COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
OGLAForm: (02A )
400654951
12/22/2014
Location lies within a Sensitivie Area with potential shallow groundwater and is located within a Designated Groundwater Protection Area for the Brighton Aquifer. Secondary containment areas for production facilities shall be constructed of steel rings, designed and installed to prevent leakage and resist degradation from erosion or routine operation and shall be constructed with a synthetic or engineered liner that contains all primary containment vessels and flowlines and is mechanically connected to the steel ring to prevent leakage.
OGLAForm: (02A )
400654951
12/22/2014
Location lies within proximity of surface water drainages and lies within the Brighton BMP Buffer Zone. Tertiary containment shall be placed along the downgradient and crossgradient portions of Production Facilities, including process vessels.
OGLAForm: (02A )
400654951
12/22/2014
Secondary containment shall be sized to contain a minimum of 150% of the volume of the largest primary containment vessel within the secondary containment area.
OGLAForm: (02A )
400654951
12/24/2014
Operator shall provide notification to the Brighton Public Works Department prior to commencement of new surface disturbing activities at the site.
OGLAForm: (02A )
400654951
12/24/2014
Operator shall prepare and implement an emergency spill response program that includes employee training, safety, and maintenance provisions and current contact information for Brighton. The emergency response plan shall specify when notifications to Brighton shall be made and must be prepared in consultation with Brighton.
OGLAForm: (02A )
400654951
1/27/2015
Operator shall provide notice to COGCC 48 hours prior to commencing construction of this Oil and Gas Location via Form 42.
Reclamation SpecialistForm: (04 )
401737262
9/25/2018
Financial assurance bond will not be released until the location meets Rule 1003, including vegetation standards.
Reclamation SpecialistForm: (04 )
401737262
9/25/2018
Approval of this form is an approval of the NTO request only. Areas detailed in the attached map are not a final delineation of the exact areas needed for production operations or interim reclamation, and are only an estimate. Future assessments regarding the size and extent of the areas needed for production may be determined on the ground by reclamation staff during a field inspection.
 
COGIS - Best Management Practice Results
BMP TypeSource DocumentBest Management Practices
PlanningForm: (02A )
400654951
1/28/2015
Site Specific Measures: Ward will maintain a Stormwater Management Plan with site specific measurements to assess erosion control.
PlanningForm: (02A )
400654951
1/28/2015
Development from existing well pads: There were no existing wellpads to drill these proposed wells from. However, in order to reduce surface disturbance, Ward is permitting this 2A for twelve (12) wells and plans for this to be a multi-wellpad. The well pad will be constructed in a manner that noise mitigation will be installed and removed without disturbing the site or landscaping. The pad will have an all-weather access road to allow for operator and emergency responders.
Traffic controlForm: (02A )
400654951
1/28/2015
Traffic Plan: A traffic plan will be done if request by Adams County.
Traffic controlForm: (02A )
400654951
1/28/2015
If required by Adams County, a traffic plan will be coordinated prior to commencment of move in and rig up.
Traffic controlForm: (02A )
400654951
1/28/2015
Ward will construct all leasehold road to accommodate local emergency vehicle access requirements and will be maintained in a reasonable condition.
General HousekeepingForm: (02A )
400654951
1/28/2015
Loadlines: All loadlines shall be bullplugged or capped.
General HousekeepingForm: (02A )
400654951
1/28/2015
Guy Line Anchors: All guy line anchors left buried for future use will be identified by a marker of bright color not less than four feet in height and not greater than one foot east of the guy line anchor.
General HousekeepingForm: (02A )
400654951
1/28/2015
Removal of Surface Trash: Ward agrees that all trash, refuse pipe, equipment, liquids, chemicals of other materials that are not necessary for the continued operations of the wells will be removed and disposed of no later than 30 days after completion. No such items will be burned or buried on location.
General HousekeepingForm: (02A )
400654951
1/28/2015
Well Site Cleared: Ward agrees that all trash, refuse pipe, equipment, liquids, chemicals of other materials that are not necessary for the continued operations of the wells will be removed and disposed of no later than 30 days after completion. No such items will be burned or buried on location.
