| Engineer | Form: (02) 401969215 05/24/2019 | Per COGCC Order 1-232, Bradenhead tests shall be performed according to the following schedule and Form 17 submitted within 10 days of each test:
1) Within 60 days of rig release, prior to stimulation. If any pressure greater than 200 psi, must contact COGCC engineer prior to stimulation.
2) If a delayed completion, 6 months after rig release and prior to stimulation. If any pressure greater than 200 psi, must contact COGCC engineer prior to stimulation.
3) A post-production test within 60 days after first sales, as reported on the Form 10, Certificate of Clearance. |
| Engineer | Form: (02) 401969215 05/24/2019 | 1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU (Spud Notice), for the first well/activity on the pad and provide 48 hour spud notice for all subsequent wells drilled on the pad.
2) Comply with Rule 317.j and provide cement coverage from the end of production casing to a minimum of 200' above Niobrara and from 200’ below Sussex to 200’ above Sussex. Verify coverage with cement bond log.
3) Oil-based drilling fluid is to be used only after all fresh water aquifers are covered. |
| Permit | Form: (02) 401969215 07/18/2019 | If conductors are preset, Operator shall comply with Notice to Operators: Procedures for Preset Conductors (dated September 1, 2016, revised October 6, 2016). |
| Permit | Form: (02) 401969215 07/18/2019 | Operator shall comply with Notice to Operators: Interim Reclamation Procedures for Delayed Operation (dated January 5, 2017). |
| Permit | Form: (02) 401969215 07/18/2019 | This Permit to Drill is approved subject to all the BMPs and COAs on the most recently approved Form 2A and any subsequently approved Form 4 for the Oil and Gas Location (Location ID # 332837). The most recently approved Form 2A and any subsequent Form 4s containing applicable COAs for this location shall be posted onsite during construction, drilling, and completions operations. |
| Permit | Form: (02) 402622567 04/08/2021 | Operator shall comply with Notice to Operators: Interim Reclamation Procedures for Delayed Operations (dated January 5, 2017). |
| Engineer | Form: (02) 402622567 05/13/2021 | 1) Submit Form 42 electronically to COGCC 2 business days prior to MIRU (spud notice) for the first well activity with a rig on the pad and provide 2 business day spud notice via Form 42 for all subsequent wells drilled on the pad.
2) Comply with Rule 408.j. and provide cement coverage from TD to a minimum of 500' above Niobrara and from 500’ below Sussex to 500’ above Sussex. Verify coverage with cement bond log.
3) Oil-based drilling fluid is to be used only after all fresh water aquifers are covered.
|
| Engineer | Form: (02) 402622567 05/13/2021 | Per COGCC Order 1-232, Bradenhead tests shall be performed according to the following schedule and Form 17 submitted within 10 days of each test:
1) Within 60 days of rig release, prior to stimulation. If any pressure greater than 200 psi, must contact COGCC engineer prior to stimulation.
2) If a delayed completion, 6 months after rig release and prior to stimulation. If any pressure greater than 200 psi, must contact COGCC engineer prior to stimulation.
3) A post-production test within 60 days after first sales, as reported on the Form 10, Certificate of Clearance. |
| Engineer | Form: (02) 402622567 05/13/2021 | Operator acknowledges the proximity of the listed wells. Operator assures that this offset list will be remediated per the DJ Basin Horizontal Offset Policy (option 4). Operator will submit a Form 42 (“OFFSET MITIGATION COMPLETED”) stating that appropriate mitigation will be completed, during the hydraulic stimulation of this well. This Form 42 shall be filed 48 hours prior to stimulation. A Bradenhead test will be performed on the offset wells listed below within 30 days prior to the beginning of stimulation of this well. Surface and production casing pressures of this offset well list will be actively monitored during stimulation of this well. Operator will assure that the offset well’s bradenhead is open and actively monitored during the entire stimulation treatment of this pad– a person will monitor for any evidence of fluid. If there is indication of communication between the stimulation treatment and an offset well, treatment will be stopped and COGCC Engineering notified.
EXTRACTION OIL & GAS INC 123-40310 GP-JEvans *2-19-19
EXTRACTION OIL & GAS INC 123-41139 GP JACKSON FED *17W-25-4
EXTRACTION OIL & GAS INC 123-41143 GP HILLSIDE FED *20W-20-13
EXTRACTION OIL & GAS INC 123-41145 GP HILLSIDE FED *20W-20-15
EXTRACTION OIL & GAS INC 123-44415 VT-Alles *1-16-18
EXTRACTION OIL & GAS INC 123-44418 VT-LDS *C3-16-18
EXTRACTION OIL & GAS INC 123-44430 GP HILLSIDE FED *20W-20-14
EXTRACTION OIL & GAS INC 123-44432 GP ALLES FED *17W-25-3
EXTRACTION OIL & GAS INC 123-50286 GP Cody Fed *20E-15-1
PDC ENERGY INC 123-43384 Clark *14J-343 |