COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
OGLAForm: (02A)
401905333
05/14/2019
Green Completions -Test separators and associated flow lines, sand traps and emission control systems shall be installed on-site to accommodate green completions techniques. When commercial quantities of salable quality gas are achieved at each well, the gas shall be immediately directed to a sales line or shut in and conserved. If a sales line is unavailable or other conditions prevent placing the gas into a sales line, the operator shall not produce the wells without an approved variance per Rule 805.b.(3)C.
OGLAForm: (02A)
401905333
05/17/2019
Operator must implement site-specific best management practices in accordance with good engineering practices, including, but not limited to, construction of a berm or diversion dike, site grading, or other comparable measures, sufficient to protect the intermittent stream located 33 feet southwest of the oil and gas location from a release of drilling, completion, produced fluids, and chemical products.
OGLAForm: (02A)
401905333
07/10/2019
The location is in a sensitive area because it falls within the boundary of the Upper Crow Creek Designated Basin, therefore, the operator shall line the secondary containment areas for the tanks and separators with an impervious material to prevent the downward migration of produced liquids.
OGLAForm: (02A)
401905333
07/26/2019
All production facilities shall be constructed within lined secondary containment.
OGLAForm: (02A)
401905333
07/26/2019
Drip pans or liners shall be used during equipment refueling and maintenance.
OGLAForm: (02A)
401905333
07/26/2019
Pigging stations shall have catchments for containing any spilled fluids. Accumulated E&P Waste shall be removed immediately upon completion of pigging operations.
OGLAForm: (02A)
401905333
07/26/2019
Site shall be graded to prevent accumulation of stormwater; runoff shall be controlled with BMPs designed and implemented in accordance with good engineering practices to prevent contaminants or sediments from being transported off location.
OGLAForm: (02A)
401905333
07/26/2019
During drilling and completion activities, a portable or temporary liner shall be emplaced beneath the rig or equipment to protect water resources.
OGLAForm: (02A)
401905333
07/26/2019
Lined secondary containment shall be provided for temporary frac tanks and temporary separation equipment.
OGLAForm: (02A)
401905333
07/26/2019
At a minimum documented weekly site inspections for spills and stormwater BMPs shall be maintained during construction, drilling, and completion activities.
 
COGIS - Best Management Practice Results
BMP TypeSource DocumentBest Management Practices
Drilling/Completion OperationsForm: (02A )
401905333
7/27/2019
Flowback and stimulation fluids from the wells being completed will be sent to tanks and/or filters to allow sand and sediment to settle out before the fluids are hauled to a state-approved disposal facility.
Storm Water/Erosion ControlForm: (02A )
401905333
7/27/2019
Location to be treated to kill weeds and regraded when necessary to maintain proper drainage.
General HousekeepingForm: (04 )
403864426
8/1/2024
Long-term facility structures will be painted a color that enables the facilities to blend in with the natural background color of the landscape, as seen from a viewing distance and location typically used by the public. Maintain appearance with garbage clean-up; a trash bin will be located on site to accumulate waste by the personnel drilling the wells. Site will have unused equipment, trash and junk removed immediately.
Storm Water/Erosion ControlForm: (04 )
403864426
8/1/2024
A sediment trap/basin will be constructed to capture any sediment prior to leaving the location. The sediment trap/basin has been sized in accordance with good engineering practices. A temporary diversion, consisting of a cut swale and compacted earthen berm, will be constructed along the pad edge and routed to the sediment basin to prevent offsite migration of sediment/contaminant into the nearby surface water features.
Storm Water/Erosion ControlForm: (04 )
403864426
8/1/2024
Cat-tracking/equipment-tracking will be used as a temporary stabilization measure of the topsoil pile. Seed/mulch will be used as a permanent stabilization measure of the topsoil pile. Weed mitigation will be performed (mowing and/or spraying) on a routine basis per Bison’s seasonal schedule and on an ad-hoc basis when necessary. Routine inspection throughout the life of the pad will be used to identify when action is needed beyond the routine weed mitigation schedule. Topsoil stockpile construction BMPs include limiting stockpile height to ten feet and slopes of no greater than 3:1.
