval.
EngineerForm: (04)
402592084
04/12/2021
1) This approval is good for one year and a new application must be made before 2/11/2022 (1 year from prior application). Updates for the planned utilization of the well should be included with the application. 2) The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request.
EngineerForm: (04)
402938945
04/18/2022
1) This approval is good for one year and a new application must be made before 2/11/2023 (1 year from prior application). Updates for the planned utilization of the well should be included with the application. 2) The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request. Please correct status from AB to TA for all applicable months 9/2013 forward. 3) Submit a current Wellbore Diagram on the Form 6 Intent for plugging.
OGLAForm: (06)
403037611
06/03/2022
Operator will implement measures to capture, combust, or control emissions to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public health, welfare and the environment.
OGLAForm: (06)
403037611
06/03/2022
This oil and gas location is located within a CPW-mapped 500 foot buffer of the Ordinary High Water Mark of West Mamm Creek for protection of Aquatic Native Species Conservation Water High Priority Habitat. At a minimum, operator will review the stormwater program and implement stormwater BMPs and erosion control measures as needed to prevent fine-grained sediment and impacted stormwater runoff from entering surface water.
EngineerForm: (06)
403037611
07/21/2022
1) Provide electronic Form 42 Notice of MIRU 2 business days ahead of operations and electronic Form 42 Notice of Plugging Operations 48 hours prior to mobilizing for plugging operations. 2) The approved Form 6, Notice of Intent will be at the location during all phases of plugging operations. 3) Operator shall implement measures to control venting and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard. 4) Properly abandon flowlines as per Rule 1105. Pursuant to Rule 911.a. Closure of Oil and Gas Facilities, Operator will submit Site Investigation and Remediation Workplans via Form 27 for COGCC prior approval before cutting and capping the plugged well, conducting flowline abandonment, and removing production equipment. Pursuant to Rule 1105.f. Abandonment Verification, within 90 days of an operator completing abandonment requirements for a flowline or crude oil transfer line, an operator must submit a Field Operations Notice, Form 42-Abandonment of Flowlines for on-location flowlines, and a Flowline Report, Form 44, for off-location flowlines or crude oil transfer lines. 5) Perform bradenhead test prior to MIRU if test has not been performed within six months of plugging or annual test has not been completed. Submit results on Form 17. Contact area environmental protection specialist for sampling and analysis requirements if initial bradenhead pressure is greater than 25 psi.
 
COGIS - Best Management Practice Results