TypeSource DocumentConditions of Approval
Field OperationsForm: (04)
400938095
12/10/2015
45 day extension to complete corrective actions was verbally granted on November 16, 2015. Follow up conference indicated work to meet corrective actions deadline would be ongoing. A meeting with the operator to discuss status of 45 extension is scheduled for 12-29-2015.
 
COGIS - Best Management Practice Results
BMP TypeSource DocumentBest Management Practices
PlanningForm: (02A )
400480064
4/12/2014
604c.(2).Q. Guy Line Anchors: Should guy line anchors be left buried for future use, they shall be identified by a bright marker greater than four (4) feet high and no more than one (1) foot east of the guy line anchor.
PlanningForm: (02A )
400480064
4/12/2014
604c.(2).S. Access Roads: KMG will utilize a lease access road from CR25 for drilling operations and maintenance equipment. This access route is contingent upon an agreement with City of Thornton. An alternative access road is also planned off of CR25. Both access routes are illustrated on the attached access road map. The road will be properly constructed and maintained to accommodate for local emergency vehicle access.
PlanningForm: (02A )
400480064
4/12/2014
604c.(2).V. Development From Existing Well Pads: Drilling from an existing well pad was not feasible for the development of these wells; however, this well pad will be considered for future well locations.
Traffic controlForm: (02A )
400480064
4/12/2014
604c.(2).D. Traffic Plan: If required by the local government, a traffic plan will be coordinated with the local jurisdiction prior to commencement of operations. Weld County Road 25 is paved and maintained by Weld County and will therefore not require dust mitigation.
General HousekeepingForm: (02A )
400480064
4/12/2014
604c.(2).O. Loadlines: All loadlines shall be bullplugged or capped.
General HousekeepingForm: (02A )
400480064
4/12/2014
604c.(2).P. Removal of Surface Trash: A commercial size trash bin for removing debris will be located on site. This bin will be for use by all parties affiliated with the operation.
Storm Water/Erosion ControlForm: (02A )
400480064
4/12/2014
604c.(2).W. Site-specific Measures: KMG maintains a Stormwater Management Plan that assesses erosion control for every KMG operated location. This well pad will be added to this plan once construction begins. This plan is updated every fourteen (14) days and after any major weather event.
Material Handling and Spill PreventionForm: (02A )
400480064
4/12/2014
604c.(2).N. Control of Fire Hazards: KMG and its contractors will employ best management practices during the drilling and production of its wells and facilities and will comply with appropriate COGCC rules concerning safety and fire. KMG will ensure that any material that might be deemed a fire hazard will remain no less than twenty-five (25) feet from the wellhead(s), tanks and separator(s).
ConstructionForm: (02A )
400480064
4/12/2014
604c.(2).E. Multiwell Pads: This 2A application is for a three-well pad. Use of this multi-well pad will reduce surface impact.
ConstructionForm: (02A )
400480064
4/12/2014
604c.(2).M. Fencing Requirements: The completed wellsites will be surrounded with a fence and gate with adequate lock to restrict access to authorized personnel only. KMG personnel will monitor the wellsites regularly upon completion of the wells. Authorized representatives and/or KMG personnel shall be on-site during drilling and completion operations.
ConstructionForm: (02A )
400480064
4/12/2014
604c.(2).R. Tank Specifications: Two 500 barrel skid mounted frac tanks will be temporarily placed on-site for use of the pre-spud rig only. One tank will store water and the other will store water based mud.
ConstructionForm: (02A )
400480064
4/12/2014
604c.(2).G. Berm Construction: Kerr McGee will create secondary containment by construction of a berm or diversion dike, site grading, or other comparable measures, sufficient to further protect the canal located 300’ northeast of the oil and gas location.
Noise mitigationForm: (02A )
400480064
4/12/2014
604c.(2).A. Noise: Pending a safety review after construction of the location, sound mitigation barriers (hay bales) will be placed along the eastern and northern sides of the pad location to damper noise during drilling and completions to the nearby building units. Sound surveys that have been conducted on each rig type are utilized to anticipate any additional noise mitigation once a drilling rig is determined.
Drilling/Completion OperationsForm: (02A )
400480064
4/12/2014
604c.(2).B. Closed Loop Drilling System: KMG will use a closed loop or “pitless” system for drilling and fluid management and will not construct a reserve pit.
Drilling/Completion OperationsForm: (02A )
400480064
4/12/2014
604c.(2).C. Green Completions: KMG will install Vapor Recovery Unit(s) (VRU) to prevent uncontrolled venting of flash gas. Environmental Control Devices (ECD) will be used to control working and breathing vapor losses for oil and water tanks. Temporary above ground polyethylene water pipelines will deliver water to location operations from larger trunk lines to reduce truck traffic and minimize air pollution.
Drilling/Completion OperationsForm: (02A )
400480064
4/12/2014
604c.(2).H. BOPE: Our rigs at a minimum will have a double ram with blind and pipe ram; and annular preventer.
Drilling/Completion OperationsForm: (02A )
400480064
4/12/2014
604c.(2).I. BOPE Testing for Drilling Operations: Upon initial rig-up, BOPE’s will be tested at a minimum of every 30 days.
Drilling/Completion OperationsForm: (02A )
400480064
4/12/2014
604c.(2).J. BOPE for Well Servicing Operations: Blowout prevention equipment will be used on any servicing operations associated with this well. Backup stabbing valves will be used during any future servicing operations during reverse circulation. Valves shall be pressure tested before each well servicing operation using low-pressure air and high-pressure fluid.
Drilling/Completion OperationsForm: (02A )
400480064
4/12/2014
604c.(2).K. Pit Level Indicators: All mud tanks (used in lieu of pits) contain pit level monitors with Electronic Drilling Recorders (EDR). KMG uses EDRs with pit level monitor(s) and alarm(s) for production rigs. Basic level gages are used on tanks utilized for the surface rig.
Drilling/Completion OperationsForm: (02A )
400480064
4/12/2014
604c.(2).L. Drill Stem Tests: No drill stem tests are planned and none will be performed without prior approval from the director.
Final ReclamationForm: (02A )
400480064
4/12/2014
604c.(2).T. Well Site Cleared: The wellsite will be cleared of all non-essential equipment within ninety (90) days after all wells associated with the pad have been plugged and abandoned.
Final ReclamationForm: (02A )
400480064
4/12/2014
604c.(2).U. Identification of Plugged and Abandoned Wells: Pursuant to rule 319.a.(5)., once the well has been plugged and abandoned, KMG will identify the location of the wellbore with a permanent monument that will detail the well name and date of plugging.