Engineer | Form: (02 ) 401203312 3/14/2017 | Bradenhead tests shall be performed according to the following schedule and the Form 17 submitted within 10 days of each test:
1) Within 60 days of rig release and prior to stimulation and
2) If a delayed completion, 6 months after rig release and prior to stimulation.
3) Within 30 days after first production, as reported on Form 5A. |
Engineer | Form: (02 ) 401203312 3/14/2017 | 1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU (spud notice) for the first well activity with a rig on the pad and provide 48 hour spud notice via Form 42 for all subsequent wells drilled on the pad.
2) Comply with Rule 317.j. and provide cement coverage from TD to a minimum of 200' above Niobrara and from 200’ below Sussex to 200’ above Sussex. Verify coverage with cement bond log. |
Engineer | Form: (02 ) 401203312 3/14/2017 | Operator acknowledges the proximity of the listed wells. Operator agrees to: provide mitigation option 1 or 2 (per the DJ Basin Horizontal Offset Policy) to mitigate the situation, ensure all applicable documentation is submitted based on the selected mitigation option chosen, and submit a Form 42 (“OFFSET MITIGATION COMPLETED”) stating that appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well.
05-123-16986, HSR-IAN 13-20
05-123-15273, UPRC 29-6J
05-123-15274, UPRC 29-3J
05-123-15837, UPRC 29-4J
05-123-16101, HSR-EGGLER 14-29
05-123-16875, HSR-RANIN 13-29
05-123-16880, HSR-PANTALEO 10-29A
05-123-16881, HSR-PETERSON 12-29
05-123-19166, HSR-EGGLER 11-29
05-123-19167, HSR-AUGUST 15-29
05-123-21614, WARDELL 18-29
05-123-22311, WARDELL 21-29
05-123-15004, WARD 30-1J
05-123-15879, HSR-MULBERG 16-30
05-123-17072, HSR-TOO DEVINE 1-31
05-123-17095, MCGUCKIN H 32-2J
05-123-17423, MCGUCKIN H 32-3 |
Engineer | Form: (02 ) 401203312 3/14/2017 | Operator acknowledges the proximity of the listed non-operated wells. Operator assures that this offset list will be remediated per the DJ Basin Horizontal Offset Policy (option 3). Operator will submit a Form 42 (“OFFSET MITIGATION COMPLETED”) stating what appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well.
05-123-16014, WARDELL 32-29 |
Engineer | Form: (04 ) 402481671 9/14/2020 | Operator shall continue to monitor pressure, and report to COGCC through annual test reporting. |
Engineer | Form: (04 ) 403345081 3/24/2023 | Operator shall continue to monitor pressure, and report to COGCC through annual testing. If monitored well conditions meet the thresholds defined by Order 1-232 a new bradenhead test and sundry must be filed.
|
Engineer | Form: (04 ) 403646747 1/19/2024 | Operator shall continue to monitor pressure, and report to ECMC through annual testing. If monitored well conditions meet the thresholds defined by Order 1-232 a new bradenhead test and sundry must be filed.
|
Engineer | Form: (04 ) 403964841 10/31/2024 | 1. Operator will implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well operations do not constitute a nuisance or hazard to public welfare.
2. Prior to starting bradenhead abatement, if a sample has not been collected within the last twelve months collect bradenhead and production gas samples for laboratory analysis. Sampling will comply with Operator Guidance - Bradenhead Testing and Reporting Instructions, Appendix A: Liquid and Gas Sampling. Copies of all final laboratory analytical results will be provided to the ECMC within three months of collecting the samples.
3. Bradenhead gas is not to be vented to atmosphere; any gas from the Bradenhead will be routed to the specified abatement system. Operator will implement measures to get an initial estimate of the gas flow rate and/or volume from the bradenhead. The abatement program may be used for six consecutive months.
4. Operator will submit a Form 42 (“OTHER”) stating that “bradenhead abatement program has started.”
5. By 4/10/25, conduct a new bradenhead test and submit the Form 17 within ten days of the test and submit a Form 4 Sundry that summarizes current well condition. The sundry should include details of the future plans, flow rate information, pressure data and a discussion of the sample analysis.
Bradenhead pressure shall not exceed threshold pressure (50 psig). |
Engineer | Form: (04 ) 404165378 5/8/2025 | 1. Operator will implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well operations do not constitute a nuisance or hazard to public welfare.
2. Bradenhead gas is not to be vented to the atmosphere; any gas from the Bradenhead will routed to to specified abatement system. Shut in bradenhead pressure shall not exceed threshold pressure . Operator will implement measures to get an estimate of the gas flow rate and/or volume from the bradenhead.
3. No later than 3/26/26, conduct a bradenhead test, submit a Form 17, and submit a Form 4 Sundry that summarizes current well condition. The well should be shut in for seven days to monitor and collect data to characterize build up pressures prior to conducting the bradenhead test. The sundry should include details of the future plans, sample analysis interpretation, bradenhead test description, and the flow rate information and pressure data.
4. If a sample has not been collected from surface casing within the last twelve months collect bradenhead gas samples for laboratory analysis. Sampling will comply with Operator Guidance - Bradenhead Testing and Reporting Instructions, Appendix A: Liquid and Gas Sampling. Copies of all final laboratory analytical results will be provided to the ECMC within three months of collecting the samples.
|