Skip to Main Content

COGIS DB

 
Facility TypeFacility ID/
API
Facility Name/
Number
Operator Name/
Number
StatusField Name/
Number
LocationLocation IDRelated Facilities
LOCATION334722GM
24-12
TEP ROCKY MOUNTAIN LLC
96850
AC
4/1/2021
GRAND VALLEY
31290
PARACHUTE/GARFIELD  045
SWSW 12 7S96W 6
334722View Related
 
COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
OGLAForm: (02A)
400466268
10/16/2013
Notify the COGCC 48 hours prior to start of pad construction (if existing pad needs to be expanded or brought out to the original footprint), rig mobilization, spud, and start of hydraulic stimulation operations using Form 42 (the appropriate COGCC individuals will automatically be email notified, including the LGD for hydraulic stimulation operations).
OGLAForm: (02A)
400466268
10/16/2013
Operator must implement best management practices to contain any unintentional release of fluids, including any fluids conveyed via temporary surface pipelines or buried permanent pipelines. Operator must ensure secondary containment for any volume of fluids contained at well site during drilling and completion operations; including, but not limited to, construction of a berm or diversion dike, diversion/collection trenches within and/or outside of berms/dikes, site grading, or other comparable measures (i.e., best management practices (BMPs) associated with stormwater management) sufficiently protective of nearby surface water. Any berm constructed at the well pad location will be stabilized, inspected at regular intervals (at least every 14 days), and maintained in good condition. The access road will be maintained as to not allow any sediment to migrate from the access road to nearby surface water or any drainages leading to surface water. Strategically apply fugitive dust control measures, including enforcing established speed limits on private roads, to reduce fugitive dust and coating of vegetation and deposition in water sources. Berms or other containment devices shall be constructed to be sufficiently impervious (preferably corrugated steel with poly liner) to contain any spilled or released material around crude oil, condensate, and produced water storage tanks.
OGLAForm: (02A)
400466268
10/16/2013
The moisture content of any cuttings in a cuttings pit, trench, or pile shall be as low as practicable to prevent accumulation of liquids greater than de minimis amounts. At the time of closure, if the drill cuttings are to be left onsite, they must also meet the applicable standards of table 910-1. Flowback and stimulation fluids must be sent to tanks, separators, or other containment/filtering equipment before the fluids can be placed into any pipeline, storage vessel, or lined pit (only if an amended Form 2A has been submitted/approved and a Form 15 Earthen Pit Permitted has been submitted/approved) located on the well pad; or into tanker trucks for offsite disposal. The flowback and stimulation fluid tanks, separators, or other containment/filtering equipment must be placed on the well pad in an area with additional downgradient perimeter berming. The area where flowback fluids will be stored/reused must be constructed to be sufficiently impervious to contain any spilled or released material. Operator shall pressure test pipelines in accordance with Rule 1101.e.(1) prior to putting into initial service any temporary surface or permanent buried pipelines and following any reconfiguration of the pipeline network. Operator shall notify the COGCC Oil and Gas Location Assessment (OGLA) Specialist for Western Colorado (Dave Kubeczko; email dave.kubeczko@state.co.us) and the COGCC Field Inspection Supervisor for Northwest Colorado (Shaun Kellerby; email shaun.kellerby@state.co.us) 48 hours prior to testing surface or buried poly/steel pipelines. Operator must implement best management practices to contain any unintentional release of fluids along all portions of the surface pipeline route where temporary pumps and other necessary equipment are located. Operator must routinely inspect the entire length of the surface pipeline to ensure integrity. Operator shall conduct daily inspections of surface poly pipeline routes for leaks during active transfer of fluids. Inspections shall be conducted by viewing the length of the pipeline; operator will endeavor to minimize surface disturbance during pipeline monitoring. The operator shall maintain records of inspections, findings and repairs, if necessary, for the life of the pipelines. Operator must ensure appropriate secondary containment for volume of fluids that may be released before pump shut down from the surface pipeline at all stream, intermittent stream, ditch, and drainage crossings. Catchment basins, if needed, should be sized to contain the volume between pump stations or between the nearest pump station and the frac pad being used for this well pad location. Pump stations along the surface poly or steel pipeline route will be continuously monitored when operating in order to swiftly respond to such a failure. Operator will utilize, to the extent practical, all existing access and other public roads, and/or existing pipeline right-of-ways, when placing/routing the surface pipelines. This will reduce surface disturbance and fragmentation of wildlife habitat in the area.
