| Construction | Form: (02A ) 400731743 6/13/2015 | Operator shall submit a Form 42 to the COGCC 48 hours prior to commencement of construction activities. |
| Construction | Form: (02A ) 400731743 6/13/2015 | The following procedure describes BCEOC standard construction practices for setting a partially buried pre-cast cement water vault and new tank battery construction.
1) The excavation will first be lined with 4” of clay or other low permeability soil.
2) A 30 mil liner will be installed on top of the low permeability soil. The 30 mil liner will be a contiguous liner which will underlay the entire tank battery.
3) The tank battery / water vault liner will be keyed into a galvanized steel containment ring installed surrounding the tank battery.
4) Sand bedding will be installed to protect the synthetic liner prior to placing equipment in the containment area.
|
| Drilling/Completion Operations | Form: (02A ) 400731743 6/13/2015 | BMP-Bonanza Creek Energy acknowledges and will comply with the “COGCC Policy On the Use of Modular Large Volume Tanks in Colorado” dated June 13, 2014. |
| Planning | Form: (02A ) 401254440 7/19/2017 | Operator shall submit a Form 42 to the COGCC 48 hours prior to commencement of construction activities. |
| Drilling/Completion Operations | Form: (02A ) 401254440 7/19/2017 | Bonanza Creek Energy acknowledges and will comply with the “COGCC Policy On the Use of Modular Large Volume Tanks in
Colorado” dated June 13, 2014. |
| Storm Water/Erosion Control | Form: (02A ) 401622843 7/25/2018 | Confluence will maintain a Stormwater Management Plan with site specific measures
to assess erosion control. Confluence will make thorough inspections, in accordance
with the requirements set forth by CDPHE Water Quality Division (WQD). The
inspection schedule is as follows:
While site is under construction, an inspection is required at least every 14 calendar
days;
Post storm event inspections must be conducted within 24 hours after the end of any
precipitation or snowmelt event that causes surface erosion.
Inspection records will be kept on file for a minimum of three (3) years from expiration
or inactivation of permit coverage. These records will be made available to the
regulatory agencies upon request. |
| Drilling/Completion Operations | Form: (04 ) 401770191 9/27/2018 | Operator Certifies that the MLVT will be designed and implemented according to the COGCC MLVT Policy dated June 13, 2014 and that there are no building units down gradient from the proposed MLVT. |