Planning | Form: (02 ) 400476360 11/9/2013 | 604c.(2).Q. Guy Line Anchors: Should guy line anchors be left buried for future use, they shall be identified by a bright marker greater than four (4) feet high and no more than one (1) foot east of the guy line anchor. |
Planning | Form: (02 ) 400476360 11/9/2013 | 604c.(2).S. Access Roads: KMG will utilize the lease access road from WCR 4 for drilling operations and maintenance equipment. The road will be properly constructed and maintained to accommodate for local emergency vehicle access. |
Planning | Form: (02 ) 400476360 11/9/2013 | 604c.(2).V. Development From Existing Well Pads: KMG is developing three new reservoirs on an existing six-well well pad. |
Planning | Form: (02 ) 400476360 11/9/2013 | Kerr-McGee Oil & Gas Onshore LP (“KMG”) respectfully requests the Director to waive Rule 318A.m for this well. KMG is the operator of the encroached upon well(s). |
Planning | Form: (02 ) 400476360 11/9/2013 | Prior to drilling operations, Operator may perform an anti-collision review of existing offset wells that have the potential of being within close proximity of the proposed well. This anti-collision review may include MWD or gyro surveys and surface locations of the offset wells with included error of uncertainty per survey instrument, and compared against the proposed wellpath with its respective error of uncertainty. If current surveys do not exist for the offset wells, Operator may have gyro surveys conducted to verify bottomhole location. The proposed well may only be drilled if the anti-collision review results indicate that the risk of collision is sufficiently low as defined by the anti-collision plan, with separation factors greater than 1.5, or if the risk of collision has been mitigated through other means including shutting in wells, plugging wells, increased drilling fluid in the event of lost returns or as is appropriate for the specific situation. In the event of an increased risk of collision, that risk will be mitigated to prevent harm to people, the environment or property. For the proposed well, upon conclusion of drilling operations, an as-constructed directional survey will be submitted to COGCC with the Form 5. |
Traffic control | Form: (02 ) 400476360 11/9/2013 | 604c.(2).D. Traffic Plan: KMG will utilize Weld County roads to access the pad. No additional traffic plan was required and/or requested. |
General Housekeeping | Form: (02 ) 400476360 11/9/2013 | 604c.(2).O. Loadlines: All loadlines shall be bullplugged or capped. |
General Housekeeping | Form: (02 ) 400476360 11/9/2013 | 604c.(2).P. Removal of Surface Trash: A commercial size trash bin for removing debris will be located on site. This bin will be for use by all parties affiliated with the operation. |
Storm Water/Erosion Control | Form: (02 ) 400476360 11/9/2013 | 604c.(2).W. Site-specific Measures: KMG maintains a Stormwater Management Plan that includes each wellsite location that assesses erosion control for each well pad. This plan is updated every fourteen (14) days and after any major weather event. |
Material Handling and Spill Prevention | Form: (02 ) 400476360 11/9/2013 | 604c.(2).F. Leak Detection Plan: Automation technology will be utilized at this facility. This technology includes the use of fluid level monitoring for the tanks and produced water sumps, high-level shut offs, and electronic sensors to monitor the interstitial space of double-walled produced water sumps. All automation is monitored by Kerr-McGee’s Integrated Operations Center (IOC,) which is manned 24 hours per day, 7 days per week. |
Material Handling and Spill Prevention | Form: (02 ) 400476360 11/9/2013 | 604c.(2).N. Control of Fire Hazards: KMG will ensure that any material that might be deemed a fire hazard will be will remain no less than twenty-five (25) feet from the wellhead(s), tanks and separator(s). |
Construction | Form: (02 ) 400476360 11/9/2013 | 604c.(2).E. Multiwell Pads: This application is part of a nine-well pad (six existing, three new). |
Construction | Form: (02 ) 400476360 11/9/2013 | 604c.(2).G. Berm Construction: A geosynthetic liner will be laid under the tanks on this location and a metal containment will be constructed. |
Construction | Form: (02 ) 400476360 11/9/2013 | 604c.(2).M. Fencing Requirements: Per specific landowner request, no fencing will be installed or avoid interferng with farming operations. |
Construction | Form: (02 ) 400476360 11/9/2013 | 604c.(2).R. Tank Specifications: Condensate storage tanks will be designed, constructed and maintained pursuant to code 30 of the National Fire Protection Association. KMG will maintain written records to verify proper design. |
Noise mitigation | Form: (02 ) 400476360 11/9/2013 | 604c.(2).A. Noise: A sound mitigation burier (hay bales) will be placed on the north and west side of the pad location to damper noise during drilling and completions to the nearby Weld County Road 4 and 19.
Sound surveys have been conducted on each rig type; which is utilized to anticipate any additional noise mitigation if necessary.
|
Drilling/Completion Operations | Form: (02 ) 400476360 11/9/2013 | 604c.(2).B. Closed Loop Drilling System: A closed loop drilling system will be utilized during drilling of the wells on this location. |
Drilling/Completion Operations | Form: (02 ) 400476360 11/9/2013 | 604c.(2).C. Green Completions: KMG will install Vapor Recovery Unit(s) (VRU’s) to prevent uncontrolled venting of flash gas. Environmental Control Devices (ECD) will be used to control working and breathing vapor losses for oil and water tanks. Produced oil and gas will be piped off of location to minimize air pollution. |
Drilling/Completion Operations | Form: (02 ) 400476360 11/9/2013 | 604c.(2).H. BOPE: Our rigs at a minimum will have a double ram with blind and pipe ram; and annular preventer. |
Drilling/Completion Operations | Form: (02 ) 400476360 11/9/2013 | 604c.(2).I. BOPE Testing for Drilling Operations: Upon initial rig-up, BOPE’s will be tested at a minimum of every 30-days. |
Drilling/Completion Operations | Form: (02 ) 400476360 11/9/2013 | 604c.(2).J. BOPE for Well Servicing Operations: Blowout prevention equipment will be used on any servicing operations associated with this well.
Backup stabbing valves will be used during any future servicing operations during reverse circulation. Valves shall be pressure tested before each well servicing operation using low-pressure air and high-pressure fluid.
|
Drilling/Completion Operations | Form: (02 ) 400476360 11/9/2013 | 604c.(2).K. Pit Level Indicators:
All mud pits contain pit level monitors with Electronic Drilling Recorders (EDR)
KMG uses an Electronic Drilling Recorder (EDR) with pit level monitor(s) and alarm(s) for production rigs. Basic level gages are used on pits utilized for the surface rig.
|
Drilling/Completion Operations | Form: (02 ) 400476360 11/9/2013 | 604c.(2).L. Drill Stem Tests: No drill stem tests will be performed without prior approval from the director. |
Drilling/Completion Operations | Form: (02 ) 400476360 11/9/2013 | Kerr McGee acknowledges and will comply with the COGCC Policy for Bradenhead Monitoring during Hydraulic Fracturing Treatments in the Greater Wattenberg Area dated May 29, 2012. |
Final Reclamation | Form: (02 ) 400476360 11/9/2013 | 604c.(2).T. Well Site Cleared: The wellsite will be cleared of all non-essential equipment within ninety (90) days after all wells associated with the pad have been plugged and abandoned. |