COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
EngineerForm: (02 )
402011489
9/17/2019
Per COGCC Order 1-232, Bradenhead tests shall be performed according to the following schedule and Form 17 submitted within 10 days of each test: 1) Within 60 days of rig release, prior to stimulation. If any pressure greater than 200 psi, must contact COGCC engineer prior to stimulation. 2) If a delayed completion, 6 months after rig release and prior to stimulation. If any pressure greater than 200 psi, must contact COGCC engineer prior to stimulation. 3) A post-production test within 60 days after first sales, as reported on the Form 10, Certificate of Clearance.
EngineerForm: (02 )
402011489
9/17/2019
Operator acknowledges the proximity of the listed well: Operator agrees to: provide mitigation option 1 or 2 (per the DJ Basin Horizontal Offset Policy) to mitigate the situation, ensure all applicable documentation is submitted based on the selected mitigation option chosen, and submit a Form 42 (“OFFSET MITIGATION COMPLETED”) for the remediated wells, referencing the API number of the proposed horizontal well(s) stating what appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well. 123-12613 Champlin 86 Amoco Unit L 1
EngineerForm: (02 )
402011489
9/17/2019
1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU (spud notice) for the first well activity with a rig on the pad and provide 48 hour spud notice via Form 42 for all subsequent wells drilled on the pad. 2) Comply with Rule 317.j. and provide cement coverage from TD to a minimum of 200' above Niobrara. Verify coverage with cement bond log. 3) Oil-based drilling fluid is to be used only after all fresh water aquifers are covered.
EngineerForm: (04 )
402473634
9/18/2020
Operator acknowledges the proximity of the listed well. Operator assures that this offset list will be remediated per the DJ Basin Horizontal Offset Policy (option 4). Operator will submit a Form 42 (“OFFSET MITIGATION COMPLETED”) stating that appropriate mitigation will be completed, during the hydraulic stimulation of this well. This Form 42 shall be filed 48 hours prior to stimulation. Operator will equip wellbore with a 5,000 psi wellhead and set downhole isolation above the Niobrara formation top and pass a successful 15-minute pressure test. Operator will monitor casing (surface and production) pressures during the stimulation treatment of the pad. A Bradenhead test will be performed prior to the beginning of stimulation and the Form 17 submitted within 10 days of the test. If there is indication of communication between the stimulation treatment and an offset well’s bradenhead, treatment will be stopped and COGCC Engineering notified. After stimulation is complete, a Form 4 Sundry may be requested describing how Option 4 work was completed and include a summary of the monitoring details. Champlin 86 Amoco Unit L 1 (123-12613)
 
COGIS - Best Management Practice Results
BMP TypeSource DocumentBest Management Practices
Drilling/Completion OperationsForm: (02 )
402011489
11/20/2019
Kerr-McGee acknowledges and will comply with the COGCC Policy for Bradenhead Monitoring during Hydraulic Fracturing Treatments in the Greater Wattenberg Area dated May 29, 2012.
Drilling/Completion OperationsForm: (02 )
402011489
11/20/2019
Anti-Collision: Kerr-McGee will perform an anti-collision evaluation of all active (producing, shut in, or temporarily abandoned) offset wellbores that have the potential of being within one hundred fifty (150) feet of a proposed well prior to drilling operations for the proposed well. Notice shall be given to all offset operators within one hundred fifty (150) feet prior to drilling.
Drilling/Completion OperationsForm: (02 )
402011489
11/20/2019
Open Hole Logging Exception: One of the first wells drilled on the pad will be logged with cased-hole neutron log with gamma-ray log from the kick-off point into the surface casing. All wells on the pad will have a cement bond log with gamma-ray run on production casing (or on intermediate casing if production liner is run) into the surface casing. The horizontal portion of every well will be logged with a measured-while drilling gamma-ray log. The Form 5, Completion Report, for each well on the pad will list all logs run in that well and have those logs attached. The Form 5 for each well shall state “Open Hole Logging Exception - No open-hole logs were run” and shall clearly identify the type of log and the well (by API#) in which open-hole logs were run.