 
COGIS - Best Management Practice Results
BMP TypeSource DocumentBest Management Practices
PlanningForm: (02A )
400466268
12/15/2013
* Originally, a new pad was being proposed to drill these wells in the NWNW Section 13 T7S R 96W. With further review, it was determined that this existing GM 24-12 pad could be used to reach the bottom holes of interest. This existing pad is further away from building units than the new pad would have been (<500'). * Will use existing pipeline corridors for new pipelines. * Other existing pads in the area are as close if not closer to building units but farther away from bottom holes making it infeasible to drill from these locations. * Share/consolidate corridors for pipeline ROWs to the maximum extent possible. * Minimize newly planned activities and operations within 300 feet of the ordinary high water mark of any reservoir, lake, wetland, or natural perennial or seasonally flowing stream or river. * Locate roads outside of drainages where possible and outside of riparian habitat. * Avoid constructing any road segment in the channel of an intermittent or perennial stream * Minimize the number, length, and footprint of oil and gas development roads * Use existing roads where possible * Combine utility infrastructure (gas, electric, and water) planning with roadway planning to avoid separate utility corridors * Combine and share roads to minimize habitat fragmentation * Where possible, consolidate pipeline and existing roadways, or roadways that are planned for development * Maximize the use of directional drilling to minimize habitat loss/fragmentation * Maximize use of remote completion/frac operations to minimize traffic * Maximize use of remote telemetry for well monitoring to minimize traffic
Traffic controlForm: (02A )
400466268
12/15/2013
* Most likely, CR 215 to the new Town of Parachute bypass road (to avoid going through town) will be used to get to the pad. The Town of Parachute has agreed to this route. Another route is possible for the rig (Hwy 6 to lease road) if the rig that is scheduled to drill this pad is changed. In that case, the appropriate state, county, and town official would be contacted and permits obtained. This would also be done 1-2 weeks prior to rig moving on location. Pilot cars, in either case, will be used to get the larger rig traffic to location.
General HousekeepingForm: (02A )
400466268
12/15/2013
* All garbage and trash will be stored in enclosed trash containers and removed and deposited in an approved sanitary landfill within one week following termination of drilling operations. No garbage or trash will be disposed of in the cuttings management area. The well site and access road will be kept free of trash and debris at all times.
WildlifeForm: (02A )
400466268
12/15/2013
* Use only certified weed-free native seed in seed mixes, except for non-native plants that benefit wildlife * Install exclusionary devices to prevent bird and other wildlife access to equipment stacks, vents and openings. * Reduce visits to well-sites through remote monitoring (i.e. SCADA) and the use of multi-function contractors. * By using an existing pad we have minimized the number, size and distribution of well pads and locate pads along existing roads where possible. * Water for completions operations will be piped from an existing water pit which will reduce truck traffic.
Storm Water/Erosion ControlForm: (02A )
400466268
12/15/2013
* Strip and segregate topsoil prior to construction. Appropriately configure topsoil piles and immediately seed to control erosion, prevent weed establishment and maintain soil microbial activity
Storm Water/Erosion ControlForm: (02A )
400466268
12/15/2013
* Onsite and offsite erosion control, re-vegetation of disturbed areas and source and storage of topsoil BMP’s will be installed prior to, during and immediately following construction as practicable with consideration given to safety, access, and ground conditions at the time of construction. Due to the nature of the topography at various sites, any number of BMP combinations may be utilized at any phase of the project. Constant efforts will be employed to limit the extent of vegetative disturbance at the time of soil exposure during all construction activities and structural BMP implementation. Stormwater is addressed under a field-wide CDPHE plan/permit.
Material Handling and Spill PreventionForm: (02A )
400466268
12/15/2013
* Automated high tank alarms are installed on tanks along with emergency shut down systems. * In addition to 2-3 times/week onsite inspections by pumpers they also have routine quarterly checklists that are filled out and kept on file regarding dump line/flow line pressures and also a checklist done for everthing regarding compliance at the wellhead and production equipment. * Pallets and materials (drilling and production materials and supplies) that are stored on the pallets are kept > 25' from wellheads during production and drilling operations.
Dust controlForm: (02A )
400466268
12/15/2013
* Fugitive dust control will be implemented during all phases of operations on an as-needed basis.
ConstructionForm: (02A )
400466268
12/15/2013
* Salvage topsoil from all road construction and other rights-of-way and re-apply during interim and final reclamation.
Noise mitigationForm: (02A )
400466268
12/15/2013
* The mufflers on the rig will be oriented to point to the north thus directing the noise from the engines away from the residential building units. * Plumb dump lines into tanks to muffle sound * Rubber cushions in lubricators are used to muffle sound for plunger lift
Emissions mitigationForm: (02A )
400466268
12/15/2013
* Combusters and we use API tanks with thief hatches and enardo valves and pipe everything to the combustion unit.
Odor mitigationForm: (02A )
400466268
12/15/2013
* We use Combusters and API tanks with thief hatches and enardo valves and pipe everything to the combustion unit.
Drilling/Completion OperationsForm: (02A )
400466268
12/15/2013
* Water for completions operations will be piped from an existing water pit which will reduce truck traffic. * Use centralized hydraulic fracturing operations. * Install and maintain adequate measures to exclude all types of wildlife (e.g., big game, birds, and small rodents) from all fluid pits (e.g., fencing, netting, and other appropriate exclusion measures). * Conduct well completions with drilling operations to limit the number of rig moves and traffic.
