| Engineer | Form: (02) 401125030 02/27/2017 | 1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU (spud notice) for the first well activity with a rig on the pad and provide 48 hour spud notice via Form 42 for all subsequent wells drilled on the pad.
2) Provide cement coverage to a minimum of 200' above Niobrara. Verify coverage with cement bond log.
|
| Engineer | Form: (02) 401125030 02/27/2017 | Bradenhead tests shall be performed and reported according to the following schedule
and Form 17 submitted within 10 days of each test.:
1) All: Within 60 days of rig release, prior to stimulation.
2) Delayed completion: 6 months after rig release, prior to stimulation.
3) All: Within 30 days of first production, as reported on Form 5A.
|
| Permit | Form: (02) 401125030 03/15/2017 | This Permit to Drill is approved subject to all the BMPs and COAs on the most recently approved Form 2A and any subsequently approved Form 4 for the Oil and Gas Location. The most recently approved Form 2A and any subsequent Form 4s containing applicable COAs for this location shall be posted onsite during construction, drilling, and completions operations.
|
| Engineer | Form: (02) 402860096 01/25/2023 | Operator acknowledges the proximity of the listed wells: Operator agrees to: provide mitigation option 1 or 2 (per the DJ Basin Horizontal Offset Policy) to mitigate the situation, ensure all applicable documentation is submitted based on the selected mitigation option chosen, and submit a Form 42 (“OFFSET MITIGATION COMPLETED”) for the remediated wells, referencing the API number of the proposed horizontal well(s) stating what appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well.
Stephenson 6-33 (API NO 123-22623)
State Booth 36-11 (API NO 123-23126)
Bay 43-1 (API NO 123-23394) |
| Engineer | Form: (02) 402860096 01/25/2023 | Operator acknowledges the proximity of the following non-operated listed wells: Operator agrees to: provide mitigation option 1 or 2 (per the DJ Basin Horizontal Offset Policy) to mitigate the situation, ensure all applicable documentation is submitted based on the selected mitigation option chosen, and submit a Form 42 (“OFFSET MITIGATION COMPLETED”) for the remediated wells, referencing the API number of the proposed horizontal well(s) stating what appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well.
Owl Creek 9 (API NO 123-11935)
Kreps 1 (API NO 123-12736)
Ehrlich 4 (API NO 123-12738)
Kreps Trust 34-6 (API NO 123-21723)
Fabrizius 41-1 (API NO 123-22345)
Uyemiura 33-31 (API NO 123-22441)
Kreps 33-6 (API NO 123-22597)
Kreps 31-6 (API NO 123-22628)
Kreps 32-6 (API NO 123-22629) |
| Engineer | Form: (02) 402860096 01/25/2023 | 1) Submit Form 42 electronically to COGCC 2 business days prior to MIRU (Spud Notice), for the first well/activity on the pad and provide 2 business days spud notice for all subsequent wells drilled on the pad.
2) Comply with Rule 408.j and provide cement coverage from the end of production casing to a minimum of 500' above Niobrara. Verify coverage with cement bond log.
3) Oil-based drilling fluid is to be used only after all aquifers are covered. |
| Engineer | Form: (02) 402860096 01/25/2023 | Per COGCC Order 1-232, Bradenhead tests shall be performed according to the following schedule and Form 17 submitted within 10 days of each test:
1) Within 60 days of rig release, prior to stimulation. If any pressure greater than 200 psi, must contact COGCC engineer prior to stimulation.
2) If a delayed completion, a second test is required between 6-9 months, of if there is pressure above 200 psi, after rig release and prior to stimulation. If any pressure greater than 200 psi, must contact COGCC engineer prior to stimulation.
3) A post-production test within 60 days after first sales, as reported on the Form 10, Certificate of Clearance. |
| Permit | Form: (02) 402860096 04/20/2023 | Operator will log two (2) wells during the first rig occupation with open-hole resistivity log with gamma-ray log from the kick-off point into the surface casing for the two stratigraphically deepest wells on each side of the pad
|
| Permit | Form: (04) 403558445 11/15/2023 | This Sundry Notice Form 4 authorizes changes in the drilling/casing/cementing program as shown on the Drilling Permit Form 2 and must be visibly posted with the permit during drilling. |