Engineer | Form: (02 ) 400585473 4/24/2014 | Operator acknowledges the proximity of the listed wells: Operator agrees to: provide mitigation option 1 or 2 (per the DJ Basin Horizontal Offset Policy) to mitigate the situation, ensure all applicable documentation is submitted based on the selected mitigation option chosen, and submit a Form 42 (“OFFSET MITIGATION COMPLETED”) for the remediated wells, referencing the API number of the proposed horizontal well(s) stating what appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well.
Bohlander, Jacob T ‘B’ 1 ( API NO 123-08056), HSR-Tuck 10-24 ( API NO 123-14346),
HSR-Walsh 8-24 ( API NO 123-14349), HSR-Escoboza 1-24 ( API NO 123-14983),
UPRR 22 Pan Am K 1 ( API NO 123-08162), Camp UPRR 41-25A ( API NO 123-13301)
|
Engineer | Form: (02 ) 400585473 4/24/2014 | Operator acknowledges the proximity of the listed non-operated wells: Operator agrees to: provide mitigation option 1 or 2 (per the DJ Basin Horizontal Offset Policy) to mitigate the situation, ensure all applicable documentation is submitted based on the selected mitigation option chosen, and submit a Form 42 (“OFFSET MITIGATION COMPLETED”) for the remediated wells, referencing the API number of the proposed horizontal well(s) stating what appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well.
Wardell 18-13J ( API NO 123-14987), Wardell H 19-3J ( API NO 123-07332),
Wardell H 19-13 ( API NO 123-15864), Wardell H 19-04 ( API NO 123-15888),
Wardell H 19-05 ( API NO 123-15889), Camp 30-4J ( API NO 123-15291)
|
Engineer | Form: (02 ) 400585473 4/24/2014 | 1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU.
2) Comply with Rule 317.i and provide cement coverage from the bottom of the production casing to a minimum of 200' above Niobrara. Verify coverage with cement bond log.
3) Run and submit Directional Survey from TD to base of surface casing. The operator shall comply with Rule 321, and it shall be the operator’s responsibility to ensure that the wellbore complies with setback requirements in commission orders or rules prior to producing the well.
|