| Pre-Construction | Form: (02 ) 400490507 11/21/2013 | The COGCC to be notified 48 hours prior to construction the Fresh Water Storage Pit. In addition, will obtain permit approval prior to constrution. |
| Storm Water/Erosion Control | Form: (02 ) 400490507 11/21/2013 | Operator has designed the well pad with insloping and a storm water control ditch to prevent sotm water run-on/runoff and release of fluids from the lcoation. See attached Construction Layout Drawing. |
| Material Handling and Spill Prevention | Form: (02 ) 400490507 11/21/2013 | Operator will ensure 110 percent secondary containment for any volume of fluids contaed at the well site during drilling and completion. Operator will implement best amangement practices to contain any unintentional release of fluids. Operator shall not allow any fluids to flow back to the Fresh Water Storage Pit/Pond. |
| Construction | Form: (02 ) 400490507 11/21/2013 | The location will be fenced and the fenced area will include the Fresh Water Storage Pit. |
| Drilling/Completion Operations | Form: (02 ) 400490507 11/21/2013 | Fresh water for the Fresh Water Storage Pit comes from water provider; Is trucked in. Water sources permitted for consumable industrial use. Fresh Water Storage Pit shall contain fresh water only and signage prohibiting theuse of the pit for any fluid that does not come from municipla, irrigation or surface water source.
Operator will implement interim relcation measures immediately after construction of the location to stabilize cut and fill slopes, stablize the topsoil and spoil stockpiles, establish desirable vegetation and control weeds on the location. |