COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
OGLAForm: (02A)
401685655
07/31/2018
Material Handling and Spill Prevention: The following COAs will apply to this Form 2A Permit if any temporary surface (COAs 45, 49, 54, and 55) or buried permanent (COA 45) flowlines and/or offsite pipelines (poly or steel) are used during operations at this oil and gas location: COA 45 - Operator shall pressure test pipelines (flowlines from wellheads to separators to blowdown tank; pipelines from onsite separators to offsite storage tanks, and any temporary surface lines used for hydraulic stimulation and/or flowback operations) in accordance with Rule 1101.e.(1) prior to putting into initial service any temporary surface or permanent buried pipelines and following any reconfiguration of the pipeline network, and tested annually. COA 49 - Operator must routinely inspect the entire length of the surface pipeline to ensure integrity. Operator shall conduct daily inspections of surface poly pipeline routes for leaks during active transfer of fluids and implement best management practices to contain any unintentional release of fluids along all portions of the surface pipeline route where temporary pumps and other necessary equipment are located. Inspections shall be conducted by viewing the length of the pipeline; operator will endeavor to minimize surface disturbance during pipeline monitoring. In addition, pump stations along the surface poly or steel pipeline route will be continuously monitored when operating in order to swiftly respond to such a failure. COA 54 - Operator will implement BMPs necessary to mitigate a potential for a release of fluids to impact streams, intermittent streams, ditches, and drainage crossings. For these crossings: if poly pipe is used on the surface, operator will ensure appropriate containment by either installing over-sized pipe “sleeves” which extend the length of the crossing and beyond to a distance deemed adequate to capture (catchment basins) and/or divert any possible release of fluids and prevent fluids from reaching the stream or drainage; installing over-sized pipe “sleeves” which extend the length of the crossing and installing shut off valves on either side of crossing instead of catchment basins; or develop an alternative means for containment. For all other pipeline materials, operator will implement BMPs necessary to mitigate a potential for E&P fluids not to reach groundwater or flowing surface water. COA 55 - Operator will utilize, to the extent practical, all existing access and other public roads, and/or existing pipeline right-of-ways, when placing/routing the temporary surface pipelines. This will reduce surface disturbance and fragmentation of wildlife habitat in the area.
OGLAForm: (02A)
401685655
07/31/2018
Drilling/Completions: The following COAs will apply: COA 11 - The moisture content of water/bentonite based mud (WBM) generated drill cuttings managed onsite shall be kept as low as practicable to prevent accumulation of liquids greater than de minimis amounts. COA 25 - Flowback and stimulation fluids must be sent to enclosed tanks, separators, or other containment/filtering equipment before the fluids can be placed into any pipeline, storage vessel, or into tanker trucks for offsite disposal. No open top tanks can be used for flowback fluids containment. The flowback and stimulation fluid tanks, separators, or other containment/filtering equipment must be placed on the well pad in an area constructed to be sufficiently impervious to contain any spilled or released material. No additional downgradient berming is required if operator constructs a sufficiently sized perimeter berm.
OGLAForm: (02A)
401685655
07/31/2018
Construction: The following COAs will apply: COA 48 - Since only one (1) blowdown tank is planned to be constructed on location, operator shall submit a scaled as-built drawing (plan view with distances) of this oil and gas location (showing wellheads, onsite flowlines, offsite pipelines, separators, combustors, etc.) and the nearby production and storage tank facility locations to which the condensate and produced water will be sent to via underground pipelines (showing onsite flowlines, offsite pipelines, condensate and produced water storage tanks, and other production facilities - combustors, etc.) within 60 calendar days of construction of the production equipment on either or both locations.
EnvironmentalForm: (04)
401806597
11/16/2018
The moisture content of any drill cuttings transported from the GV 1-8 (Location ID 323823) to the Federal GM 41-8 pad (Location ID 334794) Cutting for management and final disposition shall be as low as practicable to prevent accumulation of liquids greater than de minimis amounts, and to prevent spillage out of trucks during transport.
EnvironmentalForm: (04)
401806597
11/16/2018
Within 45-days of completion of the managment of cuttings generated from the GV 1-8 (Location ID 323823). The Operator shall provide a report detailing the API numbers, the volume of cuttings generated, and the actual cuttings managment process that was performed including sampling actitivities, and anlaytical results.
EnvironmentalForm: (04)
401806597
11/16/2018
The Operator shall adhere to the BLM COAs that were provided to them at the Federal GM 41-8 pad (Location ID 334794).
 
COGIS - Best Management Practice Results
BMP TypeSource DocumentBest Management Practices
PlanningForm: (02A )
401685655
9/18/2018
- Combine and share roads to minimize habitat loss/fragmentation - Use existing roads where possible - Combine utility infrastructure (gas, electric, and water) planning with roadway planning to avoid separate utility corridors - Where possible, consolidate pipeline and existing roadways, or roadways that are planned for development - Maximize the use of directional drilling to minimize habitat loss/fragmentation - Maximize use of long-term centralized tank batteries to minimize traffic - Maximize use of remote completion/frac operations to minimize traffic - Maximize use of remote telemetry for well monitoring to minimize traffic
Drilling/Completion OperationsForm: (02A )
401685655
9/18/2018
- Use centralized hydraulic fracturing operations. - TEP will ensure 110 percent secondary containment for any volume of fluids contained at the well site during drilling and completions operations. - TEP will implement best management practices to contain any unintentional release of fluids. - Either a lined drilling pit or closed loop system will be implemented.
Interim ReclamationForm: (02A )
401685655
9/18/2018
- Utilize staked soil retention blankets for erosion control and reclamation of large surface areas with 1.5:1 or steeper slopes. Avoid use of plastic blanket materials. - Remove well pad and road surface materials that are incompatible with post-production land use and re-vegetation requirements. - Use only certified weed-free native seed in seed mixes, except for non-native plants that benefit wildlife - TEP will use certified, weed free grass hay, straw, hay or other mulch materials used for the reseeding and reclamation of disturbed areas. - Install exclusionary devices to prevent bird and other wildlife access to equipment stacks, vents and openings. - Reduce visits to well-sites through remote monitoring (i.e. SCADA) and the use of multi-function contractors.