COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
OGLAForm: (06 )
403695652
3/28/2024
Due to proximity to surface water, Operator will review the stormwater program and implement stormwater BMPs and erosion control measures as needed to prevent fine-grained sediment and impacted stormwater runoff from entering surface water.
OGLAForm: (06 )
403695652
3/28/2024
Notification will be given to any adjacent building unit occupants within a 1000 feet of the wellhead of planned P&A start date.
EngineerForm: (06 )
403695652
4/4/2024
1) Provide electronic Form 42 Notice of MIRU 2 business days ahead of operations and electronic Form 42 Notice of Plugging Operations 48 hours prior to mobilizing for plugging operations. These are two separate notifications, required by Rules 405.e and 405.l. 2) Prior to placing cement above the base of the Upper Pierre (2600') : verify that all fluid (liquid and gas) migration has been eliminated. If evidence of fluid migration or pressure remains, contact ECMC Engineer for an update to plugging orders. 3) Pump surface casing shoe plug at 383' only after isolation has been verified. If surface casing cement is not circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 212' or shallower and provide a minimum of 10 sx plug at the surface. 4) Leave at least 100’ of cement in the wellbore for each plug without mechanical isolation. 5) After cut and prior to cap, verify isolation by either a 15 minute bubble test or 15 minute optical gas imaging recording. If there is indication of flow contact ECMC Engineering. Provide a statement on the 6SRA which method was used and what was observed. Retain records of final isolation test for 5 years.
EngineerForm: (06 )
403695652
4/4/2024
Consistent with Rule 911.a, a Form 27 must be approved prior to cut and cap, conducting flowline abandonment, or removing production equipment. Allow 30 days for Director review of the Form 27; include the Form 27 document number on the Form 44 for offsite flowline abandonment (if applicable) and on the Form 6 Subsequent. Properly abandon flowlines per Rule 1105. If flowlines will be abandoned in place, include with the Form 27: pressure test results conducted in the prior 12 months as well as identification of any document numbers for a ECMC Spill/Release Report, Form 19, associated with the abandoned line.
EngineerForm: (06 )
403695652
4/4/2024
Prior to starting plugging operations a bradenhead test shall be performed if there has not been a reported bradenhead test within the 60 days immediately preceding the start of plugging operations. 1) If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required. 2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required. The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the ECMC within three (3) months of collecting the samples. If there is a need for sampling, contact ECMC engineering for verification of plugging procedure.
EngineerForm: (06 )
403695652
4/4/2024
Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public welfare.
EngineerForm: (06 )
403695652
4/4/2024
Verify existing cement coverage by CBL - submit to ECMC for verification of plugging orders prior to continuing plugging operations.
EngineerForm: (06 )
403695652
4/4/2024
PLUGGING CHANGES CIBP @ 7000' with 2 sacks cement Perf at 4900' with 50 sacks cement Perf at 2550' with 50 sacks cement Perf at 1350' with 300 sacks cement - Leave 10 sacks on retainer at 1250' CIBP at 383' with 35 sacks cement on top
 