| Agency | Form: (02A) 2094413 03/18/2010 | Operator must implement best management practices to contain any unintentional release of fluids. |
| Agency | Form: (02A) 2094413 03/18/2010 | Location is in a sensitive area because of close proximity to surface water, therefore, operator must ensure 110 percent secondary containment for any volume of fluids contained at well site during drilling and completion operations. |
| Agency | Form: (02A) 2094413 03/18/2010 | No portion of any pit that will be used to hold liquids shall be constructed on fill material, unless the pit and fill slope are designed and certified by a professional engineer, subject to review and approval by the director prior to construction of the pit. The construction and lining of the pit shall be supervised by a professional engineer or their agent. The entire base of the pit must be in cut. |
| Agency | Form: (02A) 2094413 03/18/2010 | The moisture content of any drill cuttings in a cuttings pit, trench, or pile shall be as low as practicable to prevent accumulation of liquids greater than de minimis amounts. At the time of closure, the drill cuttings must also meet the applicable standards of table 910-1. |
|
| PROPOSED BMPs | Form: (07 ) 0 1/23/2012 | PROPOSED BMP's
LARAMIE ENERGY II, LLC
West Mamm Project
Sec. 29 & 32, Twn 7S, Rng 93W 6" PM
Sec. 5, Twn. 8S, Rng. 93W 6 ' PM
Garfield County, CO
Locations
Johnson 32 -03 Pad Johnson 05 -03 Pad
Johnson 05 -05 Pad Johnson 05 -06 Pad
Johnson 05 -07 Pad
Stormwater Management
Stormwater Management will be managed under (Laramie Energy II) LE II's Stormwater Management Plan known as the "West Mamm Creek Project" under CDPHE General Permit No. COR- 03E157. The permit and will be amended to include any additional disturbance.
Prior to construction a stormwater "perimeter" will be built around the site for initial work purposes. Once the pad construction is completed, LE II's Stormwater Administrator will inspect the site and install any necessary Erosion Control Devices to manage sediment discharge from the pad. These devices may include but are not limited to:
- Rock Check dams
- Settling ponds
- Straw waddles
- Silt Fencing (used sparingly)
Once the final stormwater Erosion Control Devices are installed they will be mapped in GIS and a diagram of the site will be drafted and included as part of the Stormwater Documentation as required by the CDPHE General Permit.
Each site will be inspected every 14 days and 72 hrs after any major storm event. These inspections will be recorded and documented in the Stormwater Manual onsite and any necessary repairs or modifications will be made and documented.
Spill Prevention Control and Counter Measures(SPCC)
Once the wells are drilled and completed onsite Laramie Energy II's "West Mamm Creek" SPCC plan will be amended to include the sites as part of the plan.
LARAMIE ENERGY II, LLC iOGCC
Best Management Practices (BMP's)
To Reduce Impacts to Wildlife
For Operations in the
Piceance Basin
In an effort to minimize the impacts to wildlife, the following BMP's are part of Laramie Energy II's (LEII) standard operating procedures for drilling and operations within the Piceance Basin. This list is a partial of LEII's policy. LEII will attempt to incorporate as much as possible the CDOW's "Actions to Minimize Adverse Impacts to Wildlife Resources" as dated October 27, 2008, unless those actions will impede upon LEII's lease rights and the wishes of surface owners who LEII has signed Surface Use and
Access Agreements (SUA's).
Initial Stages for Infrastructure and Roads
1. Road design and General
- No firearms, no dogs on location, and no feeding of wildlife.
- Minimize the amount of traffic on lease roads within 3 hours of sunrise and sunset.
- Use existing routes as much as possible to avoid new disturbance and habitat fragmentation and minimize new road construction.
- Maximize the topography as much as possible in designing roads to reduce, visual, noise, impacts, etc.
- Participate in road sharing agreements with other Operators when possible.
- Design and surface roads based on the traffic, speed, and type of vehicles to reduce, dust, mud,and environmental damage.
- Locate roads away from riparian areas and bottoms of drainages as much as possible or re -route entirely.
- Obtain Army Corp of Engineer Permits for any stream crossings prior to construction.
- Analyze crossings and flow characteristics to determine the best method of crossing, (i.e. culvert,bridge, or low water).
- Armor all stream crossings to reduce erosion and to comply with Stormwater Requirements.
- Implementation of fugitive dust control measures including but not limited to water or magnesium chloride applications, and road surfacing.
- Limit traffic to the minimum needed for safe and efficient operations.
- No driving or parking off of disturbed areas.
- Install and use locked gates or other means when allowed by landowner or Federal Agencies to prevent unauthorized travel on roads and rights -of ways.
