Planning | Form: (02A ) 400711489 3/3/2015 | 604c.(2).I. BOPE Testing: KPK will subcontract a testing company to test the BOPE and pipe once every 30 days or once per well for high pressure. Once installed, KPK will test the BOPE and ancillary equipment to 400 psi and 10% maximum leak off. |
Planning | Form: (02A ) 400711489 3/3/2015 | 604c.(2).U. – Abandoned Wells: All abandoned wells will be marked per Rule 319.a.(5) |
Planning | Form: (02A ) 400711489 3/3/2015 | 604c.(2).W. – Site-specific measures: A lighting plan will be used in order to minimize impact on any buildings if night operations are required. |
Traffic control | Form: (02A ) 400711489 3/3/2015 | 604c.(2).D. – Traffic: KPK obtains required permits from Weld County and the City of Ft. Lupton. |
General Housekeeping | Form: (02A ) 400711489 3/3/2015 | Housekeeping will consist of neat and orderly storage of materials and fluids. Wastes will be temporarily stored in sealed containers and regularly collected and disposed of at offsite suitable facilities according to WMP. If spills occur prompt cleanup is required to minimize any commingling of waste materials with storm water runoff. Routine maintenance will be limited to fueling and lubrication of equipment. Drip pans will be used during routine fueling and maintenance to contain spills or leaks. Any waste product from maintenance will be containerized and transported offsite for disposal at a certified facility. There will be no major equipment overhauls conducted onsite. Equipment will be transported offsite for major overhauls. Cleanup of trash and discarded materials will be conducted at the end of each workday. Cleanup will consist of patrolling the roadway, access areas, and other work areas to pick up trash, scrap debris, other discarded materials, any contaminated soil, and dust control on location. Materials will be disposed of properly. |
General Housekeeping | Form: (02A ) 400711489 3/3/2015 | 604c.(2).N. – Fire Hazards: KPK will remove unused flammable material and stored at least 25’ from the wellhead or electrical equipment. |
General Housekeeping | Form: (02A ) 400711489 3/3/2015 | 604c.(2).P. – Trash: All unused material, trash, debris, etc. will be hauled off location during production operations. A commercial bin will be installed on location during drilling and completion operations. |
General Housekeeping | Form: (02A ) 400711489 3/3/2015 | 604c.(2).T. – Abandoned Wellsite: Within 90 days after abandonment activities, all equipment, trash, debris, etc. will be removed from location. |
Storm Water/Erosion Control | Form: (02A ) 400711489 3/3/2015 | Storm water Management Plan (SWMP) will be in place to address construction and operations associated with oil and gas development throughout the state of Colorado in accordance with Colorado Department of Public Health and Environment (CDPHE) General Permit rules. |
Material Handling and Spill Prevention | Form: (02A ) 400711489 3/3/2015 | Spill Prevention Control and countermeasure plan (SPCC) is in place to address construction, drilling and operations associated with oil and gas development throughout the state of Colorado in accordance with CFR 112. |
Material Handling and Spill Prevention | Form: (02A ) 400711489 3/3/2015 | 604c.(2).F. – Leak Detection Plan: Leak detection plan is developed based on CDPHE Reg 3 and Reg 7 with a AVO inspection performed. |
Construction | Form: (02A ) 400711489 3/3/2015 | Secondary containment will be built with steel berms and liner for flood control.
Location is built sloped in the opposite direction of the river. Containment berms will be placed around tanks.
|
Construction | Form: (02A ) 400711489 3/3/2015 | 604c.(2).G. – Berms: All berms will be lined with a geosynthetic liner and metal berms capable of containing 150% of the largest tank installed. The production facility will be built sloped in the opposite direction of the river. |
Construction | Form: (02A ) 400711489 3/3/2015 | 604c.(2).Q. – Line Anchors: All anchors used for surface rigs will be flagged no less than 4’ in height. |
Construction | Form: (02A ) 400711489 3/3/2015 | 604c.(2).R. – Tanks: All new storage tanks will be installed based on NFPA Code 30. KPK will maintain records to verify proper design, construction and maintenance and will be made available upon request by the Director. |
Construction | Form: (02A ) 400711489 3/3/2015 | 604c.(2).S. – Access Roads: The existing access road will be improved to accommodate local emergency vehicle access requirements if necessary. |
Noise mitigation | Form: (02A ) 400711489 3/3/2015 | Production activities that are known to produce higher than normal noise levels, will be carried out during the day in order to minimize disturbance to neighboring houses.
The separation equipment will be installed as far as possible from the residence building, as agreed with the surface owner.
|
Drilling/Completion Operations | Form: (02A ) 400711489 3/3/2015 | 604c.(2).O. – Loadlines: All loadlines will be bullplugged or capped. |