WELL05-123-51857BERRY FARMS
8-6HZ
KERR MCGEE OIL & GAS ONSHORE LP
47120
PR
8/15/2023
WATTENBERG
90750
WELD  123
SENE 8 3N67W 6
318973View Related
 
COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
EngineerForm: (02 )
403097905
10/13/2022
Operator acknowledges the proximity of the listed wells. Operator agrees to: provide mitigation option 1 or 2 (per the Offset Well Evaluation and Hydraulic Fracturing Operator Guidance Document) to mitigate the situation, ensure all applicable documentation is submitted based on the selected mitigation option chosen, and submit a Form 42 (“OFFSET MITIGATION COMPLETED”) stating that appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well. 123-18034FREAUFF #34-4A 123-18091PSC #43-11 123-19194HSR-PESCO #1-9A 123-15652FT ST VRAIN #23A 123-15651FORT SAINT VRAIN #21 123-10377FT ST VRAIN #9 123-10411BERRY #1 123-21633PSC #2-11 123-17958HSR-PESCO #4-11 123-21581PSC #3-9-5Y 123-31481BERRY P #08-27D 123-22781XCEL #14-10 123-21632PSC #15-11 123-24067PSC #27-11 123-24103PSC #39-11 123-25713PLATTE #35-2 123-19288HSR-BERRY #2-8 123-17925PSC #12-10A 123-18006PSC #22-11 123-24048PSC #37-11
EngineerForm: (02 )
403097905
10/13/2022
Operator acknowledges the proximity of the non-operated well. Operator assures that this offset will be remediated per the Offset Well Evaluation and Hydraulic Fracturing Operator Guidance Document Operator using Option 3. Operator will submit a Form 42 (“OFFSET MITIGATION COMPLETED”) stating what appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well. 123-19014PSC #31-10
EngineerForm: (02 )
403097905
10/13/2022
Operator acknowledges the proximity of the listed non-operated wells. Operator assures that this offset list will be remediated per the Offset Well Evaluation and Hydraulic Fracturing Operator Guidance Document (option 4). Operator will submit a Form 42 (“OFFSET MITIGATION COMPLETED”) stating that appropriate mitigation will be completed, during the hydraulic stimulation of this well. This Form 42 shall be filed 48 hours prior to stimulation. Operator will equip the well with at least a 5,000 psi wellhead and monitor casing (surface and production) pressures during the entire stimulation treatment. Surface and production casing pressures of this offset well list will be actively monitored during the entire stimulation treatment of this pad. If there is indication of communication between the stimulation treatment and an offset well, treatment will be stopped and COGCC Engineering notified. 123-21625PSC #15-10 123-23256PSC #2-10 123-24044PSC #24-11 123-15653FT ST VRAIN #24A 123-18317HSR-PSC #15-3 123-41355GOOSE #9N-A8HZ
EngineerForm: (02 )
403097905
10/13/2022
1) Submit Form 42 electronically to COGCC 2 business days prior to MIRU (spud notice) for the first well activity with a rig on the pad and provide 2 business day spud notice via Form 42 for all subsequent wells drilled on the pad. 2) Comply with Rule 408.j. and provide cement coverage from TD to a minimum of 500' above Niobrara. Verify coverage with a cement bond log.
EngineerForm: (02 )
403097905
10/13/2022
Per COGCC Order 1-232, Bradenhead tests shall be performed according to the following schedule and Form 17 submitted within 10 days of each test: 1) Within 60 days of rig release, prior to stimulation. If any pressure greater than 200 psi is observed or if there is continuous flow, Operator must contact COGCC engineering for approval prior to stimulation. 2) If a delayed completion, a second test is required between 6-9 months after rig release and must be conducted prior to stimulation. If any pressure greater than 200 psi is observed or if there is continuous flow, Operator must contact COGCC engineering for approval prior to stimulation. 3) A post-production test within 60 days after first sales, as reported on the Form 10, Certificate of Clearance.
PermitForm: (02 )
403097905
10/25/2022
If conductors are preset, operator shall comply with Notice to Operators: Procedures for Preset Conductors (dated September 1, 2016).
PermitForm: (02 )
403097905
10/25/2022
Operator shall comply with Notice to Operators: Interim Reclamation Procedures for Delayed Operations (dated January 5, 2017).
 
COGIS - Best Management Practice Results
BMP TypeSource DocumentBest Management Practices
Drilling/Completion OperationsForm: (02 )
403097905
11/2/2022
Kerr-McGee acknowledges and will comply with the COGCC Policy for Bradenhead Monitoring during Hydraulic Fracturing Treatments in the Greater Wattenberg Area dated May 29, 2012.
Drilling/Completion OperationsForm: (02 )
403097905
11/2/2022
Anti-Collision: Kerr-McGee will perform an anti-collision evaluation of all active (producing, shut in, or temporarily abandoned) offset wellbores that have the potential of being within one hundred fifty (150) feet of a proposed well prior to drilling operations for the proposed well. Notice shall be given to all offset operators within one hundred fifty (150) feet prior to drilling.
Drilling/Completion OperationsForm: (02 )
403097905
11/2/2022
Open Hole Logging Exception: One of the first wells drilled on the pad will be logged with cased-hole neutron log with gamma-ray log from the kick-off point into the surface casing. All wells on the pad will have a cement bond log with gamma-ray run on production casing (or on intermediate casing if production liner is run) into the surface casing. The horizontal portion of every well will be logged with a measured-while drilling gamma-ray log. The Form 5, Completion Report, for each well on the pad will list all logs run in that well and have those logs attached. The Form 5 for each well shall state “Open Hole Logging Exception - No open-hole logs were run” and shall clearly identify the type of log and the well (by API#) in which open-hole logs were run.
PlanningForm: (04 )
403498892
9/22/2023
Site lighting will be shielded and directed downward and inward toward operations to avoid glare on public roads and nearby Building Units.
Community Outreach and NotificationForm: (04 )
403498892
9/22/2023
Courtesy notifications will be sent to all parcel owners with building units within 2,000 feet of the location letting them know about our subsequent well operations and providing contact information for Kerr McGee’s response line and online resources.
Community Outreach and NotificationForm: (04 )
403498892
9/22/2023
Signs will be placed in conspicuous locations and will include Oxy contact information; the Oxy Stakeholder Relations team will respond to all community member inquiries. The signs will be placed so as not to create a potential traffic hazard.
WildlifeForm: (04 )
403498892
9/22/2023
This location was reviewed using a desktop method to review publicly available wildlife data (including CPW & ECMC data) as well as internal wildlife datasets and aerial imagery. All field personnel are trained to identify wildlife risks and raise concerns noticed during operations with the KMOG Health, Safety, and Environment (HSE) department.
Dust controlForm: (04 )
403498892
9/22/2023
Water will be placed on dirt access roads to mitigate dust as needed.
Noise mitigationForm: (04 )
403498892
9/22/2023
Noise associated with pipe handling, traffic, and other operational activity will be minimized between 7:00 pm and 7:00 am. Based off the rig sound signature, rig orientation will be considered to reduce noise levels to nearby building units.