COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
PermitForm: (02)
400420666
08/05/2013
Operator must meet water well testing requirements per Rule 318A.
EngineerForm: (02)
400420666
09/11/2013
1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU. 2) Comply with Rule 317.i and provide cement coverage from end of 7” casing to a minimum of 200' above Niobrara and from 200’ below and 200’ above Parkman . Verify coverage with cement bond log. 3) Comply with Rule 321. Run and submit Directional Survey from TD to base of surface casing. Ensure that the wellbore complies with setback requirements in commission orders or rules prior to producing the well.
EngineerForm: (02)
400420666
09/11/2013
Operator acknowledges the proximity of the listed wells. Operator agrees to provide mitigation Option 1 or 2 per the DJ Basin Horizontal Offset Policy, ensure all applicable documentation is submitted based on the selected mitigation option chosen, and submit a Form 42(s) (“OFFSET MITIGATION COMPLETED”) for the remediated wells, referencing the API Number of the proposed horizontal well(s) stating what appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well. Dinner #13-33 API #05-123-22370 Palser E. #14-23 API #05-123-22616 Schwisow E. #14-16 API #05-123-16126 Schwisow E. #14-09 API #05-123-16125 Dinner #14-32 API #05-123-21943 Dinner #14-31 API #05-123-21944 Dinner #1 API #05-123-10788 Dinner #15-43 API #05-123-20032 Mel Bickling #31-22 API #05-123-11059 Bickling E. #22-8 API #05-123-18788 Dinner #23-2 API #05-123-17767 Feit E. #23-5 API #05-123-17728 Feit E. #23-3 API #05-123-17727 Feit #2-23 EG API #05-123-12056 Ryan #1-26 EG API #05-123-07431
PermitForm: (02)
400420666
01/14/2014
Operator shall comply with Buffer Zone Move-In, Rig-Up Notice Policy dated 12-16-2013.
PermitForm: (02)
400420666
01/14/2014
Open hole resistivity and gamma logs shall be run to describe the stratigraphy of the entire well bore and to adequately verify the setting depth of surface casing and aquifer coverage. On a multi-well pad, these open hole logs are only required on one of the first wells drilled on the pad and the Form 5 for every well on the pad shall identify which well was logged.
EngineerForm: (02)
400420666
01/21/2014
Operator acknowledges the proximity of the listed non operated wells. Operator agrees to provide mitigation Option 1 or 2 per the DJ Basin Horizontal Offset Policy, ensure all applicable documentation is submitted based on the selected mitigation option chosen, and submit a Form 42(s) (“OFFSET MITIGATION COMPLETED”) for the remediated wells, referencing the API Number of the proposed horizontal well(s) stating what appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well. JR #1 API #05-123-12840 Benson #24-15 API #05-123-14705 Benson #13-15 API #05-123-12942 Willson #1-15 API #05-123-13327 Riggs #44-16 API #05-123-14480 Ole #21-24 API #05-123-23634 Ole #4-24 API #05-123-13239
EngineerForm: (02)
400420666
01/21/2014
Operator acknowledges the proximity of the listed non producing wells. Operator agrees to provide mitigation Option 3 per the DJ Basin Horizontal Offset Policy, ensure all applicable documentation is submitted based on the selected mitigation option chosen, and submit a Form 42(s) (“OFFSET MITIGATION COMPLETED”) for the remediated wells, referencing the API Number of the proposed horizontal well(s) stating what appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well. Bickling #1 API #05-123-13024 Dinner #15-1 API #05-123-10987 Dinner #15-2 API #05-123-11166 Mel Bickling #11-22 API #05-123-10719
EngineerForm: (04)
402956570
03/03/2022
This approval is good for one year and a new application must be made before March 2, 2023. Updates for the planned utilization of the well should be included with the application.
EngineerForm: (04)
402956570
03/03/2022
The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request.
EngineerForm: (04)
402956570
03/03/2022
Update production reporting from 10/21 to present to reflect TA status and not SI.
OGLAForm: (06)
403445247
07/06/2023
Due to proximity to a wetland, surface water, or expected shallow groundwater, operator will use secondary containment for all tanks and other liquid containers. Operator will implement stormwater BMPs and erosion control measures as needed to prevent sediment and stormwater runoff from entering the wetland and surface water.
OGLAForm: (06)
403445247
07/06/2023
Due to proximity of plugging and abandonment (P&A) operations to BUs, operator will comply with Table 423 Maximum Permissible Noise Levels for residential land use. Prior to initiating work, operator will install temporary sound walls, straw bales, or other BMPs to dampen noise if necessary for compliance.