Material Handling and Spill PreventionForm: (02A )
400654951
1/28/2015
Leak Detection Plan: To ensure protection for the surface during fracturing treatment, the location will be specifically constructed to contain any releases or spills. Secondary containment from any chemical spills or leaks will surround any trucks that carry, mix, or add chemicals to the flow stream as well as connections that could possibly leak fluid. Should any spill or release occur, every reasonable step will be taken to quickly remediate the area disturbed.
Material Handling and Spill PreventionForm: (02A )
400654951
1/28/2015
Control of Fire Hazards: Ward and its contractor’s employ best management practices during the drilling and production of its wells and facilities. They will comply with appropriate COGCC and any county rules concerning fire and safety. Ward will ensure that any flammable material will remain no less than 25 feet from the wellhead (s), tanks and separator(s).
Material Handling and Spill PreventionForm: (02A )
400654951
1/28/2015
Berm Construction:Containment berms will be constructed of steel rings, designed and installed to prevent leakage and resist degradation from erosion or routine operation. Secondary containment areas for tanks will be constructed with a synthetic or engineered liner that contains all primary containment vessels and flowlines and is mechanically connected to the steel ring to prevent leakage.
Material Handling and Spill PreventionForm: (02A )
400654951
1/28/2015
Tank specifications: Tanks shall be constructed and maintained in accordance with the National Fire Protection Association Code 30 (2008 version). All tanks will be visually inspected once a day for issues. Recorded inspections will be conducted once a month pursuant to 40 CFR §112.
Dust controlForm: (02A )
400654951
1/28/2015
Operator will comply with Rule 805.c and take all practicable measures to control fugitive dust caused by the operation, including but not limited to wetting the soil with fresh water via a truck with a spreader bar if deemed necessary.
ConstructionForm: (02A )
400654951
1/28/2015
Fencing: The wellsite will be fenced if requested by the Surface Owner.
ConstructionForm: (02A )
400654951
1/28/2015
Visual Mitigation: Pursuant to Rule 804, the tank battery shall be painted in uniform, non-contrasting, non-reflective color tones with the colors matched to but slightly darker than the surrounding landscape. Additionally, because the location is within the Rule 604.a.(2) setback due to its proximity to the dealership to the south and east, the battery facilities will be fenced with a 6’ chain-link fence, the color for which shall be sufficiently similar to the tank color. This fence shall serve to restrict access to the site by unauthorized persons and as visual mitigation of the facility components.
Noise mitigationForm: (02A )
400654951
1/28/2015
Temporary sound barriers may be installed if necessary.
Drilling/Completion OperationsForm: (02A )
400654951
1/28/2015
Closed Loop System: Closed Loop System will be used for drilling and fluid management. No reserve pit will be used or fresh water pits.
Drilling/Completion OperationsForm: (02A )
400654951
1/28/2015
Green Completions: Ward will comply with COGCC Rule 805b.(3)A and utilize Green Completion Methods.
Drilling/Completion OperationsForm: (02A )
400654951
1/28/2015
BOPE Testing: Upon initial rig-up and once every 30 days during drilling operations, pressure testing of the casing string and each component of the BOPE will be performed to 70% of working pressure or 70% of the internal yield of the casing, whichever is less. BOPE for well servicing operations: Adequate blowout prevention equipment will be used on any servicing operations associated with this well. Backup staving valves shall be required on well servicing operations during reverse circulation. Valves will be pressure tested before each well servicing operation using both low-pressure and high-pressure fluid. BOPE: Ward will utilize drilling rigs with a minimum of a double ram and annular preventer.
Drilling/Completion OperationsForm: (02A )
400654951
1/28/2015
Drill Stem Tests: Drill Stem Tests are not anticipated for this location.
Drilling/Completion OperationsForm: (02A )
400654951
1/28/2015
Pit Level Indicators: Pit Level Indicators will not be needed as no pits will be used on location.
Final ReclamationForm: (02A )
400654951
1/28/2015
Identification of Plugged and Abandoned Wells: Pursuant to Rule 319.a.(5)., once the well has been plugged and abandoned, Ward will identify the location of the wellbore with a permanent monument that will detail the well name and date of plugging upon a permanent monument. The well site will be cleared within 90 days after a well is plugged and abandoned. The wellsite will be cleared of all non-essential equipment and trash.