Storm Water/Erosion ControlForm: (04 )
403864426
8/1/2024
Stormwater management controls include, but are not limited to, the following: Structural erosion controls - Earthen berm, drainage swale, Culvert, Surface roughening, Hydro mulch/seeding, Mulching, Filtrexx, Rip-rap, Surface armor, Vehicle track pad, and sediment basin. Non-structural erosion controls include, but are not limited to, the following: Minimize disturbance footprint, Minimize soil compaction in reclaimed areas, Preserving vegetation, Protecting sensitive habitats, Proper site selection, Re-vegetation, Routine inspections, and Street sweeping.
Material Handling and Spill PreventionForm: (04 )
403864426
8/1/2024
Audible, Visual, and Olfactory (AVO) inspections are of the facility are conduced daily by the Operator. Any valve or fitting that is found to be ineffective is either repaired immediately or well shut-in procedures are implemented.
Material Handling and Spill PreventionForm: (04 )
403864426
8/1/2024
During drilling and completions operations, a temporary impermeable synthetic or geosynthetic liner will be utilized under oil-based equipment. This liner will be installed on top of the plated surface and will provide an additional layer of protection against spills. Secondary containment devices, such as duck ponds or equivalent type products, will be used to protect any pipe connections or equipment that carry, mix, or could possibly leak fluids or chemicals.
Material Handling and Spill PreventionForm: (04 )
403864426
8/1/2024
All flowlines are designed/constructed/tested to ASME B31.4 and API 1104 standards. Only materials with Material Test Reports (MTRs) provided by the pipeline supplier are used in the construction of the flowlines.
Material Handling and Spill PreventionForm: (04 )
403864426
8/1/2024
Documented Audible, Visual, and Olfactory (AVO) inspections and optical gas imaging surveys are conducted monthly by a third-party specialist.
Material Handling and Spill PreventionForm: (04 )
403864426
8/1/2024
All secondary containment devices will enclose an area sufficient to contain and provide secondary containment for one-hundred fifty percent (150%) of the largest single tank. All containment devices shall be inspected at regular intervals and maintained in good condition.
Dust controlForm: (04 )
403864426
8/1/2024
Operator will use soil stockpile stabilization measures to suppress fugitive dust caused solely by wind, including, but not limited to: the use of surface roughening and tracking, seeding with crimped straw mulching or hydroseeding, and, erosion control logs will be installed as a secondary measure along the toe slopes.
ConstructionForm: (04 )
403864426
8/1/2024
Operator acknowledges and will comply with the Colorado Oil & Gas Conservation Commission Policy on the Use of Modular Large Volume Tanks in Colorado dated June 13, 2014.
Noise mitigationForm: (04 )
403864426
8/1/2024
All trucks on location will be prohibited from idling when not in use to prevent unnecessary noise.
Emissions mitigationForm: (04 )
403864426
8/1/2024
Test separators and associated flow lines, sand traps and emission control systems shall be installed on-site to accommodate green completions techniques. When commercial quantities of salable quality gas are achieved at each well, the gas shall be immediately directed to a sales line or shut in and conserved. If a sales line is unavailable or other conditions prevent placing the gas into a sales line, the operator shall not produce the wells without an approved variance.
Emissions mitigationForm: (04 )
403864426
8/1/2024
Reduced Emission Completions Practices and enclosed flowback tanks will be utilized in accordance with Rule 903 and Operator will comply with both rules 903.c.(3).B and 903.c.(3).C. Once commercial quantities of salable quality gas are achieved at each well, the gas shall be immediately directed to a sales line or shut in and conserved.
WildlifeForm: (04 )
403898189
8/23/2024
Any areas reclaimed will be planted with the recommended CPW/Weld County seed mix. Bison will conduct drilling operations outside of Mule Deer and Pronghorn Winter Concentration Area stips. Bison will utilize a quiet frac fleet for completion operations.