COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
EngineerForm: (02)
402881462
01/20/2023
Operator acknowledges the proximity of the listed wells: Operator agrees to: provide mitigation option 1 or 2 (per the DJ Basin Horizontal Offset Policy) to mitigate the situation, ensure all applicable documentation is submitted based on the selected mitigation option chosen, and submit a Form 42 (“OFFSET MITIGATION COMPLETED”) for the remediated wells, referencing the API number of the proposed horizontal well(s) stating what appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well. Dillard A 4-4 (API NO 123-24185) Erickson 5-43 (API NO 123-18513) Erickson A 4-5 (API NO 123-23489) Cecil 32-34 (API NO 123-23809)
EngineerForm: (02)
402881462
01/20/2023
Operator acknowledges the proximity of the following non-operated listed wells: Operator agrees to: provide mitigation option 1 or 2 (per the DJ Basin Horizontal Offset Policy) to mitigate the situation, ensure all applicable documentation is submitted based on the selected mitigation option chosen, and submit a Form 42 (“OFFSET MITIGATION COMPLETED”) for the remediated wells, referencing the API number of the proposed horizontal well(s) stating what appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well. NC Farms 16-32 (API NO 123-34782) NC Farms 10-32 (API NO 123-34785) NC Farms 15-32 (API NO 123-34789) NC Farms 9-32 (API NO 123-34790) NC Farms 20-32 (API NO 123-34793) Heinze 44-29 (API NO 123-22341) Francis 21-8 (API NO 123-27380)
EngineerForm: (02)
402881462
01/20/2023
1) Submit Form 42 electronically to COGCC 2 business days prior to MIRU (Spud Notice), for the first well/activity on the pad and provide 2 business days spud notice for all subsequent wells drilled on the pad. 2) Comply with Rule 408.j and provide cement coverage from the end of production casing to a minimum of 500' above Niobrara. Verify coverage with cement bond log. 3) Oil-based drilling fluid is to be used only after all aquifers are covered.
EngineerForm: (02)
402881462
01/20/2023
Per COGCC Order 1-232, Bradenhead tests shall be performed according to the following schedule and Form 17 submitted within 10 days of each test: 1) Within 60 days of rig release, prior to stimulation. If any pressure greater than 200 psi, must contact COGCC engineer prior to stimulation. 2) If a delayed completion, a second test is required between 6-9 months, of if there is pressure above 200 psi, after rig release and prior to stimulation. If any pressure greater than 200 psi, must contact COGCC engineer prior to stimulation. 3) A post-production test within 60 days after first sales, as reported on the Form 10, Certificate of Clearance.
PermitForm: (02)
402881462
02/28/2023
If conductors are preset, operator shall comply with Rule 406.e.
PermitForm: (02)
402881462
02/28/2023
Operator shall comply with Notice to Operators: Interim Reclamation Procedures for Delayed Operations (dated January 5, 2017).
PermitForm: (02)
402881462
03/20/2023
Operator will log two (2) wells during the first rig occupation with open-hole resistivity log with gamma- ray log from the kick-off point into the surface casing for the two stratigraphically deepest wells on each side of the pad.
 
COGIS - Best Management Practice Results
BMP TypeSource DocumentBest Management Practices
Drilling/Completion OperationsForm: (02 )
402881462
3/27/2023
Open-Hole Logging Exception: One of the first wells drilled on the pad during the first rig occupation will be logged with cased-hole neutron log with gamma-ray log from the kick-off point into the surface casing. All wells on the pad will have a cement bond log with gamma-ray run on production casing (or on intermediate casing if production liner is run) into the surface casing. The horizontal portion of every well will be logged with a measured-while-drilling gamma-ray log. The Form 5, Completion Report, for each well on the pad will list all logs run in that well and have those logs attached. The Form 5 for each well will state “Open-Hole Logging Exception - No open-hole logs were run” and will clearly identify the type of log and the well (by API#) in which open-hole logs were run.
Drilling/Completion OperationsForm: (02 )
402881462
3/27/2023
If a skid is performed for the subject well, then the only required BOPE tests are for the BOPE connection bonnet seal breaks, as long as a full BOPE test was performed at the beginning of the pad, and as long as all necessary BOPE tests are completed at least every 30 days during the pad operations.
Drilling/Completion OperationsForm: (02 )
402881462
3/27/2023
Anti-collision: Prior to drilling operations, Operator will perform an anti-collision scan of existing offset wells that have the potential of being within close proximity of the proposed well. This anti-collision scan will include definitive MWD or gyro surveys of the offset wells with included error of uncertainty per survey instrument and compared against the proposed well path with its respective error of uncertainty. If current surveys do not exist for the offset wells, Operator may have gyro surveys conducted to verify bottom hole location. The proposed well will only be drilled if the anti-collision scan results indicate that there is not a risk for collision, or harm to people or the environment. For the proposed well, upon conclusion of drilling operations, an as constructed gyro survey will be submitted to COGCC with the Form 5.