Planning | Form: (02A ) 400762434 5/1/2015 | Development from existing well pads: In order to reduce surface disturbance, Ward is permitting this 2A for twelve (18) wells.
The well pad will be constructed in a manner that noise mitigation will be installed and removed without disturbing the site or landscaping.
|
Traffic control | Form: (02A ) 400762434 5/1/2015 | A traffic plan will be done if request by Adams County.
Ward will construct all leasehold road to accommodate local emergency vehicle access requirements and will be maintained in a reasonable condition.
|
General Housekeeping | Form: (02A ) 400762434 5/1/2015 | Loadlines: All loadlines shall be bullplugged or capped.
Guy Line Anchors: All guy line anchors left buried for future use will be identified by a marker of bright color not less than four feet in height and not greater than one foot east of the guy line anchor.
Removal of Surface Trash: Ward agrees that all trash, refuse pipe, equipment, liquids, chemicals of other materials that are not necessary for the continued operations of the wells will be removed and disposed of no later than 30 days after completion. No such items will be burned or buried on location.
Well Site Cleared: Ward agrees that all trash, refuse pipe, equipment, liquids, chemicals of other materials that are not necessary for the continued operations of the wells will be removed and disposed of no later than 30 days after completion. No such items will be burned or buried on location.
|
Storm Water/Erosion Control | Form: (02A ) 400762434 5/1/2015 | Stormwater will be managed by Ward’s Stormwater Management Plan which the Colorado Department of Public Health and Environment oversees. Appropriate BMPs will be installed as conditions dictate and maintained and/or replaced as necessary. |
Material Handling and Spill Prevention | Form: (02A ) 400762434 5/1/2015 | Leak Detection Plan: To ensure protection for the surface during fracturing treatment, the location will be specifically constructed to contain any releases or spills. Secondary containment from any chemical spills or leaks will surround any trucks that carry, mix, or add chemicals to the flow stream as well as connections that could possibly leak fluid. Should any spill or release occur, every reasonable step will be taken to quickly remediate the area disturbed.
Control of Fire Hazards: Ward and its contractor’s employ best management practices during the drilling and production of its wells and facilities. They will comply with appropriate COGCC and any county rules concerning fire and safety. Ward will ensure that any flammable material will remain no less than 25 feet from the wellhead (s), tanks and separator(s).
Berm Construction: A containment berm will be constructed around the oil and water storage tanks. The berm will be inspected regularly and maintained in good condition.
Tank specifications: Tanks shall be constructed and maintained in accordance with the National Fire Protection Association Code 30 (2008 version). All tanks will be visually inspected once a day for issues. Recorded inspections will be conducted once a month pursuant to 40 CFR §112.
|
Dust control | Form: (02A ) 400762434 5/1/2015 | Operator will comply with Rule 805.c and take all practicable measures to control fugitive dust caused by the operation, including but not limited to wetting the soil with fresh water via a truck with a spreader bar if deemed necessary. |
Noise mitigation | Form: (02A ) 400762434 5/1/2015 | Fencing: The wellsite will be fenced if requested by the Surface Owner.
Visual Mitigation: Pursuant to Rule 804, the tank battery shall be painted in uniform, non-contrasting, non-reflective color tones with the colors matched to but slightly darker than the surrounding landscape.
|
Noise mitigation | Form: (02A ) 400762434 5/1/2015 | Ward is planning on using sound walls to mitigate noise levels during drilling and completion. A background noise study will be done prior to drilling and the appropriate soundwall design will be chosen to meet or exceed COGCC noise requirements. |
Drilling/Completion Operations | Form: (02A ) 400762434 5/1/2015 | Closed Loop System: Closed Loop System will be used for drilling and fluid management. No reserve pit will be used.
Green Completions: Ward will comply with COGCC Rule 805b.(3)A and utilize Green Completion Methods.
BOPE Testing: Upon initial rig-up and once every 30 days during drilling operations, pressure testing of the casing string and each component of the BOPE will be performed to 70% of working pressure or 70% of the internal yield of the casing, whichever is less.
BOPE for well servicing operations: Adequate blowout prevention equipment will be used on any servicing operations associated with this well. Backup staving valves shall be required on well servicing operations during reverse circulation. Valves will be pressure tested before each well servicing operation using both low-pressure and high-pressure fluid.
BOPE: Ward will utilize drilling rigs with a minimum of a double ram and annular preventer.
Drill Stem Tests: Drill Stem Tests are not anticipated for this location.
Pit Level Indicators: Pit Level Indicators will not be needed as no pits will be used on location.
|
Drilling/Completion Operations | Form: (02A ) 400762434 5/1/2015 | All light will be directed downward as much as possible to mitigate light pollution into the adjacent neighborhood. In addition the soundwall will also help to limit light pollution. |
Final Reclamation | Form: (02A ) 400762434 5/1/2015 | Identification of Plugged and Abandoned Wells: Pursuant to Rule 319.a.(5)., once the well has been plugged and abandoned, Ward will identify the location of the wellbore with a permanent monument that will detail the well name and date of plugging. |