Engineer | Form: (02 ) 401772717 11/21/2018 | Operator acknowledges the proximity of the listed wells. Operator agrees to: provide mitigation option 1 or 2 (per the DJ Basin Horizontal Offset Policy) to mitigate the situation, ensure all applicable documentation is submitted based on the selected mitigation option chosen, and submit a Form 42 (“OFFSET MITIGATION COMPLETED”) stating that appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well.
05-123-07726, MATHEWS 2
05-123-09319, STITT GAS UNIT 1 |
Engineer | Form: (02 ) 401772717 11/21/2018 | Bradenhead tests shall be performed according to the following schedule and the Form 17 submitted within 10 days of each test:
1) Within 60 days of rig release and prior to stimulation and
2) If a delayed completion, 6 months after rig release and prior to stimulation.
3) Within 30 days after first production, as reported on Form 5A.
If a bradenhead test reports a surface casing pressure greater than 200 psig stimulation is not allowed until the Engineering Supervisor has been consulted. |
Engineer | Form: (02 ) 401772717 11/21/2018 | 1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU (spud notice) for the first well activity with a rig on the pad and provide 48 hour spud notice via Form 42 for all subsequent wells drilled on the pad.
2) Comply with Rule 317.j. and provide cement coverage from TD to a minimum of 200' above Niobrara and from 200’ below Sussex to 200’ above Sussex. Verify coverage with cement bond log.
3) Oil-based drilling fluid is to be used only after all fresh water aquifers are covered. |
Engineer | Form: (04 ) 402924977 1/18/2022 | Operator shall continue to monitor pressure, and report to COGCC through annual testing. If monitored well conditions meet the thresholds defined by Order 1-232 a new bradenhead test and sundry must be filed. |
Engineer | Form: (04 ) 402687896 5/4/2022 | 1) This well has been designated inactive and must be plugged and abandoned, have an approved Form 5B or be added to a Form 6A list no later than November 1, 2022.
2) The Form 7, Operators Report of Monthly Operations, must correctly reflect the well status.
|
Engineer | Form: (04 ) 403063573 6/16/2022 | 1) This well is designated inactive and must be properly returned to production, plugged and abandoned, have an approved Form 5B or be submitted on a Form 6A (to be designated as Out of Service) no later than no later than November 1, 2022. |