General Housekeeping | Form: (02A ) 400592772 6/4/2014 | Any material not in use that might constitute a fire hazard will be removed a minimum of twenty-five (25) feet from the tanks and separator. Any electrical equipment installations inside the bermed area will comply with API RP 500 classifications and comply with the current national electrical code as adopted by the State of Colorado.
|
General Housekeeping | Form: (02A ) 400592772 6/4/2014 | All surface trash, debris, scrap or discarded material connected with the operations of the property shall be removed from the premises or disposed of in a legal manner.
|
Material Handling and Spill Prevention | Form: (02A ) 400592772 6/4/2014 | • Annual hydrostatic test on the oil dump line from the separator to the tank battery.
• Annual hydrostatic “static” tests on our oil tanks.
• Annual hydrostatic “static” tests on our produced water tank and water dump line from the separator to the produced water tank.
• Lease Operator inspections of all equipment not to exceed 48 hours.
• Monthly documented inspections (EU).
• Annual environmental inspections of all battery and well equipment and pads.
• Annual UT inspections of the pressure vessels and input into Encana’s RIPL Predictive Integrity Maintenance Program. (HLP separators and fuel gas separators)
|
Material Handling and Spill Prevention | Form: (02A ) 400592772 6/4/2014 | Well effluent containing more than ten (10) barrels per day of condensate or within two (2) hours after first encountering hydrocarbon gas of salable quality will be directed to a combination of sand traps, separators, surge vessels, and tanks as needed to ensure safe separation of sand, hydrocarbon liquids, water, and gas and to ensure salable products are efficiently recovered for sale or conserved and that non-salable products are disposed of in a safe and environmentally responsible manner.
|
Construction | Form: (02A ) 400592772 6/4/2014 | This site will be constructed using a liner. |
Construction | Form: (02A ) 400592772 6/4/2014 | This location will have all weather access roads to allow for operator and emergency response.
|
Drilling/Completion Operations | Form: (02A ) 400592772 6/4/2014 | All newly installed or replaced crude oil and condensate storage tanks will be designed, constructed, and maintained in accordance with National Fire Protection Association (NFPA) Code 30 (2008 version). Encana will maintain written records verifying proper design, construction, and maintenance, and will make these records available for inspection by the Director. In addition, onsite inspections are conducted internally to insure guidelines are met.
|