Drilling/Completion Operations | Form: (02 ) 402378547 11/19/2021 | Blowout Prevention Equipment (“BOPE”): A double ram and annular preventer will be used during drilling. Stabbing valves shall be installed in the event of reverse circulation and shall be prior tested with low and high pressure fluid. |
Drilling/Completion Operations | Form: (02 ) 402378547 11/19/2021 | Bradenhead Monitoring: Operator acknowledges and will comply with COGCC Policy for Bradenhead Monitoring during Hydraulic Fracturing Treatments in the Greater Wattenberg Area dated May 29, 2012. |
Drilling/Completion Operations | Form: (02 ) 402378547 11/19/2021 | Anti-collision: Operator will perform an anti-collision evaluation of all active (producing, shut in, or temporarily abandoned) offset wellbores that have the potential of being within 150 feet of a proposed well prior to drilling operations for the proposed well. Notice shall be given to all offset operators prior to drilling. |
Drilling/Completion Operations | Form: (02 ) 402378547 11/19/2021 | Open Hole Logging Exception: One of the first wells drilled on the pad will be logged with Cased hole Neutron Log with
Gamma Ray Log from the kick-off point to into the surface casing. All wells on the pad will have a cement bond log with
gamma-ray run on production casing (or on intermediate casing if production liner is run) into the surface casing. The
horizontal portion of every well will be logged with a measured while-drilling gamma-ray log. The Form 5, Completion
Report, for each well on the pad will list all logs run in that well and have those logs attached. The Form 5 for each well
shall clearly state “Open Hole Logging Exception - No open-hole logs were run” , will clearly identify the type of log and
the well (by API#) in which open hole logs were run. |