| Engineer | Form: (02) 400581853 04/17/2014 | 1) Provide 48 hour notice prior to spud via electronic Form 42.
2) Provide cement coverage to a minimum of 200' above Niobrara. Verify coverage with cement bond log.
3) Run and submit Directional Survey from TD to base of surface casing. Ensure that the wellbore complies with setback requirements in commission orders or rules prior to producing the well.
|
| Engineer | Form: (04) 400765201 03/30/2015 | 1) The venting or flaring of natural gas shall be conducted in accordance with COGCC Rule 912 for the initial production test period.
2) Notify the local emergency dispatch or the local governmental designee of any natural gas flaring.
3) If flaring will continue more than 6 months, submit updated requests to flare to COGCC on Form 4 (Sundry Notice), which discusses timing to connect to sales line, plans to develop infrastructure, and justification for continued venting/flaring.
4) The operator is required to obtain and maintain any required air permits from CDPHE.
5) The venting or flaring volumes shall be reported by Form 7, Operator’s Monthly Report of Operations.
|
| Engineer | Form: (04) 400966006 02/16/2016 | 1) Venting or flaring of natural gas shall comply with COGCC Rule 912.
2) Submit requests to flare annually to COGCC on Form 4 (Sundry Notice), which discusses timing to connect to sales line, plans to develop infrastructure, and justification for continued venting/flaring. Provide gas analysis including H2S with each Sundry Notice.
3) Report flaring volumes on Form 7, Operator’s Monthly Report of Operations.
4) The operator is required to obtain and maintain any required air permits from CDPHE. The combustion device must comply with applicable design destruction efficiency for hydrocarbons (typically enclosed device 98%).
5) Notify the local emergency dispatch or the local governmental designee of natural gas flaring.
|
| Engineer | Form: (04) 401184117 04/25/2017 | 1) Venting or flaring of natural gas shall comply with COGCC Rule 912.
2) Submit requests to flare annually to COGCC on Form 4 (Sundry Notice), which discusses timing to connect to sales line, plans to develop infrastructure, and justification for continued venting/flaring. Provide gas analysis including H2S with each Sundry Notice.
3) Report flaring volumes on Form 7, Operator’s Monthly Report of Operations.
4) The operator is required to obtain and maintain any required air permits from CDPHE. The combustion device must comply with applicable design destruction efficiency for hydrocarbons (typically enclosed device 98%).
|
| Engineer | Form: (04) 401512735 10/04/2018 | 1) Flaring of natural gas shall comply with COGCC Rule 912.
2) Report metered volumes of gas flared on the Form 7, Operators Report of Monthly Operations.
3) Operator will use an enclosed combustion device with a 98% design destruction efficiency for hydrocarbons. Operator shall manage this well so that production volumes do not exceed combustor capacity.
4) Provide the local emergency dispatch or the local governmental designee prior notice of natural gas flaring by supplying them with a copy of the approved Sundry Notice and all attachments. Operator shall notify local government designee and emergency dispatch prior to flaring when flaring can be reasonably anticipated, or as soon as possible, but in no event more than two (2) hours after the flaring occurs.
5) Approval of this Sundry Notice applies to this well only.
6) Well completion practices in Rule 805.b.(3) shall apply to future well completions on this Oil and Gas Location. When commercial quantities of salable quality gas are achieved at any future well, the gas shall be immediately directed to a sales line, or shut in and conserved, or a variance from Rule 805.b.(3)C must be obtained to produce the well. The Rule 912 notice and approval requirements apply regardless of a variance from Rule 805.b.(3)C. |
| Engineer | Form: (04) 402105004 10/23/2020 | Presence of hydrogen sulfide should be reported on a Form 42, Field Operations Notice. |
| Engineer | Form: (04) 402105004 10/23/2020 | 1) Flaring of natural gas shall comply with COGCC Rule 912.
2) Submit requests to flare annually to COGCC on Form 4 (Sundry Notice), which discusses timing to connect to sales line, plans to develop infrastructure, and justification for continued venting/flaring. Provide gas analysis including H2S with each Sundry Notice.
3) Report metered flaring volumes on Form 7, Operator’s Monthly Report of Operations.
4) The operator is required to obtain and maintain any required air permits from CDPHE.
5) The expectation for permanent flares controlling separators will be an enclosed combustion device with a 98% design destruction efficiency for hydrocarbons. Operator shall manage this well so that production volumes do not exceed the combustor capacity.
6) Notify the local emergency dispatch or the local governmental designee of natural gas flaring.
|
| Engineer | Form: (04) 402839868 01/18/2022 | Must have an approved gas capture plan or variance approved by the Commission prior to January 15, 2022. Must be complete and provide all necessary details. Without prior approval - well is to be shut in and conserved until gas capture plan or variance is approved. |
| Engineer | Form: (04) 402526267 01/18/2022 | 1) Flaring of natural gas shall comply with COGCC Rule 912.
2) Submit requests to flare annually to COGCC on Form 4 (Sundry Notice), which
discusses timing to connect to sales line, plans to develop infrastructure, and
justification for continued venting/flaring. Provide gas analysis including H2S with each
Sundry Notice.
3) Report metered flaring volumes on Form 7, Operators Monthly Report of Operations.
4) The operator is required to obtain and maintain any required air permits from
CDPHE.
5) The expectation for permanent flares controlling separators will be an enclosed
combustion device with a 98% design destruction efficiency for hydrocarbons.
6) Notify the local emergency dispatch or the local governmental designee of natural
gas flaring.
|