LOCATION449137EWS
4
EWS 4 DJ BASIN LLC
10649
AC
6/6/2023
TAMPA
80830
KEENESBURG/WELD  123
NESE 18 2N63W 6
449137View Related
 
COGIS - Conditions of Approval Results
No records to display.
 
COGIS - Best Management Practice Results
BMP TypeSource DocumentBest Management Practices
PlanningForm: (02A )
401151995
2/6/2017
The EWS 4 is a single well pad that will be linked to the EWS Facility #4 by a buried 4- inch pipeline.
Traffic controlForm: (02A )
401151995
2/6/2017
Access road. The access road will be constructed to accommodate local emergency vehicles. This road will be maintained for access until drilling and completion operations are complete. Emergency access will be at the EWS Facilty #4 once drilling and completion operations are complete.
General HousekeepingForm: (02A )
401151995
2/6/2017
Fencing requirements. A permanent fencing plan will be created for the site by Expedition during the final construction of the location. Expedition is under contract to purchase the property and will be the surface owner at the time of construction.
General HousekeepingForm: (02A )
401151995
2/6/2017
Removal of surface trash. All trash, debris and material not intrinsic to the operation of the oil and gas facility shall be removed and legally disposed of as is applicable.
Material Handling and Spill PreventionForm: (02A )
401151995
2/6/2017
Leak Detection Plan. Staff will visit the location daily and visually inspect all fittings for leaks. Additionally, monthly documented SPCCP inspections are conducted pursuant to 40 CFR §112. There will be no produced water or hydrocarbon storage tanks at this location.
Material Handling and Spill PreventionForm: (02A )
401151995
2/6/2017
Berm construction. No permanenet berms shall be constructed at this site. The drill pad will be bermed during drilling operations.
Material Handling and Spill PreventionForm: (02A )
401151995
2/6/2017
Load-lines. All load-lines shall be bull-plugged or capped.
Material Handling and Spill PreventionForm: (02A )
401151995
2/6/2017
Tank specifications No tanks for produced water or hydrocarbons will be constructed on this site.
Noise mitigationForm: (02A )
401151995
2/6/2017
Lighting abatement measures shall be implemented, including the installation lighting shield devices on all of the more conspicuous lights and low density sodium lighting where practicable. Rig shrouding is not believed necessary as this is a remote area. Permanent equipment on location shall be muffled to reduce noise, or shall be appropriately buffered.
Odor mitigationForm: (02A )
401151995
2/6/2017
Oil & gas facilities and equipment shall be operated in such a manner that odors and dust do not constitute a nuisance or hazard to public welfare.
Drilling/Completion OperationsForm: (02A )
401151995
2/6/2017
Closed Loop Drilling Systems – Pit Restrictions. Not applicable; a closed-loop system will be used for drilling.
Drilling/Completion OperationsForm: (02A )
401151995
2/6/2017
Green Completions – No hydrocarbons are anticipated to be produced from this well. Producing zones will be cased off and cemented.
Drilling/Completion OperationsForm: (02A )
401151995
2/6/2017
Blowout preventer equipment (“BOPE”). A double ram and annular preventer will be used during drilling. At least the drilling company shall have a valid well blowout prevention certifications.
Drilling/Completion OperationsForm: (02A )
401151995
2/6/2017
BOPE for well servicing operations. Adequate BOP equipment shall be used. Stabbing valves shall be installed in the event of reverse circulation and shall be prior tested with low and high pressure fluid.
Drilling/Completion OperationsForm: (02A )
401151995
2/6/2017
Pit level indicators. Not applicable; a closed-loop system will be used and no pits shall be dug.
Drilling/Completion OperationsForm: (02A )
401151995
2/6/2017
Drill stem tests. Not applicable; no Drill Stem tests are planned.
Drilling/Completion OperationsForm: (02A )
401151995
2/6/2017
Control of fire hazards. All materials which are considered fire hazards shall be a minimum of 25’ from the wellhead tanks or separators. Electrical equipment shall comply with API RP 500 and will comply with the current national electrical code. An emergency response plan shall be generated for this site.
Drilling/Completion OperationsForm: (02A )
401151995
2/6/2017
Guy line anchors. All guy line anchors shall be brightly marked pursuant to Rule 604.c (2)Q.
Final ReclamationForm: (02A )
401151995
2/6/2017
Within 90-day subsequent to the time of plugging and abandonment of the entire site, superfluous debris and equipment shall be removed from the site.
Final ReclamationForm: (02A )
401151995
2/6/2017
P&A’d wells shall be identified pursuant to 319.a.(5).
Traffic controlForm: (02A )
401716056
11/23/2018
Access road. The access road will be constructed to accommodate local emergency vehicles. This road will be maintained for access until drilling and completion operations are complete. Emergency access will be at the EWS Facilty #4 once drilling and completion operations are complete.
General HousekeepingForm: (02A )
401716056
11/23/2018
Removal of surface trash. All trash, debris and material not intrinsic to the operation of the oil and gas facility shall be removed and legally disposed of as applicable.
Storm Water/Erosion ControlForm: (02A )
401716056
11/23/2018
During drilling operations, the location will have a berm or ditch installed along at least the southwest edge of the location, parallel to the nearest property line.
Material Handling and Spill PreventionForm: (02A )
401716056
11/23/2018
Leak Detection Plan. Staff will visit the location daily and visually inspect all fittings for leaks. Additionally, monthly documented SPCCP inspections are conducted pursuant to 40 CFR §112. There will be no produced water or hydrocarbon storage tanks at this location.
Drilling/Completion OperationsForm: (02A )
401716056
11/23/2018
Blowout preventer equipment (“BOPE”). A double ram and annular preventer will be used during drilling. At least the drilling company shall have a valid well blowout prevention certifications.
12