COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
AgencyForm: (02A)
400024625
02/19/2010
Visits to the well site will be reduced by the use of remote monitoring (i.e. SCADA) and the use of multi-function contractors. EnCana and its contractors will maximize the use of state-of-the-art drilling technology when available to minimize disturbance. Post-development well site visitations will be conducted between the hours of 9:00 a.m. and 4:00 p.m. during December 1 and April 15 in mule deer critical winter range. On the occasion that well conditions are not stabilized, EnCana will be allowed to work any hours during the day or year, as necessary to stabilize the well. This BMP excludes fluid movement in order to protect the environment and workovers required for maintenance of the well. Hours for well site visits will not be restricted outside the mule deer critical winter range period of the December 1 to April 15.
Reclamation SpecialistForm: (04)
402525408
11/30/2020
The portion of Caerus Piceance LLC’s variance request waiver to not recontour and reclaim the access road is approved.
Reclamation SpecialistForm: (04)
402525408
11/30/2020
Per language within the SOVR, the portion of the variance request to not recontour the Location to its original relative position, is approved.
Reclamation SpecialistForm: (04)
402525408
11/30/2020
The areas labeled, “Reclaimed Disturbance”, as identified on the figures attached to this sundry, and any other areas disturbed by oil and gas not subject to the variance request, are subject to all COGCC 1000 series rule requirements including the requirement to establish 80% vegetation cover of reference area levels.
Reclamation SpecialistForm: (04)
402525408
11/30/2020
All corrective actions identified on a field inspection report must be performed by the corrective action date until final reclamation is passed.
Reclamation SpecialistForm: (04)
402525408
11/30/2020
Continue to monitor and manage the site for erosion, weed control & establishment of vegetation until final reclamation is passed.
Reclamation SpecialistForm: (04)
402525408
11/30/2020
Stormwater controls shall be installed and maintained in accordance with good engineering practice for long-term erosion control.
Reclamation SpecialistForm: (04)
402525408
11/30/2020
Approval of the variance request does not absolve the Operator from enforcement due to past or future non-compliance with the rules or COAs.
Reclamation SpecialistForm: (04)
402525408
11/30/2020
Upon approval of this variance request, Caerus Piceance LLC will be required to gravel the access road as indicated within the variance request documents.
Reclamation SpecialistForm: (04)
402525408
12/28/2020
Continue compliance with all Rules not eligible for a variance until final reclamation has been passed.
Reclamation SpecialistForm: (04)
403150301
09/15/2022
Approval/Passing of the form 4 acknowledges that the Oil and Gas Conservation Commission has received the notice. It is not an acknowledgement that reclamation has been passed. A field inspection will be conducted at a future date to evaluate compliance with reclamation standards.
 
COGIS - Best Management Practice Results
BMP TypeSource DocumentBest Management Practices
Storm Water/Erosion ControlForm: (04 )
400769246
4/24/2017
"Encana will make use seasonal road maintenance in late summer or early fall, after the annual monsoon rains and prior to the fall hunting season. This road maintenance includes general blading to eliminate ruts and to reshape road surface in order to maintain the general public access of the road and to accommodate local emergency vehicle access requirements. Encana will also maintain any existing water bars or wing-ditches on the access road during this maintenance."
Storm Water/Erosion ControlForm: (04 )
400769246
4/24/2017
Encana has seeded the cut-slope of the location, and the vegatative growth will serve as a natural berm to mitigate erosin and sediment migration.
Storm Water/Erosion ControlForm: (04 )
400769246
4/24/2017
Encana will make use seasonal road maintenance in late summer or early fall, after the annual monsoon rains and prior to the fall hunting season. This road maintenance includes general blading to eliminate ruts and reshape road surface in order to maintain the general public access of the road and to accommodate local emergency vehicle access requirements. Encana will also maintain any existing water bars or wing-ditches on the access road during this maintenance