Engineer | Form: (02 ) 400939366 8/8/2016 | 1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU (Spud Notice), for the first well/activity on the pad and provide 48 hour spud notice for all subsequent wells drilled on the pad.
2) Comply with Rule 317.j and provide cement coverage from the end of production casing to a minimum of 200' above Niobrara. Verify coverage with cement bond log.
|
Engineer | Form: (02 ) 400939366 8/8/2016 | Bradenhead tests shall be performed and reported according to the following schedule and Form 17 submitted within 10 days of each test.:
1) Within 60 days of rig release, prior to stimulation.
2) 6 months after rig release, prior to stimulation.
3) Within 30 days of first production, as reported on Form 5A.
|
Engineer | Form: (02 ) 400939366 8/8/2016 | Operator acknowledges the proximity of the following non-operated listed wells: Operator agrees to: provide mitigation option 1 or 2 (per the DJ Basin Horizontal Offset Policy) to mitigate the situation, ensure all applicable documentation is submitted based on the selected mitigation option chosen, and submit a Form 42 (“OFFSET MITIGATION COMPLETED”) for the remediated wells, referencing the API number of the proposed horizontal well(s) stating what appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well.
FAY 1 (API NO 123-12802)
|
Permit | Form: (02 ) 400939366 3/9/2017 | This Permit to Drill is approved subject to all the BMPs and COAs on the most recently approved Form 2A and any subsequently approved Form 4 for the Oil and Gas Location (Location ID #322888). The most recently approved Form 2A and any subsequent Form 4s containing applicable COAs for this location shall be posted onsite during construction, drilling, and completions operations.
|
OGLA | Form: (04 ) 403012415 4/20/2022 | Operator will implement measures to capture, combust, or control emissions to protect health and safety, and to ensure that vapors and odors from well repair operations with heavy equipment do not constitute a nuisance or hazard to public health, welfare and the environment. Due to proximity of building units (BUs) all blowdown gases will be controlled. |
OGLA | Form: (04 ) 403012415 4/20/2022 | Prior to commencing operations, at a minimum, the operator will provide an informational sheet to the owners/occupants of BUs that are nearby and adjacent to the parcel on which the well is located. The sheet will include the operator's contact information and the nature, timing, and expected duration of the well repair operations with heavy equipment. |
OGLA | Form: (04 ) 403012415 4/20/2022 | Prior to commencing operations, the operator will post signs in conspicuous locations. The signs will indicate the operator is bring in heavy equipment to conduct well repair operations are being conducted, the well name, well, and the applicable contact information. Signs will be placed so as not to create a potential traffic hazard. |