2. Well pad design and location
- Locate well pads to maximize directional drilling practices. LEII currently plans and attempts to locate pads for 16 -20 wells which equates to roughly 4 well pads per section.
- Design each location to accommodate both current and future gas production.
- Locate well pads to minimize disturbance yet maximize use to reduce surface impacts.
- Review State and Federal GIS mapping to avoid Sensitive Wildlife Habitat (SWH), Restricted Surface Occupancy (RSO) areas, steep slopes, etc., as much as possible with roads and pad location.
- Design and install gathering lines within the disturbed area of new roads and adjacent to as much as possible to reduce disturbance construction.
|
| PROPOSED BMPs | Form: (07 ) 0 1/23/2012 | -Design Rights -of Way widths to the minimum needed for safe and efficient construction of pipelines
-Remote Telemetry for production operations
3. Drilling and Production Operations
-Implement remote telemetry in all operations
- Where topographically possible and subject to landowner approval, use centralized water gathering and transportation systems.
- Install exclusionary devices to prevent bird and other wildlife access to equipment stacks, vents,and openings.
- Locate facilities to minimize visual effects (e.g. paint color, screening, etc.)
- LEII implements a closed system in its operations. No fluid pits are constructed or used during drilling or completion operations.
- LEII implements an aggressive weed management program. LEII incorporates and uses the BLM Glenwood Springs Energy Office's "Noxious and Invasive Weed Management Plan for Oil
and Gas Operators- March 2007" for all operations. Each spring, Laramie inventories all pads, roads, and pipelines to insure no noxious weeds have been introduced. If noxious weeds are found, the county will be notified and the weeds will be treated. Weeds are continuously monitored and treated throughout the growing season. Only herbicides approved by the EPA and State are used by certified weed applicators.
4. Reclamation
- Strip and segregate topsoil from other soil horizons during pad, road, and pipeline construction.
- Minimize topsoil degradation by windrowing no higher than 5 feet when possible.
- Immediately seed topsoil to reduce erosion and prevent weed establishment and maintain soil microbial activity.
- Use only certified weed free native seed mixes, unless recommended otherwise by Federal Agencies or the Landowner.
- Use locally adapted seed when available.
- Use diverse seed mixes to mirror the surrounding area unless recommended otherwise by Federal Agencies or the Landowner.
- Monitor re- vegetation success until a minimum of 75% of preferred perennial plant cover (no weeds) is established.
- Perform "interim" reclamation on all disturbed areas not needed for active producing operatios.
- If possible, conduct interim and final reclamation during optimum periods (e.g. late fall/early winter or early spring).
- If needed, fence reclaimed areas to minimize livestock/wildlife impact until plant species have are capable of sustaining grazing.
LARAME ENERGY II, LLC
BMPS FOR
Sensitive Wildlife Habitat and Restricted Surface Occupancy
Areas Specific to Laramie Energy II, LLC
Operations Within the Piceance Basin
Garfield County, CO
Sensitive Wildlife Habitat (SWH)
Black Bear
• Initiate a food and waste /refuse management program that uses bear -proof food storage containers and trash receptacles.
• Initiate an education program that reduces bear conflicts.
• Establish policy to prohibit keeping food and trash in sleeping quarters.
• Establish policy to support enforcement of state prohibition on feeding of black bear.
• Report bear conflicts immediately to CDOW.
Deer and Elk
• Consult with CDOW GIS and Federal GIS database at the initial stage of development to identify the locations of mule deer and elk important wintering habitats and production areas. Attempt to avoid any critical habitat patches with roads and development.
• Attempt to avoid oil and gas activities within mule deer critical winter range, elk winter concentration areas, elk production areas, and migration corridors.
• Attempt to conduct post - development well site visitations between the hours of 10:00 a.m. and 3:00 p.m. and reduce well site visitations between December 1 and April 15 in mule deer critical winter range and elk winter concentration areas.
• Phase and concentrate all development activities, so that large areas of undisturbed habitat for wildlife remain and thorough reclamation occurs immediately after development and before moving to new sites. Development should progress at a pace commensurate with reclamation success.
• Gate single - purpose roads and restrict general public access to reduce traffic disruptions to wildlife.
• Avoid aggressive non - native grasses and shrubs in mule deer and elk habitat restoration.
• Reclaim mule deer and elk habitats with native shrubs, grasses, and (orbs appropriate to the ecological site disturbed.
• Restore appropriate sagebrush species or subspecies on disturbed sagebrush sites. Use locally collected seed for reseeding where possible.
|
|