Engineer | Form: (04 ) 401829191 1/9/2019 | This approval is good for one year and a new application must be made before November 30, 2019. Updates for the planned utilization of the well should be included with the application.
A Form 5A is required to report all plugs currently downhole which isolate the perforated interval and verify the current status. |
Engineer | Form: (04 ) 403240725 12/13/2022 | If well is not producing by November 20, 2023, an official MIT will need to be done. |