| UIC | Form: (31) 2493726 10/01/2015 | Initial maximum daily injection rate limited to 10,000 bbl/day. Operator must request
increase above that. Request will be evaluated based on existing daily injection rate
and seismic activity within 2.5 miles of the injection well. |
| UIC | Form: (31) 2493726 10/01/2015 | Operator is required to install a seismometer at a location to be determined by the
operator and COGCC from which seismic activity in the vicinity of the injection well can
be monitored. The operator will be responsible for maintenance of the seismometer.
Data gathered by the seismometer will be made available to one or more third parties
(such as the USGS, CU-Boulder, CSM, or CSU) for analysis. |
| UIC | Form: (31) 2493726 10/01/2015 | A water analysis to include TDS, major cations, and major anions is required 1- year
after initial injection and from then on at 5-year intervals. Water analyses should be
submitted via Sundry Notice and in Electronic Data Deliverable (EDD) Format. |