Skip to Main Content

COGIS DB

 
Facility TypeFacility ID/
API
Facility Name/
Number
Operator Name/
Number
StatusField Name/
Number
LocationLocation IDRelated Facilities
WELL05-001-07476MONAGHAN FARMS 24B-5
1-A
CHAMPLIN PETROLEUM COMPANY
15550
PA
2/8/1984
SECOND CREEK
76900
AURORA/ADAMS  001
SESW 5 3S65W 6
376231View Related
 
COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
EngineerForm: (06)
404049263
05/06/2026
1) Provide electronic Form 42 Notice of MIRU 2 business days ahead of operations and electronic Form 42 Notice of Plugging Operations 48 hours prior to mobilizing for plugging operations. These are two separate notifications, required by Rules 405.e and 405.l. 2) Pump surface casing shoe plug at 250' only after isolation has been verified. If surface casing cement is not circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 142' or shallower and provide a minimum of 10 sx plug at the surface. 3) Leave at least 100’ of cement in the wellbore for each plug without mechanical isolation. 4) After cut and prior to cap, verify isolation by either a 15 minute bubble test or 15 minute optical gas imaging recording. If there is indication of flow contact ECMC Engineering. Provide a statement on the 6SRA which method was used and what was observed. Retain records of final isolation test for 5 years. 5) With the Form 6 SRA operator must provide written documentation which positively affirms each COA listed above has been addressed.
EngineerForm: (06)
404049263
05/07/2026
Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public welfare.
 
COGIS - Best Management Practice Results
No records to display.