| Engineer | Form: (02) 403310585 04/03/2023 | Operator acknowledges the proximity of the listed wells. Operator agrees to: provide mitigation option 1 or 2 (per the Offset Well Evaluation and Hydraulic Fracturing Operator Guidance Document) to mitigate the situation, ensure all applicable documentation is submitted based on the selected mitigation option chosen, and submit a Form 42 (“OFFSET MITIGATION COMPLETED”) stating that appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well.
123-07256 J J WARDELL 'B' #1
123-08284 ARISTOCRAT ANGUS #1
123-12844 WARDELL B #1
123-14230 HSR-KRANDEL #9-25
123-14986 WARDELL #18-12J
123-15046 UPRC #17-4J
123-15193 CAMP #30-12J
123-15204 CAMP #30-11J
123-15290 CAMP #30-3J
123-15291 CAMP #30-4J
123-15733 UPRC #19-15J
123-15734 UPRC #19-16J
123-15893 WARDELL #H 19-2J
123-16994 HSR-CAMP #4-31X
123-16996 UPRC #19-10J
123-17029 GLOVER #30-7J
123-17030 GLOVER #30-8J
123-17064 UPRC #19-9J
123-17602 WARDELL 7A #1
123-17609 WARDELL 7A #2
123-20502 HSR-REI #3-17A
123-22100 CAMP H #30-19
123-22153 UPRC H #19-23
123-25847 WARDELL #22-29
123-25848 WARDELL #25-29
123-25886 WARDELL #29-20
123-26199 BUTTERBALL H #30-27
123-27291 WARDELL #6-4-7
123-29168 HPD PLATTEVILLE #1
123-30000 CAMP H #30-28
123-31767 McGuckin H #31-29
123-31864 Camp H #30-32
123-35346 REI H #17-30D
123-35347 REI H #17-21D
123-39710 HPD PLATTEVILLE #2
123-40090 WARDELL #2G-19HZ |
| Engineer | Form: (02) 403310585 04/03/2023 | Operator acknowledges the proximity of the listed non-operated wells. Operator assures that this offset list will be remediated per the Offset Well Evaluation and Hydraulic Fracturing Operator Guidance Document Operator using Option 3. Operator will submit a Form 42 (“OFFSET MITIGATION COMPLETED”) stating what appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well.
123-16983 CAMP #30-6J
123-17091 CAMP #30-14J
123-08106 BOOKER, HAROLD E. #1 |
| Engineer | Form: (02) 403310585 04/03/2023 | Operator acknowledges the proximity of the listed non-operated wells. Operator assures that this offset list will be remediated per the Offset Well Evaluation and Hydraulic Fracturing Operator Guidance Document (option 4). Operator will submit a Form 42 (“OFFSET MITIGATION COMPLETED”) stating that appropriate mitigation will be completed, during the hydraulic stimulation of this well. This Form 42 shall be filed 48 hours prior to stimulation. Operator will equip the well with at least a 5,000 psi wellhead and monitor casing (surface and production) pressures during the entire stimulation treatment. Surface and production casing pressures of this offset well list will be actively monitored during the entire stimulation treatment of this pad. If there is indication of communication between the stimulation treatment and an offset well, treatment will be stopped and COGCC Engineering notified.
123-50640 Rifle Falls #10N
123-17090 CAMP #30-13J |
| Engineer | Form: (02) 403310585 04/03/2023 | 1) Submit Form 42 electronically to COGCC 2 business days prior to MIRU (spud notice) for the first well activity with a rig on the pad and provide 2 business day spud notice via Form 42 for all subsequent wells drilled on the pad.
2) Comply with Rule 408.j. and provide cement coverage from TD to a minimum of 500' above Niobrara and from 500’ below Sussex to 500’ above Sussex. Verify coverage with a cement bond log.
3) Oil based drilling fluid can only be used after all groundwater has been isolated. |
| Engineer | Form: (02) 403310585 04/03/2023 | Per COGCC Order 1-232, Bradenhead tests shall be performed according to the following schedule and Form 17 submitted within 10 days of each test:
1) Within 60 days of rig release, prior to stimulation. If any pressure greater than 200 psi is observed or if there is continuous flow, Operator must contact COGCC engineering for approval prior to stimulation.
2) If a delayed completion, a second test is required between 6-9 months after rig release and must be conducted prior to stimulation. If any pressure greater than 200 psi is observed or if there is continuous flow, Operator must contact COGCC engineering for approval prior to stimulation.