OGLAForm: (06)
403445247
07/06/2023
Operator will implement measures to capture, combust, or control emissions to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public health, welfare and the environment. Due to the proximity of residential building units (RBUs) all blowdown gasses will be controlled.
OGLAForm: (06)
403445247
07/06/2023
Prior to commencing operations, the operator will post signs in conspicuous locations at intersections that will remain in place throughout the duration of the plug and abandonment activities. The signs will indicate plugging and abandonment operations are being conducted, the well name, well, and the applicable contact information. Signs will be placed so as not to create a potential traffic hazard.
OGLAForm: (06)
403445247
07/06/2023
3rd party wildlife surveys will be conducted on this well prior to rigging up for P&A activities. Should sensitive HPH conditions be identified during the screening process, Chevron will delay the work until conditions (nesting) clear and/or consult directly with CPW for guidance and discussion of potential mitigation measures that may be incorporated.
OGLAForm: (06)
403445247
07/06/2023
Notification will be given to any adjacent building unit occupants within a 1000 feet of the wellhead of planned P&A start date.
EngineerForm: (06)
403445247
07/06/2023
Prior to starting plugging operations a Bradenhead test shall be performed if there has not been a reported Bradenhead test within the 60 days immediately preceding the start of plugging operations. 1) If, before opening the Bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required. 2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required. The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the ECMC within three (3) months of collecting the samples.
EngineerForm: (06)
403445247
07/06/2023
1) Provide 2 business day notice of plugging MIRU via electronic Form 42, and provide 48 hours Notice of Plugging Operations, prior to mobilizing for plugging operations via electronic Form 42. These are 2 separate notifications, required by Rules 405.e and 405.I. 2) Prior to placing the 861’ plug: verify that all fluid migration (liquid and gas) has been eliminated. If evidence of fluid migration or pressure remains, contact ECMC Engineer for an update to plugging orders. 3) After isolation has been verified, pump surface casing shoe plug. If cement is not circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 611’ or shallower and provide 10 sx plug at the surface. 4) Leave at least 100’ of cement in the wellbore for each plug without mechanical isolation. 5) With the Form 6 SRA operator must provide written documentation which positively affirms each COA listed above has been addressed.
EngineerForm: (06)
403445247
07/06/2023
FLOWLINE AND SITE CLOSURE 1) Consistent with Rule 911.a, a Form 27 must be approved prior to cut and cap, conducting flowline abandonment, or removing production equipment. Allow 30 days for Director review of the Form 27; include the Form 27 document number on the Form 44 for offsite flowline abandonment (if applicable) and on the Form 6 Subsequent. 2) Properly abandon flowlines per Rule 1105. If flowlines will be abandoned in place, include with the Form 27: pressure test results conducted in the prior 12 months as well as identification of any document numbers for a ECMC Spill/Release Report, Form 19, associated with the abandoned line.
 
COGIS - Best Management Practice Results
BMP TypeSource DocumentBest Management Practices
General HousekeepingForm: (02 )
400420666
1/21/2014
Housekeeping will consist of neat and orderly storage of materials and fluids. Wastes will be temporarily stored in sealed containers and regularly collected and disposed of at offsite, suitable facilities. If spills occur prompt cleanup is required to minimize any commingling of waste materials with stormwater runoff. Routine maintenance will be limited to fueling and lubrication of equipment. Drip pans will be used during routine fueling and maintenance to contain spills or leaks. Any waste product from maintenance will be containerized and transported offsite for disposal or recycling. There will be no major equipment overhauls conducted onsite. Equipment will be transported offsite for major overhauls. Cleanup of trash and discarded materials will be conducted at the end of each work day. Cleanup will consist of patrolling the roadway, access areas, and other work areas to pickup trash, scrap debris, other discarded materials, and any contaminated soil. These materials will be disposed of properly.
Storm Water/Erosion ControlForm: (02 )
400420666
1/21/2014
Stormwater management plans (SWMP) are in place to address construction, drilling and operations associated with Oil & Gas development throughout the state of Colorado in accordance with Colorado Department of Public Health and Environment (CDPHE) General Permit No. COR-038637. BMP's will be constructed around the perimeter of the site prior to, or at the beginning of construction. BMP's used will vary according to the location, and will remain in place until the pad reaches final reclamation.
Material Handling and Spill PreventionForm: (02 )
400420666
1/21/2014
Spill prevention Control and Countermeasures (SPCC) plans are in place to address any possible spill associated with Oil & Gas operations throughout the state of Colorado in accordance with CFR 112.