COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
EngineerForm: (02)
400445605
09/13/2013
1) Note surface casing depth change from 1000’ to 1250’. Increase cement volumes accordingly. 2) Submit Form 42 electronically to COGCC 48 hours prior to MIRU. 3) Comply with Rule 317.i and provide cement coverage from end of 7” casing to a minimum of 200' above Niobrara. Verify coverage with cement bond log. 4) Comply with Rule 321. Run and submit Directional Survey from TD to base of surface casing. Ensure that the wellbore complies with setback requirements in commission orders or rules prior to producing the well.
EngineerForm: (02)
400445605
09/13/2013
Operator acknowledges the proximity of the non-operated 1 Mathews API # 123-07177 well. Operator assures that this offset will be remediated per the DJ Basin Horizontal Offset Policy (options 1,2 or 3) or operator will address this well with mitigation option 4. Operator will submit a Form 42 (“OTHER – AS SPECIFIED BY PERMIT CONDITION”) stating what appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well.
 
COGIS - Best Management Practice Results
BMP TypeSource DocumentBest Management Practices
Drilling/Completion OperationsForm: (02 )
400445605
9/27/2013
Prior to drilling operations, Operator may perform an anti-collision review of existing offset wells that have the potential of being within close proximity of the proposed well. This anti-collision review may include MWD or gyro surveys and surface locations of the offset wells with included error of uncertainty per survey instrument, and compared against the proposed wellpath with its respective error of uncertainty. If current surveys do not exist for the offset wells, Operator may have gyro surveys conducted to verify bottomhole location. The proposed well may only be drilled if the anti-collision review results indicate that the risk of collision is sufficiently low as defined by the anti-collision plan, with separation factors greater than 1.5, or if the risk of collision has been mitigated through other means including shutting in wells, plugging wells, increased drilling fluid in the event of lost returns or as is appropriate for the specific situation. In the event of an increased risk of collision, that risk will be mitigated to prevent harm to people, the environment or property. For the proposed well, upon conclusion of drilling operations, an as-constructed directional survey will be submitted to COGCC with the Form 5.
Drilling/Completion OperationsForm: (02 )
400445605
9/27/2013
Kerr McGee acknowledges and will comply with the COGCC Policy for Bradenhead Monitoring during Hydraulic Fracturing Treatments in the Greater Wattenberg Area dated May 29, 2012.
PlanningForm: (04 )
403270905
1/9/2023
Site lighting will be shielded and directed downward and inward toward operations to avoid glare on public roads and nearby Building Units.
Community Outreach and NotificationForm: (04 )
403270905
1/9/2023
Signs will be placed in conspicuous locations and will include Oxy contact information; the Oxy Stakeholder Relations team will respond to all community member inquiries. The signs will be placed so as not to create a potential traffic hazard
Community Outreach and NotificationForm: (04 )
403270905
1/9/2023
Courtesy notifications will be sent to all parcel owners with building units within 1,500 feet of the location letting them know about our subsequent well operations and providing contact information for Kerr McGee’s response line and online resources.
WildlifeForm: (04 )
403270905
1/9/2023
This location was reviewed using a desktop method to review publicly available wildlife data (including CPW & COGCC data) as well as internal wildlife datasets and aerial imagery. All field personnel are trained to identify wildlife risks and raise concerns noticed during operations with the KMOG Health, Safety, and Environment (HSE) department.
Dust controlForm: (04 )
403270905
1/9/2023
Water will be placed on dirt access roads to mitigate dust as needed.
Noise mitigationForm: (04 )
403270905
1/9/2023
Noise associated with pipe handling, traffic, and other operational activity will be minimized between 7:00 pm and 7:00 am. Based off the rig sound signature, rig orientation will be considered to reduce noise levels to nearby building units.