COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
EngineerForm: (02 )
400578460
4/21/2014
1) Provide 48 hour notice prior to spud via electronic Form 42. 2) Provide cement coverage to a minimum of 200' above Niobrara. Verify coverage with cement bond log. 3) Run and submit Directional Survey from TD to base of surface casing. Ensure that the wellbore complies with setback requirements in commission orders or rules prior to producing the well.
EngineerForm: (02 )
400578460
4/21/2014
Operator acknowledges the proximity of the following offset well(s) of concern: 05-123-05492, H H DUELL B 2, DA, Crzo F6N in process. 05-123-05505, DUELL 3, DA, Crzo F6N in process. 05-123-09617, DUELL 25-1, DA, Crzo F6N approved. 05-123-11022, DUELL 4 B I, PA, No Crzo F6 yet, OWE says Carrizo will re-enter/plug prior to fracing. 05-123-11222, DUELL 5C, PA, Crzo F6N in process. 05-123-13563, DUELL 2-BR, PA, Crzo F6N in process. 05-123-09031, DUELL 1-26, PA, Crzo F6N approved. 05-123-09264, DUELL ET AL 1-26,DA, Crzo F6N approved. 05-123-05477, STATE 1, DA, No Crzo F6N yet, Not on OWE’s, No isolation. Operator agrees to: comply with the DJ Basin Horizontal Offset Policy to mitigate the situation, ensure all applicable documentation is submitted based on the selected mitigation option chosen, and submit Form 42(s) (“OFFSET MITIGATION COMPLETED”) for the remediated wells, referencing the API Number of the proposed horizontal well(s) stating what appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well.
PermitForm: (02 )
400578460
4/29/2014
Open hole resistivity and gamma logs shall be run to describe the stratigraphy of the entire well bore and to adequately verify the setting depth of surface casing and aquifer coverage. On a multi-well pad, these open hole logs are only required on one of the first wells drilled on the pad and the Drilling Completion Report - Form 5 for every well on the pad shall identify which well was logged.
EngineerForm: (04 )
400738486
3/13/2015
1) The venting or flaring of natural gas shall be conducted in accordance with COGCC Rule 912 for the initial production test period. 2) Notify the local emergency dispatch or the local governmental designee of any natural gas flaring. 3) If flaring will continue more than 6 months, submit updated requests to flare to COGCC on Form 4 (Sundry Notice), which discusses timing to connect to sales line, plans to develop infrastructure, and justification for continued venting/flaring. 4) The operator is required to obtain and maintain any required air permits from CDPHE. 5) The venting or flaring volumes shall be reported by Form 7, Operator’s Monthly Report of Operations.
 
COGIS - Best Management Practice Results
BMP TypeSource DocumentBest Management Practices
PlanningForm: (02 )
400578460
5/15/2014
A Form 15 Pit Report will be submitted 30 days prior to construciton of the freshwater storage pit. A survey of the lcoation and revision to the existing pit size in the process of being drawing.
Storm Water/Erosion ControlForm: (02 )
400578460
5/15/2014
Operator has designed the well pad with insloping and a storm water control ditch to prevent storm water run-on/run-off and the release of fluids from the location. See attached Construction Layout Drawing.
Material Handling and Spill PreventionForm: (02 )
400578460
5/15/2014
Operator will ensure 110 percent secondary containment for any volume of fluids contained at the well site during drilling and completion. Oeprtor will implement best management practices to contain any unintentionl release of fluids. Operator shall not allow any fluids to flow back tot he Fresh Water Storage Pit/Pond.
ConstructionForm: (02 )
400578460
5/15/2014
The construction location will be fenced.
Drilling/Completion OperationsForm: (02 )
400578460
5/15/2014
Fresh water for the Fresh Water Storage Pit comes from water provider; water sources permitted for consumbale industrial use. Freshwater Storage Pit shall contain fresh water only and signage prohibiting the use of the pit for any fluid that does not come frum municipal, irrigation or surface water source. Operator will implement interim relcamation measures immediately after construction of the location to stabilize cut and fill slopes, stabilize the topsoil and spoil stockpiles, establish desirable vegetation and control weeds on the location. An Open Hole Resistivity log will be provided for one well on this pad, preferably the number 4 well.