Engineer | Form: (02 ) 400290736 6/15/2012 | 1) Note surface casing setting depth change from 1400’ to 1910’. Increase cement coverage accordingly.
2) Submit Form 42 electronically to COGCC 48 hours prior to MIRU.
3) Comply with Rule 317.i and provide cement coverage from TD to a minimum of 200' above Niobrara. Verify coverage with cement bond log.
4) Run and submit Directional Survey from TD to base of surface casing. The operator shall comply with Rule 321, and it shall be the operator’s responsibility to ensure that the wellbore complies with setback requirements in commission orders or rules prior to producing the well.
|
Engineer | Form: (02 ) 400290723 6/15/2012 | 1) Note surface casing setting depth change from 1400’ to 1910’. Increase cement coverage accordingly.
2) Submit Form 42 electronically to COGCC 48 hours prior to MIRU.
|
Permit | Form: (02 ) 400333880 10/15/2012 | Operator statement that a swell packer will be set a location which will make TOP to be at least 600' from the section line. |
Agency | Form: (02 ) 400335491 10/23/2012 | <style type="text/css">
p {margin:0px 0px 0px 2px;}
ul {margin-top:2px;margin-bottom:2px;}
ol {margin-top:2px;margin-bottom:2px;}
.Normal {font-family:Portable User Interface;font-size:11px;vertical-align:middle;color:#000000;}
.TableDefault {border-collapse:collapse;border:1px solid #000000;}
.TableDefault th {padding:2px;vertical-align:top;text-align:left;border:1px solid #000000;}
.TableDefault td {padding:2px;vertical-align:top;text-align:left;border:1px solid #000000;}
</style>
|
Engineer | Form: (02 ) 400333880 10/29/2012 | 1) Note surface casing setting depth change from 1400’ to 1910’. Increase cement coverage accordingly.
FOR PILOT HOLE 2) Submit Form 42 electronically to COGCC 48 hours prior to MIRU.
FOR HORIZONTAL LATERAL 3) Comply with Rule 317.i and provide cement coverage from TVD to a minimum of 200' above Niobrara. Verify coverage with cement bond log.
4) Run and submit Directional Survey from TD to base of surface casing. The operator shall comply with Rule 321, and it shall be the operator’s responsibility to ensure that the wellbore complies with setback requirements in commission orders or rules prior to producing the well.
5) As part of the Form 5 Drilling Completion Report, include the produceable interval as defined by swell packer configuration. (supply the swell packer placement as part of a wellbore diagram)
|
Engineer | Form: (02 ) 400335491 10/29/2012 | 1) Note surface casing setting depth change from 1400’ to 1910’. Increase cement coverage accordingly.
FOR PILOT HOLE 2) Submit Form 42 electronically to COGCC 48 hours prior to MIRU.
FOR HORIZONTAL LATERAL3) Comply with Rule 317.i and provide cement coverage from TVD to a minimum of 200' above Niobrara. Verify coverage with cement bond log.
4) Run and submit Directional Survey from TD to base of surface casing. The operator shall comply with Rule 321, and it shall be the operator’s responsibility to ensure that the wellbore complies with setback requirements in commission orders or rules prior to producing the well.
5) As part of the Form 5 Drilling Completion Report, include the produceable interval as defined by swell packer configuration. (supply the swell packer placement as part of a wellbore diagram)
|
Engineer | Form: (04 ) 400893136 3/2/2016 | 1) Flaring of natural gas shall comply with COGCC Rule 912.
2) Submit requests to flare annually to COGCC on Form 4 (Sundry Notice), which discusses timing to connect to sales line, plans to develop infrastructure, and justification for continued venting/flaring. Provide gas analysis including H2S with each Sundry Notice.
|
Engineer | Form: (04 ) 401222191 4/11/2018 | 1) Flaring of natural gas shall comply with COGCC Rule 912.
2) Submit requests to flare annually to COGCC on Form 4 (Sundry Notice), which discusses timing to connect to sales line, plans to develop infrastructure, and justification for continued venting/flaring. Provide gas analysis including H2S with each Sundry Notice.
3) Report metered flaring volumes on Form 7, Operator’s Monthly Report of Operations.
4) The operator is required to obtain and maintain any required air permits from CDPHE.
