| PROPOSED BMPs | Form: (07 ) 0 1/23/2012 | Certification to Discharge
Under
CDPS General Permit COR -03000
Stormwater Discharges Associated with Construction
T10S, R55W
Sec. 19: NE1 /4SW1 /4
Lincoln County, Colorado
U -iop BMP Plan
Wiepking - Fullerton Energy, L.L.C.
4600 S. Downing St.
Englewood, CO 80113
303 - 789 -1798
303 - 761 -9067 (fax)
Certification Number COR 39788
Description of Well Site and Construction Area
1 -3 acre site with access road for drilling of oil and gas well. Terrain is flat
with native grass and sagebrush. No receiving waters will be affected by
well pad. Drilling pits closed and reclaimed with the drillsite reseeded within
6 months weather permitting. Silt fences will be installed on low side site of
drill site. Topsoil will be separated and spread on drill site as final operation
before reseeding operations. To prevent soil erosion site will be disked and
straw crimped in or manure spread.
Stormwater Management Plan (SWMP) is on file in Wiepking - Fullerton
Energy, L.L.C. office.
Spill Prevention, Control and Countermeasure Plan is on file in Wiepking-
Fullerton Energy, L.L.C. office.
|
| Storm Water/Erosion Control | Form: (02A ) 400684035 10/2/2014 | BMP Plan
Wiepking-Fullerton Energy, L.L.C.
4600 S. Downing St.
Englewood, CO 80113
303-789-1798
303-761-9067 (fax)
Certification to Discharge
Under
CDPS General Permit COR-03000
Stormwater Discharges Associated with Construction
Certification Number COR 39788
Aloha Mula # 3S well
T10S, R55W
Sec. 19: NE1/4SW1/4
Lincoln County, Colorado
Description of Well Site and Construction Area
1-3 acre site with access road for drilling of oil and gas well. Terrain is rolling with native grass and sagebrush. No receiving waters will be affected by well pad. The Aloha Mula # 3S is a proposed second vertical well to be drilled 106' east of the producing Aloha Mula # 3 oil well within the original 3 acre disturbed area. The original drilling pit has been reclaimed and the drill site reseeded with native grass. A new drilling pit will be dug within the original disturbed area. The Drilling pits closed and reclaimed with the drillsite reseeded within 6 months weather permitting. Surface Roughening will be used on the low side site of drill site to reduce speed of runoff, increase infiltration, reduce erosion, trap sediment and prepare soil, reseeding. Topsoil will be separated and spread on drill site as final operation before reseeding operations. To prevent soil erosion site will be disked and straw crimped in or manure spread.
Stormwater Management Plan (SWMP) is on file in Wiepking-Fullerton Energy, L.L.C. office.
Spill Prevention, Control and Countermeasure Plan is on file in Wiepking-Fullerton Energy, L.L.C. office.
|