| Engineer | Form: (02) 402496703 11/24/2020 | 1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU (spud notice) for the first well activity with a rig on the pad and provide 48 hour spud notice via Form 42 for all subsequent wells drilled on the pad.
2) Comply with Rule 317.j. and provide cement coverage from TD to a minimum of 500' above Niobrara. Verify coverage with cement bond log.
3) Oil-based drilling fluid is to be used only after all fresh water aquifers are covered. |
| Engineer | Form: (02) 402496703 11/24/2020 | Per COGCC Order 1-232, Bradenhead tests shall be performed according to the following schedule and Form 17 submitted within 10 days of each test:
1) Within 60 days of rig release, prior to stimulation. If any pressure greater than 200 psi, must contact COGCC engineer prior to stimulation.
2) If a delayed completion, 6 months after rig release and prior to stimulation. If any pressure greater than 200 psi, must contact COGCC engineer prior to stimulation.
3) A post-production test within 60 days after first sales, as reported on the Form 10, Certificate of Clearance. |
| Engineer | Form: (02) 402496703 11/24/2020 | Operator acknowledges the proximity of the listed wells. Operator agrees to: provide mitigation option 1 or 2 (per the DJ Basin Horizontal Offset Policy) to mitigate the situation, ensure all applicable documentation is submitted based on the selected mitigation option chosen, and submit a Form 42 (“OFFSET MITIGATION COMPLETED”) stating that appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well.
123-15652 FT ST VRAIN #23A
123-10159 FREAUFF #1
123-17777 UPRC #5-9L
123-18470 PSC #14-3
123-19194 HSR-PESCO #1-9A
123-21687 XCEL #14-3
123-18317 HSR-PSC #15-3
123-17974 FREAUFF #33-4A
123-18034 FREAUFF #34-4A
123-10111 SAINT VRAIN ASSOC. #1 |
| Engineer | Form: (02) 402496703 11/24/2020 | Operator acknowledges the proximity of the listed wells. Operator assures that this offset will be remediated per the DJ Basin Horizontal Offset Policy (option 4). Operator will submit a Form 42 (“OTHER – AS SPECIFIED BY PERMIT CONDITION”) stating that appropriate mitigation will be completed, during the hydraulic stimulation of this well. This Form 42 shall be filed 48 hours prior to stimulation. A Bradenhead test will be performed on the offset wells listed below within 30 days prior to the beginning of stimulation of this well. Surface and production casing pressures of this offset well list will be actively monitored during stimulation of this well. Operator will assure that the offset well’s bradenhead is open and actively monitored during the entire stimulation treatment of this pad. If there is indication of communication between the stimulation treatment and an offset well, treatment will be stopped and COGCC Engineering notified.
123-31492 UPRC P #05-24D
123-21633 PSC #2-11
123-16542 HSR-HEIMARK #6-2
123-31481 BERRY P #08-27D
123-24067 PSC #27-11
123-18319 HSR-PSC #1-10A
123-24099 XCEL #21-11 |
| Permit | Form: (02) 402496703 01/07/2021 | The existing Oil and Gas Location (ID 416717) for this proposed well is approved for 11 wells. The operator will plug and abandon existing wells on the location so that the number of wells does not exceed 11 wells. If the operator chooses not to plug and abandon any of the existing wells, an amended 2A must be submitted and approved prior to spudding any well that would increase the number of wells on this location to more than 11 wells. |
| Permit | Form: (02) 402496703 01/07/2021 | If conductors are preset, operator shall comply with Notice to Operators: Procedures for Preset Conductors (dated September 1, 2016, revised October 6, 2016). |
| Permit | Form: (02) 402496703 01/07/2021 | Operator shall comply with Notice to Operators: Interim Reclamation Procedures for Delayed Operations (dated January 5, 2017). |
| Engineer | Form: (04) 403351251 03/24/2023 | Operator acknowledges the proximity of the listed wells. Operator assures that this offset will be remediated per the DJ Basin Horizontal Offset Policy (option 4). Operator will submit a Form 42 (“OTHER – AS SPECIFIED BY PERMIT CONDITION”) stating that appropriate mitigation will be completed, during the hydraulic stimulation of this well. This Form 42 shall be filed 48 hours prior to stimulation. A Bradenhead test will be performed on the offset wells listed below within 30 days prior to the beginning of stimulation of this well. Surface and production casing pressures of this offset well list will be actively monitored during stimulation of this well. Operator will assure that the offset well’s bradenhead is open and actively monitored during the entire stimulation treatment of this pad. If there is indication of communication between the stimulation treatment and an offset well, treatment will be stopped and COGCC Engineering notified.
123-31492 UPRC P #05-24D
123-21633 PSC #2-11
123-16542 HSR-HEIMARK #6-2
123-31481 BERRY P #08-27D
123-24067 PSC #27-11
123-18319 HSR-PSC #1-10A
123-24099 XCEL #21-11
123-18317 HSR-PSC 15-3 |
| Engineer | Form: (04) 403795519 06/03/2024 | 1. Submit a Form 4 reporting the results of the operation within 30 days after the Pressure Blanket well has returned to production. Report the following:
a) The total volume of gas or water injected in the well.
b) The total volume of gas or water recovered from the well during withdrawal.
c) The well’s shut in pressure after the Blanket fluid has been withdrawn.
d) Pressure monitoring data during offset frac operations.
2. All injected and withdrawn gas or water must be reported on a Form 7. |
| Engineer | Form: (04) 403915844 12/26/2024 | Operator shall correct Form 7 reporting to reflect injected water volumes. |