Skip to Main Content

COGIS DB

 
Facility TypeFacility ID/
API
Facility Name/
Number
Operator Name/
Number
StatusField Name/
Number
LocationLocation IDRelated Facilities
WELL05-123-38313WARDELL
4G-7HZ
KERR MCGEE OIL & GAS ONSHORE LP
47120
PA
7/7/2022
WATTENBERG
90750
WELD  123
LOT4 7 3N65W 6
434750View Related
 
COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
PermitForm: (02)
400447393
08/16/2013
Operator must meet water well testing requirements per Rule 318A.
EngineerForm: (02)
400447393
09/27/2013
1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU. 2) Comply with Rule 317.i and provide cement coverage from end of 7” casing to a minimum of 200' above Niobrara. Verify coverage with cement bond log. 3) Comply with Rule 321. Run and submit Directional Survey from TD to base of surface casing. Ensure that the wellbore complies with setback requirements in commission orders or rules prior to producing the well.
EngineerForm: (02)
400447393
09/27/2013
Operator acknowledges the proximity of the HSR-Prinvale #12-7A API #123-15103, HSR-Rewank #4-7A API #123-15027, HSR-Niall #13-7 API #123-15044, HSR-Gromalla #5-7 API #123-15043, HSR-Roeder #14-7A API #123-15064, HSR-Oberkfell #6-7A API #123-15094, HSR-Cook #11-7A API #123-15072, HSR-Harland #3-7A API #123-15045, HSR_Frey #13-6 API #123-15009, Bell L #12-16 API #123-15718, Bell L #12-1 API #123-15703, and the Bell L #12-9 API #123-15711 wells; Operator agrees to: provide mitigation option 1 or 2 (per the DJ Basin Horizontal Offset Policy) to mitigate the situation, ensure all applicable documentation is submitted based on the selected mitigation option chosen, and submit a Form 42 (“OTHER – AS SPECIFIED BY PERMIT CONDITION”) stating what appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well.
EngineerForm: (04)
402186292
10/23/2019
Shut in bradenhead pressure shall not exceed 50 psig.
EngineerForm: (04)
402186292
10/23/2019
1. Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well operations do not constitute a nuisance or hazard to public welfare. 2. Prior to starting bradenhead abatement, if a sample has not been collected within the last twelve months collect bradenhead and production gas samples for laboratory analysis. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions, Appendix A: Liquid and Gas Sampling. Copies of all final laboratory analytical results shall be provided to the COGCC within three months of collecting the samples. 3. Bradenhead gas is not to be vented to atmosphere; any gas from the Bradenhead will be routed to an enclosed tank and/or combustor. Operator shall implement measures to get an initial estimate of the gas flow rate and/or volume from the bradenhead. The abatement program may be used for six consecutive months. 4. Operator will submit a Form 42 (“OTHER”) stating that “bradenhead abatement program has started.” 5. At the conclusion of the six months, conduct a new bradenhead test and submit the Form 17 within ten days of the test and submit a Form 4 Sundry that summarizes current well condition. The sundry should include details of the future plans and the flow rate information and pressure data.
EngineerForm: (04)
402508171
10/13/2020
1. Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well operations do not constitute a nuisance or hazard to public welfare. 2. Bradenhead gas is not to be vented to the atmosphere; any gas from the Bradenhead will be routed to the specified abatement system. Shut in bradenhead pressure shall not exceed 50 psig. Operator shall implement measures to get an estimate of the gas flow rate and/or volume from the bradenhead. 3. Within thirty days of 10/12/2021, submit a Form 4 Sundry that summarizes current well condition. The sundry should include details of the future plans, sample analysis interpretation, bradenhead test description, and the flow rate information and pressure data. 4. Shut well in for at least seven days to monitor build up pressures then conduct a new bradenhead test and submit the Form 17 within ten days of the test. 5. Collect production gas samples for laboratory analysis. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions, Appendix A: Liquid and Gas Sampling. Copies of all final laboratory analytical results shall be provided to the COGCC within three months of collecting the samples.
EngineerForm: (04)
402893503
12/22/2021
1. Operator will implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well operations do not constitute a nuisance or hazard to public welfare. 2. Bradenhead gas is not to be vented to the atmosphere; any gas from the Bradenhead will be routed to an enclosed tank and/or combustor. Shut in bradenhead pressure shall not exceed 50 psig. Operator will implement measures to get an estimate of the gas flow rate and/or volume from the bradenhead. 3. Within thirty days of 11/04/2022, conduct a bradenhead test, submit a Form 17, and submit a Form 4 Sundry that summarizes current well condition. The sundry should include details of the future plans, sample analysis interpretation, bradenhead test description, and the flow rate information and pressure data. 4. Shut well in for at least seven days to monitor build up pressures then conduct a new bradenhead test and submit the Form 17 within ten days of the test. 5. If a sample has not been collected from surface casing within the last twelve months collect bradenhead gas samples for laboratory analysis. Sampling will comply with Operator Guidance - Bradenhead Testing and Reporting Instructions, Appendix A: Liquid and Gas Sampling. Copies of all final laboratory analytical results will be provided to the COGCC within three months of collecting the samples.
OGLAForm: (06)
402976094
03/16/2022
Operator will implement measures to capture, combust, or control emissions to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public health, welfare and the environment.
EngineerForm: (06)
402976094
03/21/2022
Prior to starting plugging operations a bradenhead test shall be performed if there has not been a reported bradenhead test within the 60 days immediately preceding the start of plugging operations. 1) If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required. 2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required. The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the COGCC within three (3) months of collecting the samples. If there is a need for sampling, contact COGCC engineering for verification of plugging procedure.
EngineerForm: (06)
402976094
03/21/2022
1) Provide electronic Form 42 Notice of MIRU 2 business days ahead of operations and electronic Form 42 Notice of Plugging Operations 48 hours prior to mobilizing for plugging operations. 2) After placing the shallowest hydrocarbon isolating plug (4434'), operator must wait a sufficient time to confirm static conditions. If at any time after placing this plug there is evidence of pressure or of fluid migration, contact COGCC engineering before continuing operations. 3) Prior to placing the 1425’ plug: verify that all fluid migration (liquid and gas) has been eliminated. If evidence of fluid migration or pressure remains, contact COGCC Engineer for an update to plugging orders. 4) After isolation has been verified, pump plug and displace. If cement is not circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 1274’ or shallower and provide 10 sx plug at the surface. 5) Leave at least 100’ of cement in the wellbore for each plug. 6) Properly abandon flowlines as per Rule 1105. Pursuant to Rule 911.a. Closure of Oil and Gas Facilities, Operator will submit Site Investigation and Remediation Workplans via Form 27 for COGCC prior approval before cutting and capping the plugged well, conducting flowline abandonment, and removing production equipment. Pursuant to Rule 1105.f. Abandonment Verification, within 90 days of an operator completing abandonment requirements for a flowline or crude oil transfer line, an operator must submit a Field Operations Notice, Form 42-Abandonment of Flowlines for on-location flowlines, or a Flowline Report, Form 44, for off-location flowlines or crude oil transfer lines. 7) With the Form 6 SRA operator must provide written documentation which positively affirms each COA listed above has been addressed.
EngineerForm: (06)
402976094
04/01/2022
Operator will run cased hole pulsed neutron and gamma ray logs - submit to COGCC for verification of plugging orders prior to continuing plugging operations.
EngineerForm: (04)
403226740
11/18/2022
1. Operator will implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well operations do not constitute a nuisance or hazard to public welfare. 2. Bradenhead gas is not to be vented to the atmosphere; any gas from the Bradenhead will be routed to an enclosed tank and/or combustor. Shut in bradenhead pressure shall not exceed 50 psig. Operator will implement measures to get an estimate of the gas flow rate and/or volume from the bradenhead. 3. Within thirty days of 11/11/2023, conduct a bradenhead test, submit a Form 17, and submit a Form 4 Sundry that summarizes current well condition. The sundry should include details of the future plans, sample analysis interpretation, bradenhead test description, and the flow rate information and pressure data. 4. Shut well in for at least seven days to monitor and collect data to characterize build up pressures then conduct a new bradenhead test and submit the Form 17 within ten days of the test. 5. If a sample has not been collected from surface casing within the last twelve months collect bradenhead and production gas samples for laboratory analysis. Sampling will comply with Operator Guidance - Bradenhead Testing and Reporting Instructions, Appendix A: Liquid and Gas Sampling. Copies of all final laboratory analytical results will be provided to the COGCC within three months of collecting the samples.
 
