LOCATION334681Federal
29-6BB (PF-29)
QB ENERGY OPERATING LLC
10844
AC
12/6/2012
PARACHUTE
67350
GARFIELD  045
SENW 29 7S95W 6
334681View Related
 
COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
OGLAForm: (02A)
400215348
10/27/2011
SITE SPECIFIC COAs: Operator must implement best management practices to contain any unintentional release of fluids, including any fluids conveyed via temporary surface or buried pipelines. Operator must ensure secondary containment for any volume of fluids contained at well site during drilling and completion operations; including, but not limited to, construction of a berm or diversion dike, diversion/collection trenches within and/or outside of berms/dikes, site grading, or other comparable measures (i.e., best management practices (BMPs) associated with stormwater management) sufficiently protective of nearby surface water. Any berm constructed at the well pad location will be stabilized, inspected at regular intervals (at least every 14 days), and maintained in good condition. Flowback and stimulation fluids must be sent to tanks, separators, or other containment/filtering equipment before the fluids can be placed into any pipeline or pit located on the well pad or into tanker trucks for offsite disposal. The flowback and stimulation fluid tanks, separators, or other containment/filtering equipment must be placed on the well pad in an area with additional downgradient perimeter berming. The area where flowback fluids will be stored/reused must be constructed to be sufficiently impervious to contain any spilled or released material. The moisture content of any drill cuttings in a cuttings pit, trench, or pile shall be as low as practicable to prevent accumulation of liquids greater than de minimis amounts.
 
COGIS - Best Management Practice Results
BMP TypeSource DocumentBest Management Practices
WildlifeForm: (02A )
400215348
11/29/2011
All wildlife stipulations and best management practices that apply, are applicable and that have been agreed to with the BLM, and are presented in our approved South Parachute Geographic Area Plan for Oil and Gas Development (EA#COC140-2006-050) will be followed.