| Permit | Form: (02) 400464222 08/23/2013 | Right to construct is the lease. Bonding is filled. The well name appears to have changed since the exception location was approved. Please make a comment that the well name has changed and attach the request letter and waiver which you already have in your possesion. Directional template not loaded into the directional tool. |
| Engineer | Form: (02) 400464222 09/10/2013 | 1) Provide 48 hour notice prior to spud via electronic Form 42.
2) Provide cement coverage to a minimum of 200' above Niobrara. Verify coverage with
cement bond log.
3) Run and submit Directional Survey from TD to base of surface casing. Ensure that
the wellbore complies with setback requirements in commission orders or rules prior to
producing the well. |