Skip to Main Content

COGIS DB

 
Facility TypeFacility ID/
API
Facility Name/
Number
Operator Name/
Number
StatusField Name/
Number
LocationLocation IDRelated Facilities
LOCATION436849BLACKCOMB
3-14
POLARIS PRODUCTION OPCO LLC
10793
AC
12/1/2023
ARIKAREE CREEK
2914
LINCOLN  073
NENW 14 6S54W 6
436849View Related
 
COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
OGLAForm: (02A)
400554032
03/31/2014
The proposed location is in a sensitive area. Secondary containment areas for tanks shall be constructed of steel rings, designed and installed to prevent leakage and resist degradation from erosion or routine operation and shall be constructed with a synthetic or engineered liner that contains all primary containment vessels and flowlines and is mechanically connected to the steel ring to prevent leakage.
OGLAForm: (02A)
400554032
03/31/2014
Reference Area photographs (taken during the growing season) and map will be submitted within 12 months from the submittal of this Form 2A.
OGLAForm: (04)
403660366
09/09/2024
All associated gas produced during this productivity test shall be combusted through a combustor with a 98% design destruction efficiency
 
COGIS - Best Management Practice Results
BMP TypeSource DocumentBest Management Practices
ConstructionForm: (02A )
400554032
4/20/2014
Certificate to Discharge Under CDPHE General Permit No. COR-030000 Stormwater Discharges assoicated with Construction Certification No. COR031825 Prior to construction, perimeter controls will be installed utilizing cuttings from the clearing operations. Once the well pad has been constructed a variety of BMP's shall be utilized for the site specific condtions. BMP's to be utilized may include, but are not limited to: -Dirt Ditch/Berm -Erosion Control Blankets -Straw Bale Barrier -Straw Wattles -Seeding -Imported hard Armor -Check Dams -Culvert/Culvert Protection -Crimpted Straw -Silt Fence -Surface Roughening/Surface Rip During construction, each site will be inspected every 14 days and 24-72 hours after any precipitation event causing erosion depending on the current site activities. These inspections will be recorded and maintained at Nighthawk's office. Repairs shall be completed as soon as possible after an inspection reporting BMP repairs are required. Any site specific modifications will be revised on the site plan when implemented at the site. A field wide Stormwater Management Plan (SWMP) for the Project Area is located at Nighthawk's office. Spill Protection Control and Countermeasures (SPCC) plans for the Project Area are stored on file at Nighthawk's office. The field wide SWMP addresses SPCC during construction operations.