COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
AgencyForm: (02A)
400056347
06/07/2010
The moisture content of any drill cuttings in a cuttings pit, trench, or pile shall be as low as practicable to prevent accumulation of liquids greater than de minimis amounts. At the time of closure, the drill cuttings must also meet the applicable standards of table 910-1.
AgencyForm: (02A)
400056347
06/16/2010
Operator must ensure 110 percent secondary containment for any volume of fluids contained at well site during drilling and completion operations. If fluids are conveyed via pipeline, operator must implement best management practices to contain any unintentional release of fluids.
AgencyForm: (02A)
400056347
06/16/2010
Operator must implement best management practices to contain any unintentional release of fluids.
AgencyForm: (02A)
400056347
06/16/2010
Reserve pit must be lined or closed loop system must be implemented during drilling.
AgencyForm: (02A)
400056347
06/16/2010
Location is in a sensitive area because of proximity to surface water; therefore, operator must ensure 110 percent secondary containment for any volume of fluids contained at well site during drilling and completion operations.
OGLAForm: (04)
401445982
11/15/2017
Operator shall notify the COGCC once cuttings re-location has commenced and then again when all cuttings for re-location to the MDP #2 Pad has been completed using the Form 42 (as described in Rule 316C.m. Notice of Completion of Form 2/2A Permit Conditions) and by emailing COGCC (dave.kubeczko@state.co.us).
EnvironmentalForm: (04)
402626975
03/31/2021
Based on a review of the information provided, it appears that no further action is necessary at this time and COGCC approves the closure request. Should conditions at the site indicate contaminant concentrations in soils exceeding COGCC standards, or, if groundwater is found to be significantly impacted, further investigation and/or remediation activities may be required at the site. Final Reclamation should comply with 100O Rules. Location/Facility closure shall meet table 915-1 cleanup standards Protection of Groundwater Soil Screening Level Concentrations. SEE F19A DOC 200449605
 
COGIS - Best Management Practice Results
BMP TypeSource DocumentBest Management Practices
ConstructionForm: (04 )
401445982
11/15/2017
Drill cuttings from the wellbore will be directed into a bermed surface containment. Any free liquids accumulated in the containment would be removed as soon as practicable.