Drilling/Completion Operations | Form: (02 ) 401633481 6/17/2018 | A closed–loop system will be used for drilling operations. |
Drilling/Completion Operations | Form: (02 ) 401633481 6/17/2018 | Blowout Prevention Equipment (“BOPE”): A double ram and annular preventer will be
used during drilling. Stabbing valves shall be installed in the event of reverse
circulation and shall be prior tested with low and high pressure fluid. |
Drilling/Completion Operations | Form: (02 ) 401633481 6/17/2018 | Bradenhead Monitoring: Operator acknowledges and will comply with COGCC Policy
for Bradenhead Monitoring during Hydraulic Fracturing Treatments in the Greater
Wattenberg Area dated May 29, 2012. |
Drilling/Completion Operations | Form: (02 ) 401633481 6/17/2018 | One of the first wells drilled on the pad will be logged with open hole Resistivity Log
and Gamma Ray Log from the kick-off point into the surface casing. All wells on the
pad will have a cement bond log with gamma-ray run on production casing (or on
intermediate casing if production liner is run) into the surface casing. The horizontal
portion of every well will be logged with a measured-while-drilling gamma-ray log. The
Form 5, Completion Report, for each well on the pad will list all logs run and have
those logs attached. The Form 5 for a well without open-hole logs shall clearly state
“No open-hole logs were run” and shall clearly identify (by API#, well name & number)
the well in which open hole logs were run. |
Drilling/Completion Operations | Form: (02 ) 401633481 6/17/2018 | Anti-collision: Operator will perform an anti-collision evaluation of all active (producing,
shut in, or temporarily abandoned) offset wellbores that have the potential of being
within 150 feet of a proposed well prior to drilling operations for the proposed well.
Notice shall be given to all offset operators prior to drilling. |
Drilling/Completion Operations | Form: (02 ) 401633481 6/17/2018 | Identification of plugged and abandoned wells will be identified pursuant to 319.a.(5). |