| Agency | Form: (02A) 400024625 02/19/2010 | Visits to the well site will be reduced by the use of remote monitoring (i.e. SCADA) and the use of multi-function contractors. EnCana and its contractors will maximize the use of state-of-the-art drilling technology when available to minimize disturbance. Post-development well site visitations will be conducted between the hours of 9:00 a.m. and 4:00 p.m. during December 1 and April 15 in mule deer critical winter range. On the occasion that well conditions are not stabilized, EnCana will be allowed to work any hours during the day or year, as necessary to stabilize the well. This BMP excludes fluid movement in order to protect the environment and workovers required for maintenance of the well. Hours for well site visits will not be restricted outside the mule deer critical winter range period of the December 1 to April 15. |
| Reclamation Specialist | Form: (04) 402525408 11/30/2020 | The portion of Caerus Piceance LLC’s variance request waiver to not recontour and reclaim the access road is approved. |
| Reclamation Specialist | Form: (04) 402525408 11/30/2020 | Per language within the SOVR, the portion of the variance request to not recontour the Location to its original relative position, is approved. |
| Reclamation Specialist | Form: (04) 402525408 11/30/2020 | The areas labeled, “Reclaimed Disturbance”, as identified on the figures attached to this sundry, and any other areas disturbed by oil and gas not subject to the variance request, are subject to all COGCC 1000 series rule requirements including the requirement to establish 80% vegetation cover of reference area levels. |
| Reclamation Specialist | Form: (04) 402525408 11/30/2020 | All corrective actions identified on a field inspection report must be performed by the corrective action date until final reclamation is passed. |
| Reclamation Specialist | Form: (04) 402525408 11/30/2020 | Continue to monitor and manage the site for erosion, weed control & establishment of vegetation until final reclamation is passed. |
| Reclamation Specialist | Form: (04) 402525408 11/30/2020 | Stormwater controls shall be installed and maintained in accordance with good engineering practice for long-term erosion control. |
| Reclamation Specialist | Form: (04) 402525408 11/30/2020 | Approval of the variance request does not absolve the Operator from enforcement due to past or future non-compliance with the rules or COAs. |
| Reclamation Specialist | Form: (04) 402525408 11/30/2020 | Upon approval of this variance request, Caerus Piceance LLC will be required to gravel the access road as indicated within the variance request documents.
|
| Reclamation Specialist | Form: (04) 402525408 12/28/2020 | Continue compliance with all Rules not eligible for a variance until final reclamation has been passed.
|
| Reclamation Specialist | Form: (04) 403150301 09/15/2022 | Approval/Passing of the form 4 acknowledges that the Oil and Gas Conservation Commission has received the notice. It is not an acknowledgement that reclamation has been passed. A field inspection will be conducted at a future date to evaluate compliance with reclamation standards. |