Interim ReclamationForm: (02A )
400466268
12/15/2013
* As soon as possible after (within 6 mos) well is placed on first sales perform interim reclamation on all disturbed areas not needed for active support of production operations. * Seed during appropriate season to increase likelihood of reclamation success * Conduct seeding in a manner that ensures that seedbed preparation and planting techniques are targeted toward the varied needs of grasses, forbs and shrubs (e.g., seed forbs and shrubs separately from grasses, broadcast big sagebrush but drill grasses, etc.) * Remove well pad and road surface materials that are incompatible with post-production land use and re-vegetation requirements * Use only certified weed-free native seed in seed mixes, except for non-native plants that benefit wildlife * WPX Energy will use certified, weed free grass hay, straw, hay or other mulch materials used for the reseeding and reclamation of disturbed areas. * Install exclusionary devices to prevent bird and other wildlife access to equipment stacks, vents and openings. * Reduce visits to well-sites through remote monitoring (i.e. SCADA) and the use of multi-function contractors.
Final ReclamationForm: (02A )
400466268
12/15/2013
* Will complete final reclamation activities so that seeding occurs during the first optimal season following plugging and abandonment of oil and gas wells.
PlanningForm: (02A )
400569748
5/31/2014
Share/consolidate corridors for pipeline ROWs to the maximum extent possible. Minimize newly planned activities and operations within 300 feet of the ordinary high water mark of any reservoir, lake, wetland, or natural perennial or seasonally flowing stream or river. Locate roads outside of drainages where possible and outside of riparian habitat. Avoid constructing any road segment in the channel of an intermittent or perennial stream. Minimize the number, length, and footprint of oil and gas development roads. Use existing roads where possible. Combine utility infrastructure (gas, electric, and water) planning with roadway planning to avoid separate utility corridors. Combine and share roads to minimize habitat fragmentation. Where possible, consolidate pipeline and existing roadways, or roadways that are planned for development. Maximize the use of directional drilling to minimize habitat loss/fragmentation. Maximize use of remote completion/frac operations to minimize traffic. Maximize use of remote telemetry for well monitoring to minimize traffic. Will use existing pipeline corridors for new pipelines.
Traffic controlForm: (02A )
400569748
5/31/2014
Most likely, CR 215 to the new Town of Parachute bypass road (to avoid going through town) will be used to get to the pad. The Town of Parachute has agreed to this route. Another route is possible for the rig (Hwy 6 to lease road) if the rig that is scheduled to drill this pad is changed. In that case, the appropriate state, county, and town official would be contacted and permits obtained. This would also be done 1-2 weeks prior to rig moving on location. Pilot cars, in either case, will be used to get the larger rig traffic to location.
General HousekeepingForm: (02A )
400569748
5/31/2014
All garbage and trash will be stored in enclosed trash containers and removed and deposited in an approved sanitary landfill within one week following termination of drilling operations. No garbage or trash will be disposed of in the cuttings management area. The well site and access road will be kept free of trash and debris at all times.
WildlifeForm: (02A )
400569748
5/31/2014
Use only certified weed-free native seed in seed mixes, except for non-native plants that benefit wildlife. Install exclusionary devices to prevent bird and other wildlife access to equipment stacks, vents and openings. Reduce visits to well-sites through remote monitoring (i.e. SCADA) and the use of multi-function contractors. By using an existing pad we have minimized the number, size and distribution of well pads and locate pads along existing roads where possible. Water for completions operations will be piped from an existing water pit which will reduce truck traffic.
Storm Water/Erosion ControlForm: (02A )
400569748
5/31/2014
Strip and segregate topsoil prior to construction. Appropriately configure topsoil piles and immediately seed to control erosion, prevent weed establishment and maintain soil microbial activity.
Storm Water/Erosion ControlForm: (02A )
400569748
5/31/2014
Onsite and offsite erosion control, re-vegetation of disturbed areas and source and storage of topsoil BMP’s will be installed prior to, during and immediately following construction as practicable with consideration given to safety, access, and ground conditions at the time of construction. Due to the nature of the topography at various sites, any number of BMP combinations may be utilized at any phase of the project. Constant efforts will be employed to limit the extent of vegetative disturbance at the time of soil exposure during all construction activities and structural BMP implementation. Stormwater is addressed under a field-wide CDPHE plan/permit.
Material Handling and Spill PreventionForm: (02A )
400569748
5/31/2014
Automated high tank alarms are installed on tanks along with emergency shut down systems. In addition to 2-3 times/week onsite inspections by pumpers they also have routine quarterly checklists that are filled out and kept on file regarding dump line/flow line pressures and also a checklist done for everthing regarding compliance at the wellhead and production equipment. Pallets and materials (drilling and production materials and supplies) that are stored on the pallets are kept > 25' from wellheads during production and drilling operations.
Dust controlForm: (02A )
400569748
5/31/2014
Fugitive dust control will be implemented during all phases of operations on an as-needed basis.
ConstructionForm: (02A )
400569748
5/31/2014
Salvage topsoil from all road construction and other rights-of-way and re-apply during interim and final reclamation.
Noise mitigationForm: (02A )
400569748
5/31/2014
The mufflers on the rig will be oriented to point to the north thus directing the noise from the engines away from the residential building units. Plumb dump lines into tanks to muffle sound. Rubber cushions in lubricators are used to muffle sound for plunger lift.
12