| Engineer | Form: (02) 401625048 06/25/2018 | Bradenhead tests shall be performed according to the following schedule and the Form 17 submitted within 10 days of each test:
1) Within 60 days of rig release and prior to stimulation and
2) If a delayed completion, 6 months after rig release and prior to stimulation.
3) Within 30 days after first production, as reported on Form 5A.
If a bradenhead test reports a surface casing pressure greater than 200 psig stimulation is not allowed until the Engineering Supervisor has been consulted. |
| Engineer | Form: (02) 401625048 06/25/2018 | 1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU (spud notice) for the first well activity with a rig on the pad and provide 48 hour spud notice via Form 42 for all subsequent wells drilled on the pad.
2) Comply with Rule 317.j. and provide cement coverage from TD to a minimum of 200' above Niobrara. Verify coverage with cement bond log.
3) Oil-based drilling fluid is to be used only after all fresh water aquifers are covered. |
| Engineer | Form: (02) 401625048 06/25/2018 | Operator acknowledges the proximity of the listed non-operated well. Operator assures that this offset will be remediated per the DJ Basin Horizontal Offset Policy (option 3). Operator will submit a Form 42 (“OFFSET MITIGATION COMPLETED”) stating what appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well.
05-123-09944, STATE C 1
|
| Permit | Form: (02) 402861132 03/18/2022 | Operator shall comply with Notice to Operators: Interim Reclamation Procedures for Delayed Operations (dated January 5, 2017).
|
| Permit | Form: (02) 402861132 03/18/2022 | If conductors are preset, operator shall comply with Notice to Operators: Procedures for Preset Conductors (dated September 1, 2016).
|
| Engineer | Form: (02) 402861132 03/29/2022 | 1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU (spud notice) for the first well activity with a rig on the pad and provide 48 hour spud notice via Form 42 for all subsequent wells drilled on the pad.
2) Comply with Rule 408.j. and provide cement coverage from TD to a minimum of 500' above Niobrara. Verify coverage with a cement bond log.
3) Oil-based drilling fluid is to be used only after all fresh water aquifers are covered.
|
| Engineer | Form: (02) 402861132 03/29/2022 | Per COGCC Order 1-232, Bradenhead tests shall be performed according to the following schedule and Form 17 submitted within 10 days of each test:
1) Within 60 days of rig release, prior to stimulation. If any pressure greater than 200 psi is observed or if there is continuous flow, Operator must contact COGCC engineering for approval prior to stimulation.
2) If a delayed completion, a second test is required between 6-9 months after rig release and must be conducted prior to stimulation. If any pressure greater than 200 psi is observed or if there is continuous flow, Operator must contact COGCC engineering for approval prior to stimulation.
3) A post-production test within 60 days after first sales, as reported on the Form 10, Certificate of Clearance. |