3) A post-production test within 60 days after first sales, as reported on the Form 10, Certificate of Clearance. |
| Permit | Form: (02) 403310585 04/05/2023 | Operator will log two (2) wells during the first rig occupation with open-hole resistivity log with gamma-ray log from the kick-off point into the surface casing for the two stratigraphically deepest wells on each side of the pad. |
| Permit | Form: (02) 403532280 09/18/2023 | Operator will log two (2) wells during the first rig occupation with open-hole resistivity log with gamma-ray log from the kick-off point into the surface casing for the two stratigraphically deepest wells on each side of the pad. |
| Engineer | Form: (02) 403532280 09/20/2023 | Operator acknowledges the proximity of the listed wells. Operator agrees to: provide mitigation option 1 or 2 (per the Offset Well Evaluation and Hydraulic Fracturing Operator Guidance Document) to mitigate the situation, ensure all applicable documentation is submitted based on the selected mitigation option chosen, and submit a Form 42 (“OFFSET MITIGATION COMPLETED”) stating that appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well.
123-07256 J J WARDELL 'B' #1
123-08284 ARISTOCRAT ANGUS #1
123-12844 WARDELL B #1
123-14230 HSR-KRANDEL #9-25
123-14986 WARDELL #18-12J
123-15046 UPRC #17-4J
123-15193 CAMP #30-12J
123-15204 CAMP #30-11J
123-15290 CAMP #30-3J
123-15291 CAMP #30-4J
123-15733 UPRC #19-15J
123-15734 UPRC #19-16J
123-15893 WARDELL #H 19-2J
123-16994 HSR-CAMP #4-31X
123-16996 UPRC #19-10J
123-17029 GLOVER #30-7J
123-17030 GLOVER #30-8J
123-17064 UPRC #19-9J
123-17602 WARDELL 7A #1
123-17609 WARDELL 7A #2
123-20502 HSR-REI #3-17A
123-22100 CAMP H #30-19
123-22153 UPRC H #19-23
123-25847 WARDELL #22-29
123-25848 WARDELL #25-29
123-25886 WARDELL #29-20
123-26199 BUTTERBALL H #30-27
123-27291 WARDELL #6-4-7
123-29168 HPD PLATTEVILLE #1
123-30000 CAMP H #30-28
123-31767 McGuckin H #31-29
123-31864 Camp H #30-32
123-35346 REI H #17-30D
123-35347 REI H #17-21D
123-39710 HPD PLATTEVILLE #2
123-40090 WARDELL #2G-19HZ
|
| Engineer | Form: (02) 403532280 09/20/2023 | Operator acknowledges the proximity of the listed non-operated wells. Operator assures that this offset list will be remediated per the Offset Well Evaluation and Hydraulic Fracturing Operator Guidance Document Operator using Option 3. Operator will submit a Form 42 (“OFFSET MITIGATION COMPLETED”) stating what appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well.
123-16983 CAMP #30-6J
123-17091 CAMP #30-14J
123-08106 BOOKER, HAROLD E. #1
|
| Engineer | Form: (02) 403532280 09/20/2023 | Operator acknowledges the proximity of the listed non-operated wells. Operator assures that this offset list will be remediated per the Offset Well Evaluation and Hydraulic Fracturing Operator Guidance Document (option 4). Operator will submit a Form 42 (“OFFSET MITIGATION COMPLETED”) stating that appropriate mitigation will be completed, during the hydraulic stimulation of this well. This Form 42 shall be filed 48 hours prior to stimulation. Operator will equip the well with at least a 5,000 psi wellhead and monitor casing (surface and production) pressures during the entire stimulation treatment. Surface and production casing pressures of this offset well list will be actively monitored during the entire stimulation treatment of this pad. If there is indication of communication between the stimulation treatment and an offset well, treatment will be stopped and COGCC Engineering notified.
123-50640 Rifle Falls #10N
123-17090 CAMP #30-13J
|
| Engineer | Form: (02) 403532280 09/20/2023 | 1) Submit Form 42 electronically to COGCC 2 business days prior to MIRU (spud notice) for the first well activity with a rig on the pad and provide 2 business day spud notice via Form 42 for all subsequent wells drilled on the pad.
2) Comply with Rule 408.j. and provide cement coverage from TD to a minimum of 500' above Niobrara and from 500’ below Sussex to 500’ above Sussex. Verify coverage with a cement bond log.
3) Oil based drilling fluid can only be used after all groundwater has been isolated.
|
| Engineer | Form: (02) 403532280 09/20/2023 | Per COGCC Order 1-232, Bradenhead tests shall be performed according to the following schedule and Form 17 submitted within 10 days of each test:
1) Within 60 days of rig release, prior to stimulation. If any pressure greater than 200 psi is observed or if there is continuous flow, Operator must contact COGCC engineering for approval prior to stimulation.
2) If a delayed completion, a second test is required between 6-9 months after rig release and must be conducted prior to stimulation. If any pressure greater than 200 psi is observed or if there is continuous flow, Operator must contact COGCC engineering for approval prior to stimulation.
3) A post-production test within 60 days after first sales, as reported on the Form 10, Certificate of Clearance.
|
| Engineer | Form: (04) 403855585 07/22/2024 | 1) Provide electronic Form 42 Notice of MIRU 2 business days ahead of operations.
2) Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well operations do not constitute a nuisance or hazard to public welfare.
|