Engineer | Form: (02 ) 400312520 9/18/2012 | 1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU.
2) Comply with Rule 317.i and provide cement coverage from end of 7” casing to a minimum of 200' above Niobrara. Verify coverage with cement bond log.
3) Comply with Rule 321. Run and submit Directional Survey from TD to base of surface casing. Ensure that the wellbore complies with setback requirements in commission orders or rules prior to producing the well.
|
Engineer | Form: (02 ) 400319966 9/18/2012 | 1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU.
|
Engineer | Form: (04 ) 402575700 2/24/2021 | All gas volumes are to be metered and combusted with a device with a 98% design efficiency for hydrocarbon destruction. The flared volumes are to be reported in the Form 7, Monthly Report of Operations. |
Engineer | Form: (04 ) 402575700 2/24/2021 | The approved productivity test is not to exceed 60 calendar days and the well is to be shut in if a gas capture plan or Sundry requesting to continue to produce without infrastructure has not been approved by that time. |
Engineer | Form: (04 ) 402046980 10/8/2021 | 1) Flaring of natural gas shall comply with COGCC Rule 912.
2) Submit requests to flare annually to COGCC on Form 4 (Sundry Notice), which
discusses timing to connect to sales line, plans to develop infrastructure, and
justification for continued venting/flaring. Provide gas analysis including H2S with each
Sundry Notice.
3) Report metered flaring volumes on Form 7, Operator??s Monthly Report of Operations.
4) The operator is required to obtain and maintain any required air permits from
CDPHE.
5) The expectation for permanent flares controlling separators will be an enclosed
combustion device with a 98% design destruction efficiency for hydrocarbons.
6) Notify the local emergency dispatch or the local governmental designee of natural
gas flaring. |
Engineer | Form: (04 ) 402719491 2/25/2022 | Operator shall have an approved Gas Capture Plan or have sought and received a variance from the COGCC Commission for continued production without gas infrastructure, prior to January 15, 2022 or wells must be shut in by January 15, 2022. |
Engineer | Form: (04 ) 402719491 2/25/2022 | Gas volumes for productivity test not reported on Form7, amend reporting. |
Engineer | Form: (04 ) 403368529 4/10/2023 | If well is not producing by March 31, 2024, an official MIT will need to be done. |
Engineer | Form: (04 ) 403368529 4/10/2023 | Well has been designated Inactive as of 06/30/2021. Submit a Form 5B, Inactive Well Notice. |
Engineer | Form: (04 ) 404005100 12/3/2024 | 1) Provide electronic Form 42 Notice of MIRU 2 business days ahead of operations.
2) Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well operations do not constitute a nuisance or hazard to public welfare. |