COGIS - Best Management Practice Results
BMP TypeSource DocumentBest Management Practices
Drilling/Completion OperationsForm: (02 )
400447393
10/17/2013
Prior to drilling operations, Operator may perform an anti-collision review of existing offset wells that have the potential of being within close proximity of the proposed well. This anti-collision review may include MWD or gyro surveys and surface locations of the offset wells with included error of uncertainty per survey instrument, and compared against the proposed wellpath with its respective error of uncertainty. If current surveys do not exist for the offset wells, Operator may have gyro surveys conducted to verify bottomhole location. The proposed well may only be drilled if the anti-collision review results indicate that the risk of collision is sufficiently low as defined by the anti-collision plan, with separation factors greater than 1.5, or if the risk of collision has been mitigated through other means including shutting in wells, plugging wells, increased drilling fluid in the event of lost returns or as is appropriate for the specific situation. In the event of an increased risk of collision, that risk will be mitigated to prevent harm to people, the environment or property. For the proposed well, upon conclusion of drilling operations, an as-constructed directional survey will be submitted to COGCC with the Form 5. At the time of permitting, the operator has identified the following well(s) as being within close proximity of the proposed well: HSR PRINVALE 12-7A
Drilling/Completion OperationsForm: (02 )
400447393
10/17/2013
Kerr McGee acknowledges and will comply with the COGCC Policy for Bradenhead Monitoring during Hydraulic Fracturing Treatments in the Greater Wattenberg Area dated May 29, 2012.