LOCATION335716BERRY F01 697
QB ENERGY OPERATING LLC
10844
AC
1/1/2026
GRAND VALLEY
31290
GARFIELD  045
SENW 1 6S97W 6
335716View Related
 
COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
EnvironmentalForm: (04)
400519045
12/10/2013
Netting can be removed during the winter (as requested) as long as the pit is frozen during the winter. If part of the pit does not freeze due to pumping or discharge of produced water into the pit, then that section of the pit must be netted and isolated so that no access to the water is possible for birds and other wildlife. It is the responsibility of the operator to protect wildlife from having access to (unfrozen) water of the pit.
OGLAForm: (04)
400519045
02/10/2014
Netting needs to be reinstalled over fluid pits upon thawing of the pits' contents, or no later than 04-01-14.
EnvironmentalForm: (04)
400743280
12/08/2014
1) Netting can be removed during the winter (as requested) as long as the pit is frozen during the winter. If part of the pit does not freeze due to pumping or discharge of produced water into the pit, then that section of the pit must be netted and isolated so that no access to the water is possible for birds and other wildlife. ********** 2) It is the responsibility of the operator to protect wildlife from having access to (unfrozen) water of the pit. Nets shall be reinstalled if condensate or oil is observed on the pit. Nets shall be installed if pits are accessible to wildlife. ********** 3) Netting needs to be reinstalled over fluid pits upon thawing of the pits' contents. Nets will be reinstalled before Sage Grouse nesting season begins on March 1st.
PermitForm: (04)
401246420
03/31/2017
The operator-of-record of this location is subject to the September 1, 2017 extended deadline granted by this variance to comply with the March 1, 2017 requirements of the COGCC Notice to Operators: Procedure for Preset Conductors (rev October 6, 2016) to have performed one of the following options: (1) plug the conductors and perform reclamation, (2) request to keep the conductors and provide additional financial assurance, or (3) submit a Rule 502.b variance for an alternative plan.
 