5) The expectation for permanent flares controlling separators will be an enclosed combustion device with a 98% design destruction efficiency for hydrocarbons.
6) Notify the local emergency dispatch or the local governmental designee of natural gas flaring.
|
Engineer | Form: (04 ) 401222191 4/11/2018 | This approval is good for one year and new application must be made before May 1, 2018. Current gas analysis should be included. |
Engineer | Form: (04 ) 401915186 4/5/2019 | Gas analysis should be submitted via Form 43. |
Engineer | Form: (04 ) 401915186 4/5/2019 | This approval is good for one year and new application must be made before February 1, 2020.
Submit requests to continue to flare prior to that date to COGCC on Form 4 (Sundry Notice), which discusses timing to connect to sales line, plans to develop infrastructure, and justification for continued venting/flaring. Provide gas analysis including H2S with each Sundry Notice. Gas analysis should also be uploaded via Form 43. |
Engineer | Form: (04 ) 402278769 4/8/2020 | 1) Flaring of natural gas shall comply with COGCC Rule 912.
2) Submit requests to flare annually to COGCC on Form 4 (Sundry Notice), which discusses timing to connect to sales line, plans to develop infrastructure, and justification for continued venting/flaring. Provide gas analysis including H2S with each Sundry Notice.
3) Report metered flaring volumes on Form 7, Operator’s Monthly Report of Operations.
4) The operator is required to obtain and maintain any required air permits from CDPHE.
5) The expectation for permanent flares controlling separators will be an enclosed combustion device with a 98% design destruction efficiency for hydrocarbons. Operator shall manage this well so that production volumes do not exceed the combustor capacity.
6) Notify the local emergency dispatch or the local governmental designee of natural gas flaring.
|
Engineer | Form: (04 ) 402278769 4/8/2020 | Additional requests will detail field development within 10 miles of this well and what infrastructure is in place and actions have been taken to access infrastructure. |
Engineer | Form: (04 ) 402278769 4/8/2020 | This approval is good for one year and new application must be made before February 1, 2020 |
Permit | Form: (06 ) 403565373 10/23/2023 | Missing 5/2023. Submit Operator's Monthly Production Reports (Form 7) required for compliance with Rule 413 within 30 days. |
Engineer | Form: (06 ) 403565373 10/24/2023 | 1) Provide electronic Form 42 Notice of MIRU 2 business days ahead of operations and electronic Form 42 Notice of Plugging Operations 48 hours prior to mobilizing for plugging operations. These are two separate notifications, required by Rules 405.e and 405.l.
2) Pump surface casing shoe plug at 3100' only after isolation has been verified. If surface casing cement is not circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 2966' or shallower and provide a minimum of 10 sx plug at the surface.
3) Leave at least 100’ of cement in the wellbore for each plug without mechanical isolation.
4) After cut and prior to cap, verify isolation by either a 15 minute bubble test or 15 minute optical gas imaging recording. If there is indication of flow contact ECMC Engineering. Provide a statement on the 6SRA which method was used and what was observed. Retain records of final isolation test for 5 years.
5) With the Form 6 SRA operator must provide written documentation which positively affirms each COA listed above has been addressed. |
Engineer | Form: (06 ) 403565373 10/24/2023 | Consistent with Rule 911.a, a Form 27 must be approved prior to cut and cap, conducting flowline abandonment, or removing production equipment. Allow 30 days for Director review of the Form 27; include the Form 27 document number on the Form 44 for offsite flowline abandonment (if applicable) and on the Form 6 Subsequent.
Properly abandon flowlines per Rule 1105. If flowlines will be abandoned in place, include with the Form 27: pressure test results conducted in the prior 12 months as well as identification of any document numbers for a ECMC Spill/Release Report, Form 19, associated with the abandoned line. |
Engineer | Form: (06 ) 403565373 10/24/2023 | Prior to starting plugging operations a bradenhead test shall be performed if there has not been a reported bradenhead test within the 60 days immediately preceding the start of plugging operations.
1) If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required.
2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required.
The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the ECMC within three (3) months of collecting the samples.
If there is a need for sampling, contact ECMC engineering for verification of plugging procedure. |
Engineer | Form: (06 ) 403565373 10/31/2023 | Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public welfare. |